Week 4 - Project Schedule Management - AO
Week 4 - Project Schedule Management - AO
Scheduling
Name: Ayomide Okunlola
Title: MGMT 183 - Project Planning and Scheduling
Instructor – Ayomide Okunlola
[email protected]
Week #3 - Winter Semester, January 2023
Project Schedule Management
o The processes:
o Define Activities – Week 3 Topic
o Sequence Activities
o Estimate Activity Durations
o Develop Schedule
o Control Schedule
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 173-230
PLAN SCHEDULE MANAGEMENT ITTO
Tools & Techniques
• Project charter
• Project management plan
• Scope management plan
• Development approach Inputs Outputs • Schedule management plan
Expert judgment
• Organizational process assets
Data analysis
• Enterprise environmental factors
Meetings
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 179
• Activity list
• Project management plan
• Activity attributes
• Schedule management plan
• Scope baseline • Milestone list
Expert judgment
• Enterprise environmental factorsInputs Outputs • Change requests
Decomposition
• Organizational process assets • Project management plan
Rolling wave planning updates
– Schedule baseline
Meetings – Cost baseline
Estimate
Plan Schedule Define Sequence Develop Control
Activity
Management Activities Activities Schedule Schedule
Durations
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017. Page 183
Project schedules grow out of the basic documents that initiate a project. The
project charter often mentions planned project start and end dates, which serve as
the starting points for a more detailed schedule. The project manager starts with the
project charter and then develops a project scope statement and WBS. Using this
information with the scope statement, WBS, WBS dictionary, project management
plan, and other related information, the project team begins to develop a schedule
1. PROJECT MANAGEMENT PLAN components include but are not limited to:
a) Schedule management plan - Defines the schedule methodology, the duration of waves
for rolling wave planning, and the level of detail necessary to manage the work
b) Scope baseline - The project WBS, deliverables, constraints, and assumptions documented
in the scope baseline are considered explicitly while defining activities
DEFINE ACTIVITIES: INPUTS
3. ENTERPRISE ENVIRONMENTAL FACTORS that can influence the Plan Define
Activities process include but are not limited to:
a. Organizational culture and structure
b. Published commercial information from commercial databases, and
c. Project management information system (PMIS).
2. DECOMPOSITION
Decomposition is a technique used for dividing and subdividing the project scope and project
deliverables into smaller, more manageable parts. Activities represent the effort needed to
complete a work package. The Define Activities process defines the final outputs as activities rather
than deliverables, as done in the Create WBS process. The activity list, WBS, and WBS dictionary
can be developed either sequentially or concurrently, with the WBS and WBS dictionary used as the
basis for development of the final activity list. Each work package within the WBS is decomposed
into the activities required to produce the work package deliverables. Involving team members in
the decomposition can lead to better and more accurate results.
DEFINE ACTIVITIES: TOOLS AND
TECHNIQUES
3. ROLLING WAVE PLANNING
Rolling wave planning is an iterative planning technique in which the work to be
accomplished in the near term is planned in detail, while work further in the future is
planned at a higher level.
It is a form of progressive elaboration applicable to work packages, planning packages, and
release planning when using an agile or waterfall approach. Therefore, work can exist at
various levels of detail depending on where it is in the project life cycle. During early strategic
planning when information is less defined, work packages may be decomposed to the known
level of detail. As more is known about the upcoming events in the near term, work packages
can be decomposed into activities.
4. MEETINGS
Meetings may be face-to-face, virtual, formal, or informal. Meetings may be held with team
members or subject matter experts to define the activities needed to complete the work.
DEFINE ACTIVITIES: OUTPUTS
1. ACTIVITY LIST
The activity list includes the schedule activities required on the project. For projects that use rolling
wave planning or agile techniques, the activity list will be updated periodically as the project
progresses. The activity list includes an activity identifier and a scope of work description for each
activity in sufficient detail to ensure that project team members understand what work is required
to be completed.
2. ACTIVITY ATTRIBUTES
Activity attributes extend the description of the activity by identifying multiple components
associated with each activity. The components for each activity evolve over time. During the initial
stages of the project, they include the unique activity identifier (ID), WBS ID, and activity label or
name. When completed, they may include activity descriptions, predecessor activities, successor
activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints,
and assumptions. Activity attributes can be used to identify the place where the work has to be
performed, the project calendar the activity is assigned to, and the type of effort involved. Activity
attributes are used for schedule development and for selecting, ordering, and sorting the planned
schedule activities in various ways within reports.
DEFINE ACTIVITIES: OUTPUTS
3. MILESTONE LIST
A milestone is a significant point or event in a project. A milestone list identifies all project
milestones and indicates whether the milestone is mandatory, such as those required by
contract, or optional, such as those based on historical information. Milestones have zero
duration because they represent a significant point or event
4. CHANGE REQUESTS
Once the project has been baselined, the progressive elaboration of deliverables into
activities may reveal work that was not initially part of the project baselines. This may result
in a change request. Change requests are processed for review and disposition through the
Perform Integrated Change Control process
DEFINE ACTIVITIES: OUTPUTS
Kristin and her team developed dozens of activities that would be used later for
creating the project schedule. The image above provides an example of how they
reviewed a work package, “Report on pilot course,” and developed a
list of activities required to build that work package. Note that unlike the
deliverables described within the WBS, which are listed as nouns, activities are
all listed using a verb and then a noun, using verbs such as review, create,
develop, interview, write, distribute, and analyze.
Thank you!
FlemingCollegeToronto.ca
Recap from Week 2
MS Project
MS Project is a tool to help you to plan projects,
manage and update project information, and
communicate the status once the project is
under way.
• The details of the project tasks and associated
resources are entered into the system as a new
project.
• The system will then display the data in such a way
that the relationships of the tasks and their time
scales can clearly be seen and potential problem
areas identified.
Understanding Project Management
In the illustration two tasks have a relationship. Task A is the predecessor task, and Task B is
the successor task. Both of these tasks are considered to be non-critical because they both
have flexibility. Let’s focus on Task A. EA marks the earliest possible time Task A can start. SS
marks the scheduled start time for Task A. By default, all tasks are scheduled to start at the
earliest possible time, unless you specify otherwise.
MS Project Creating Tasks
Building a task list
• Tasks are the most basic building blocks of any project’s plan.
• They represent the work to be done to accomplish the goals of the project.
• Tasks describe work in terms of dependencies, duration, and resource requirements.
• Summary tasks, subtasks, and milestones - generally called activities or work packages.
• On this topic:
• Creating tasks, entering task durations and dates, entering milestone tasks, creating summary
tasks, linking tasks to create dependencies, switching task scheduling from manual to automatic,
checking a plan’s duration and finish date, and documenting task information.
• Every task in a plan is given an ID number, but the number does not necessarily represent the
order in which tasks occur.
• Every task in Project has one of two scheduling modes that controls how the task is scheduled:
• Manual (the default) or Automatically scheduled.
Naming Tasks
• Develop good practices about how you name tasks in your plans.
• Task names should be recognizable and make sense to those who will perform the tasks and to other
stakeholders who will read the task names.
• Use short verb phrases that describe the work to be done, such as “Edit manuscript.”
• Use descriptive phrases that communicate the required work and make sense to you and others who will
perform the work or review the plan.
• If tasks will be organized into an outline, don’t repeat details from the summary task name in the
subtask name unless it adds clarity.
• If tasks will have resources assigned to them, don’t include resource names in the task names.
• You can edit task names later - don’t have to be exactly right when you’re initially entering them into
a plan.
Enter task durations and dates
• A task’s duration represents the amount of time you expect it will take to
complete the task.
• Project can work with task durations that range from minutes to months.
• Depending on the scope of your plan, you’ll probably want to work with task durations on the
scale of hours, days, and weeks.
• Project uses standard values for minutes and hours for durations:
• 1 minute equals 60 seconds, and 1 hour equals 60 minutes.
• For the durations of days, weeks, and months, you can use Project’s defaults (for
example, 20 days per month) or define your own values in the Project Options
dialog box.
Manage time-related settings
• Assume that a plan has a project calendar with working time defined as 8:00 A.M.
through 5:00 P.M., with one hour off for lunch breaks, Monday through Friday,
leaving nonworking time defined as evenings (after 5:00 P.M.) and weekends.
• If you estimate that a task will take 16 hours of working time, you could enter its duration as 2d to
schedule work over two 8-hour workdays.
• You should then expect that starting the task at 8:00 A.M. on a Friday means that it will not be
completed until 5:00 P.M. on the following Monday.
• No work would be scheduled over the weekend because Saturday and Sunday have been defined as
nonworking time.
• We shall use default values: 8 hours per day, 40 hours per week, and 20 days per month.
Time formats
• You could schedule tasks to occur during nonworking and working time.
• To do this, enter an elapsed duration to a task. You enter elapsed duration by preceding the duration
abbreviation with an e.
• You might use an elapsed duration for a task that goes on continuously rather than just
during normal working hours.
• For instance, a construction project might have the tasks Pour foundation concrete and Remove
foundation forms.
• Create a task called Wait for concrete to cure, because you don’t want to remove the forms until the concrete has cured. The task
Wait for concrete to cure should have an elapsed duration because the concrete will cure over a contiguous range of days,
whether they are working or nonworking days. If the concrete takes 48 hours to cure, you can enter the duration for that task as
2ed, schedule the task to start on Friday at 9:00 A.M., and expect it to be complete by Sunday at 9:00 A.M.
Enter milestone tasks
• In addition to entering tasks to be completed, you might want to account for an
important event for your project’s plan, such as the end of a major phase of the project.
• Create a milestone task.
• Examples –
• Completion of a phase of work
• Imposed upon the plan - such as a deadline by which to apply for funding.
• Because the milestone itself doesn’t normally include any work, milestones are normally
represented as tasks with zero duration.
• To visually distinguish milestones, their Gantt chart symbol appears as a diamond rather
than a bar.
• You can flag any task of any duration as a milestone.
Creating summary tasks
• A summary task is made up of and summarizes the subtasks indented below it in
the plan’s outline.
• When the summary tasks are sequenced over time, the highest-level summary tasks
are called phases.
3. To delete a task
FlemingCollegeToronto.ca