0% found this document useful (0 votes)
22 views

Project Analysis and Management

The document discusses project analysis and management. It defines what a project is, outlines common features of projects, and distinguishes between projects, programs, plans and policies. It also discusses the project cycle and different approaches to project planning.

Uploaded by

kedir Jemal
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views

Project Analysis and Management

The document discusses project analysis and management. It defines what a project is, outlines common features of projects, and distinguishes between projects, programs, plans and policies. It also discusses the project cycle and different approaches to project planning.

Uploaded by

kedir Jemal
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 173

Project Analysis and Management

MSc Hargeisa University

01.04.2024 Prepared by Kedir 1


What is project?
• Projects can be of any size and duration.
• A project is a means of moving from a problem to a solution via a
series of planned activities.
• A project has a definite beginning and end.
• Projects consist of several activities.
• Two essential features are present in every project no matter how
simple or complicated they are:

– All projects must be planned out in advance


– The execution of the project must be controlled

01.04.2024 Prepared by Kedir 2


What is a project?...
• A project is a multitask job with a definite starting point, definite
ending point, a clearly defined scope of work, a budget, and
usually a temporary team.

 A project is not a repetitive activity.

• A project is a problem scheduled for solution.

 This definition makes us to realize that a project is conducted to


solve a problem.

01.04.2024 Prepared by Kedir 3


Common features of a project

 Involves the investment of scarce resources in expectation of future


benefits

 An activity that is capable of being planned, financed and


implemented

 Has a defined set of objectives

 Has specific start and end dates

 Has a well-defined sequence of investment and production activities,

01.04.2024 Prepared by Kedir 4


Cont…
 Involves risk and uncertainty
 Has geographical or organizational
boundaries
 It is an activity around which conceptual
boundaries can be ascribed.
 It is likely to have a partially or wholly
independent administration.

01.04.2024 Prepared by Kedir 5


Projects, programmes, plans, policies
• Projects are usually the smallest unit of development
programmes and plans
– Concrete manifestation of the development plans in a specific time and
place.

• Programmes are planned continuous or ongoing development and


investment activities that are not generally time bound.
 The major difference between a project and a program is not so
much in objectives but lies more in scope, the details and the
accuracy.

01.04.2024 Prepared by Kedir 6


Cont…
• Policy: a definite course or method of action selected (by
gov’t, institutions, groups or individuals) from among
alternatives and in the light of given conditions to guide and,
usually, to determine present and future decisions.

• It is a set of coherent decisions with a common long-term


purpose (s).

 Livestock policy for example:


A coherent set of decisions with a common long-term
objective (s) affecting or relevant to the livestock
subsector.

01.04.2024 Prepared by Kedir 7


Cont…

• Policies are usually national policies (not district or


provincial) and are not necessarily limited in time:

 one does not usually speak in terms of “ 2-year


policies” as one does of “2-year project” or “5-year
plans”

01.04.2024 Prepared by Kedir 8


Cont…
Elements in policy
• It is always helpful to distinguish between two elements which
are essential part of any policy:

– Policy objectives
• the “ends” of a policy
• reflect the overall purpose or long-term aim (s)
• Are what the policy intended to achieve

Example: more beef export or fairer access to grazing


lands

01.04.2024 Prepared by Kedir 9


Cont…
– Policy instruments

• Are the “means” of a policy


• The actions used to carry it out
• The methods by which its objectives are achieved

Example: import tariffs on dairy products or a


subsidy on an artificial insemination service

01.04.2024 Prepared by Kedir 10


PROJECT

• Implementing development programs via project is the most


challenging problem.

• There are many critical issues for such challenges:


Poor project preparation
Selecting priority areas for investment,
Designing effective price policies, and
Mobilizing resources

01.04.2024 Prepared by Kedir 11


Cont…
 Careful project preparation is the best available means

– To ensure efficient, and economic use of capital funds and


– To increase the chances of implementation on schedule

• The capacity to prepare and analyze projects lags.

01.04.2024 Prepared by Kedir 12


Cont…
• Successful project management can then be defined as having
achieved the project objectives:

– Within time
– Within cost
– At the desired performance/technology level
– Utilized the assigned resources effectively and efficiently
– Accepted by the customer/ beneficiaries

01.04.2024 Prepared by Kedir 13


The potential benefits of project management are:

• Identification of functional responsibilities to ensure that all


activities are accounted for, regardless of personnel turnover

• Minimizing the need for continuous reporting

• Identification of time limits for scheduling

• Identification of a methodology for trade-off analysis

01.04.2024 Prepared by Kedir 14


Cont…
• Measurement of accomplishment against plans

• Early identification of problems so that corrective


action may follow

• Improved estimating capability for future


planning

• Knowing when objectives cannot be met or will


be exceeded
01.04.2024 Prepared by Kedir 15
Obstacles of project management

• Project complexity
• Customer's/beneficiary’s special requirements and scope
changes
• Project risks
• Changes in technology
• Forward planning and pricing

01.04.2024 Prepared by Kedir 16


Defining project management?

• Project management is the:


– planning,
– organizing,
– directing, and controlling of project
resources

01.04.2024 Prepared by Kedir 17


Cont….
• Classical management is usually considered to have five
functions
or principles:
– Planning
– Organizing
– Staffing
– Controlling
– Directing
• We should also comment on what is meant by a "relatively"
short-term project.

01.04.2024 Prepared by Kedir 18


Approaches to project planning

The different approaches for project planning include:

a) Top-bottom – Centralized
 focus on national realities
 Participation as a means
b) Bottom- up – Grass root communities
 People Centered
Participation as a end

01.04.2024 Prepared by Kedir 19


Approaches to project planning…

c) Participatory – Blended

 It balance by taking into account both national and grass root


community level realities in project planning

01.04.2024 Prepared by Kedir 20


Data Riquired
a) Demographic data
– Target population
– Household characteristics
– Gender issue
– Age group and dependency ratio
– Cross-cutting issues

01.04.2024 Prepared by Kedir 21


Cont…
b) Economic data
• Non farm data
• Input and output coefficient
• Sectoral, regional, national & international prices

c) Political Stability, good governance and democracy

01.04.2024 Prepared by Kedir 22


Project Analysis and
Management
CH-2
The Project cycle

01.04.2024 Prepared by Kedir 23


Project Cycle
• The way in which projects are planned and carried out follows a
sequence that has become known as the project cycle
 The cycle starts with the identification of an idea and develops
that idea into a working plan that can be implemented and
evaluated.
• In operational terms each stage in the project cycle can be
understood as leading to a decision point.

 The project cycle is thus interactive in nature

01.04.2024 Prepared by Kedir 24


Cont…

• The details of what occurs during each phase differ between


institutions, reflecting differences in procedures.
 Within all institutions the cycle shares three common themes:

1) The cycle defines the key decisions, information requirements and


responsibilities at each phase.

2) The phases in the cycle are progressive – each phase needs to be


completed for the next to be tackled with success.

3) The cycle draws on evaluation to build experience from existing


projects into the design of future programmes and projects.

01.04.2024 Prepared by Kedir 25


Cont…
• There are several models of project cycle but the most
important ones are:
Traditional approach
Process approach
The Asian Development Bank project cycle
The Integrated project planning & magm’t cycle
(IPPMC)
The United Nation Industrial Development
Organization (UNIDO) project cycle

01.04.2024 Prepared by Kedir 26


Cont…
• The first two are the models of the World Bank

• The most popular model is the traditional version of the WB


developed in 1970 with four stages and in 1978 transformed to 5
levels and known as Baum Project Cycle Model
• The process approach of the WB (the new approach) was
developed in 1994.
• Emphasis on the issue of participation

• Particularly relevant to projects where beneficiary


participation is critical.

01.04.2024 Prepared by Kedir 27


Traditional project cycle (the Blueprint Approach)

Evaluation – added after 1978 and involves ex-post


evaluation

Identification

Evaluation Preparation

Implementation Appraisal

01.04.2024 Prepared by Kedir 28


The Process Approach Project Cycle
Process Approach of the World Bank has four stages: listening,
piloting , demonstration and mainstreaming

Listening

Mainstreaming Piloting

Demonstrating

01.04.2024 Prepared by Kedir 29


Cont…
• Listening
 Making the project idea or concept originate
• From local communities and other project beneficiaries
• On the needs and priorities of the community
 Piloting:
• Starting small-scale projects with trials of different
techniques in a holistic approach

01.04.2024 Prepared by Kedir 30


Cont…
• Demonstrating:
• Conducting trials on representative scale (eg. village,
kebele ) through joint participation.

• Mainstreaming:
– This is the process of extending the project to a larger scale (eg.
District, region, etc).

01.04.2024 Prepared by Kedir 31


The Integrated Project Planning and Management Cycle
(IPPMC)

• Developed to clarify the procedures of project planning and


implementation

• Four major phases


– Phase I - Planning, appraisal and design
– Phase II - Selection, approval and activation
– Phase III - Operation, control and handover
– Phase IV - Evaluation and refinement

01.04.2024 Prepared by Kedir 32


United Nations Industrial Development Organization (UNIDO)
Project life Cycle

• Refers to the development process of an industrial investment


project
• Covers from initial idea until the plant is operational.

• Three distinct phases :-


• Pre-investment phase

• Investment phase

• Operational phase

01.04.2024 Prepared by Kedir 33


Project Idea Generation, Sources
& Techniques
Part II

01.04.2024 Prepared by Kedir Jemal 34


Cont…
• It has become commonplace to state there is no
shortage of good ideas in development.

• As President Bill Clinton put it:


“Nearly every problem has been solved by
someone, some where. The challenge of the 21st
century is to fid out what works and scale it up.

01.04.2024 Prepared by Kedir Jemal 35


PROJECT SELECTION PROCESS

• Identification of a new project is a complex


problem.
• Project selection process starts with the
generation of project ideas.
• In order to select the most promising project,
the entrepreneur needs to generate a few ideas
about the possible project one can undertake.

01.04.2024 Prepared by Kedir Jemal 36


Idea Generation
• Project selection process starts with the
generation of a project idea.
• Ideas are based on technological
breakthroughs.
• Most of the project ideas are variant of
present products or services.
• To stimulate the flow of ideas, the following
are helpful:

01.04.2024 Prepared by Kedir Jemal 37


Cont…
• The project ideas can be generated from various
internal and external sources. These are :-
 Knowledge of market, products, and services.
 Knowledge of potential customer choice.
 Emerging trends in demand for particular
product
 Scope for producing substitute product.
 Market survey & research.

01.04.2024 Prepared by Kedir Jemal 38


Cont…
 Going through Professional magazines.
 Making visits to trade and exhibitions
 Government guidelines & policy.
 Ideas given by the experienced person.
 Ideas by own experience.
 SWOT analysis.

01.04.2024 Prepared by Kedir Jemal 39


Cont…
• SWOT Analysis :- SWOT is an acronym for
strengths, weaknesses, opportunities and threats.
• SWOT analysis represents conscious, deliberate
and systematic effort by an organisation to
identify opportunities that can be profitably
exploited by it.
• Periodic SWOT analysis facilitates the
generation of ideas.
• Need Assessment for developmental projects
01.04.2024 Prepared by Kedir Jemal 40
Idea Generation Techniques
• Active Search: Active search refers to hunting
for a particular solution.

• Attribute List: Attribute listing refers to


taking an existing product or system, breaking
it into parts and then recombining these to
identify new forms of the product or system.

01.04.2024 Prepared by Kedir Jemal 41


Cont…
• Brainstorm: Brainstorming involves generating
a large number of solutions to a problem (idea)
with a focus on the quantity of ideas.
• During this process, no ideas are evaluated; in
fact unusual ideas are welcomed.
• Ideas are often combined to form a single good
idea as suggested by the slogan “1+1=3”.
– Brainstorming can be used by groups as well as
individuals.
01.04.2024 Prepared by Kedir Jemal 42
Cont…
• Collaborate: Collaboration refers to two or more
people working together towards a common goal.

• Designers often work in groups and co-create during


the entire creative process.
• Critique: Critique refers to receiving input on current
ideas.
• This could be collaborative such as receiving a design critique
from a colleague or individuals critiquing their own ideas.
• This technique often spurs new thought by finding solutions
to fault within current concepts.

01.04.2024 Prepared by Kedir Jemal 43


Cont…
• Documenting: Documenting refers to designers writing
down ideas (physically or electronically).

• This includes journaling, writing stories, and taking notes.


• Expert Opinion: Often elicit opinions from
experts to identify potential problems with products or
services before more comprehensive evaluations.
• This occurs when they are looking for an answer to a
problem that is outside their domain knowledge or
when they want to test a new idea.

01.04.2024 Prepared by Kedir Jemal 44


Cont…
• Incubate: Incubation refers to stepping back
from the problem to let the subconscious mind
work.
• Prototyping: refers to a low fidelity model of
an idea.
• These models can be created with any type of
material (paper, clay, etc.) as they are only
used to conceptualize a thought.

01.04.2024 Prepared by Kedir Jemal 45


Cont…
• Reflect: Reflection occurs when designers
review their previous work (sketches,
documents, prototypes, etc.)
• Sketching: Sketching refers to a rough
drawing of an idea.
• Socializing: Socializing refers to talking with
others about topics unrelated to the current
project.

01.04.2024 Prepared by Kedir Jemal 46


Screening project ideas
• A number of possible projects that
would address that need or opportunity are
elaborated and screened.
• The alternative project ideas must adherence to:
– government policies,
– development vision and
– program orientations and
– prioritized on the basis of their benefits and ease of
implementation.
• This leads to an ordered list of possible projects.
01.04.2024 Prepared by Kedir Jemal 47
Cont…

01.04.2024 Prepared by Kedir Jemal 48


Project Preparation

• Refers to the completion of the feasibility studies on which


financing institutions usually base their appraisal of a project.
• The objective of project preparation is to demonstrate that a
project based on the chosen concept is:
– In accordance with the country's development objectives and
priorities;
– Technically sound and the best of alternatives;
– Attractive to the intended beneficiaries;
– Operationally and managerially workable;
– Economically and financially viable;
– Sustainable and environmentally sound.

01.04.2024 Prepared by Kedir 49


Cont…
• Feasibility - Detail study of the project
• Background of the project
• Technical Study
• Market Study
• Organisation & Management
• Financial Analysis
• Economic Analysis
• Environmental Analysis
• Cross-cutting Analysis
• Sensitivity Analysis
• Risk Analysis

01.04.2024 Prepared by Kedir 50


Cont…
SWOT Analysis
• SWOT stands for Strengths, Weaknesses, Opportunities and Threats,
which are the themes under which ideas are catalogued using this
analytical tool.
• SWOT analysis is particularly useful in the project identification
process, appraisal as well as implementation of the project .
• SWOT analysis involves brainstorming sessions with concerned
participants
• Participants are required to list out all their ideas concerning the matter
being reviewed, under each of the four themes .

• All ideas are then reviewed and consensus reached on which are critical
to the success of the matter under review.
01.04.2024 Prepared by Kedir 51
Project Appraisal

• Appraisal — evaluation of alternative options and actions (ex ante


analysis)
• Strictly apply sensitivity and risk analysis
• Compare with standards or establish standards
• Don’t overlook appraising designs, manpower & marketing
procedures.

01.04.2024 Prepared by Kedir 52


Project Implementation
• Project implementation is a phenomenon by which project plans
are translated into reality within their specified time and budget.
• It covers the period starting from the time decision is made to
invest the project up to the completion.

• First, the better and more realistic a project plan is, the more
likely it is that the plan can be carried out and the expected
benefit realized.
• Second, project implementation must be flexible
• Circumstances will change, and project managers must be able
to respond intelligently to these changes.

01.04.2024 Prepared by Kedir 53


Cont…
• Project analysts generally divide the implementation phase
into three different time periods.
– Investment period -when the major project investments are
undertaken
– Development period -when its production builds up
• Once full development is reached, it continues for the
life of the project.

– Monitoring and Completion

• Most important part of project where project fails in most


developing countries

01.04.2024 Prepared by Kedir 54


What is Project Management?
 The art of organising, leading, reporting and
completing a project through people.

01.04.2024 55
Cont...
• A project manager is a person who causes things
to happen

• Therefore, project management is causing a


planned undertaking to happen.

01.04.2024 56
Project Manager Role
• A Good Project Manager
– Takes ownership of the whole project
– Is proactive not reactive
– Adequately plans the project
– Is respected (NOT Authoritarian)
– Is Decisive
– Is a Good Communicator
– Manages by data and facts not uniformed optimism
– Leads by example
– Has sound Judgement
– Is a Motivator
– Is Diplomatic
01.04.2024 57
Project Planning
• Adequate planning leads to the correct completion of
work

01.04.2024 58
Cont...
• Inadequate planning leads to frustration towards the
end of the project & poor project performance

Project Start Project End

01.04.2024 59
Key Elements of Project Plan
Contractual Aspects
– A complete list and description of all reporting
requirement.
Schedules
– Various schedule and lists of all objective
Resources
a) Budget.
b) Cost monitoring and control.
Personnel
– Personnel requirements
Evaluation Methods
– Be evaluated against the standard.
Potential Problems
– Anticipate potential difficulties.
01.04.2024 Prepared by Kedir Jemal 60
Common constraints in project
Implementation
• Over optimistic estimate at inception
• Lack of adequate knowledge about the Banks
(Creditors) guidelines on project implementation
procedures, such as
– disbursement,
– procurement and
– selection of contractors

01.04.2024 Prepared by Kedir 61


Cont…
• Inappropriate technology choice
• Shortage of qualified and experienced
personnel
• Lack of prompt decisions on certain issues,
like selection of sites for carrying out project
activities.
• High cost of input
Example feed shortage for livestock projects
01.04.2024 Prepared by Kedir 62
Cont….
• Inefficiency of the contracting firms resulting in
delays on finalization of construction/machinery
delivery.
• Change of project personnel (trained personnel
leave jobs before implementation is completed).
• Natural calamities caused by flash floods, road
blots due to landslides, and disruption of the
operation of important service facilities.

01.04.2024 Prepared by Kedir 63


Cont…
• Lack of proper communication facilities
between the field units, project headquarters
and the creditor/s.
• Unhealthy atmosphere created by political
upheaval in the project area, (labor strike,
change in government etc.).
• Corruption

01.04.2024 Prepared by Kedir 64


Project Management

Aspects of Project preparation and


Analysis

01.04.2024 Prepared by Kedir 65


Cont…
 There is a need for projects to be:

• Conceptually coherent,
• Relevant to national needs and capabilities,
• Technically sound,
• Viable in economic and financial terms,
• Attractive to the participants,
• Socially acceptable, and
• Environmentally and fiscally sustainable

01.04.2024 Prepared by Kedir 66


Aspects of project design and analysis

• There are six important aspects:


1. Technical aspects
2. Institutional-organizational-managerial aspects
3. Social aspects
4. Commercial aspects
5. Financial aspects
6. Economic aspects

01.04.2024 Prepared by Kedir 67


Technical Aspects

• The technical analysis concerns the project's inputs


(supplies) and outputs (production) of real goods and
services.

• The other aspects of project analysis can only proceed in


light of the technical analysis
• Good technical staff are essential for this work

• The technical analysis will examine the possible technical


relations in a proposed project

01.04.2024 Prepared by Kedir 68


Cont…
• Example: Dairy camel production enterprise
» Feed availability,
» Disease prevalence,
» Environmental condition
» Climatic variables (Rainfall, temp., relative
humidity)
» Availability of water and land, soil type,
» Production supplies and their availability,
» Availability of different infrastructure, etc
» Overall technical aspect properly addressed

01.04.2024 Prepared by Kedir 69


Cont…
• On the basis of these and similar considerations, the
technical analysis will determine
– the potential yields in the project area

– the possibilities for diversification.


• The technical analysis will also examine

• the storage facilities


• the processing systems

01.04.2024 Prepared by Kedir 70


Consequences of poor Technical Analysis

 Under or over estimation of quantities required by and


outputs of the project.

 Spurious cost and benefit estimation

 It will have effect on the project life time

01.04.2024 Prepared by Kedir 71


Institutional-organizational-managerial Aspect (IOMA)

• Here the emphasis is around the overlapping IOMA,


which clearly have an important effect on project
implementation
• A project must relate properly to the institutional
structure of the country and region
– What will be the arrangements for land tenure?
– What size holding will be encouraged?
– Does the project incorporate local institutions and
use them to further the project?

01.04.2024 Prepared by Kedir 72


Cont…
– How will the administrative organization of
the project relate to existing agencies?
– Is there to be a separate project authority?
– What will be its links to the relevant
operating ministries?
– Will the staff be able to work with existing
agencies?

01.04.2024 Prepared by Kedir 73


Cont…
• The organizational proposals should be examined to see that the
project is manageable.
– Is the organization such that lines of authority will be clear?
– Are authority and responsibility properly linked?
– Does the organizational design encourage delegation of
authority? or
– Do too many people report directly to the project director?
– Is a special monitoring group needed?
– What about training arrangements?
– Does the project have sufficient authority to keep its accounts
in order and to make disbursements promptly?

01.04.2024 Prepared by Kedir 74


Cont…
 Managerial issues are crucial to good project design and
implementation.
– The analyst must examine the ability of available staff to
judge whether they can administer such large-scale public
sector activities
– When managerial skills are limited, provision may have to be
made for training, especially of middle-level personnel.
– Expatriate managers may have to be hired, but caution should
be taken into account.
• In agricultural projects the analyst should consider the managerial
skills of the farmers and pastoralist who will participate.

01.04.2024 Prepared by Kedir 75


Social aspects
• The project analysts are expected to examine carefully the
broader social implications of proposed investments.
• Income distribution
• Employment opportunities
• Effects of projects on some groups of the society
• There should be considerations concerning the quality of life.
• consider the issue of adverse environmental impact.

01.04.2024 Prepared by Kedir 76


Commercial aspects

• Pays attention on the arrangements for marketing the output


produced and supply of inputs needed.
Output side:
• Careful analysis of the proposed market for the project's
production is essential
• Where will the products be sold?
• Is the market large enough to absorb the new production
without affecting the price?
• If the price is likely to be affected, by how much?
• Will the project still be financially viable at the new price?
• What share of the total market will the proposed project
supply?
• Are there suitable facilities for handling the new production?
01.04.2024 Prepared by Kedir 77
Cont…
• Is the product for domestic consumption or for
export?
• What financing arrangements will be necessary to
market the output, and
• What special provisions need to be made in the
project to finance marketing?
• Since the product must be sold at market
prices, a judgment about future government
price supports or subsidies may be in order.

01.04.2024 Prepared by Kedir 78


Cont…
• Input side:
• Appropriate arrangements must be made for farmers to secure the
supplies of inputs they need to adopt new technology.

• Do market channels for inputs exist, and

• Do they have enough capacity to supply new inputs on time?

• What about financing for the suppliers of inputs and credit for the
farmers to purchase these supplies?

• Arrangements for the procurement of equipment and supplies:


Bidding and specification preparation.

01.04.2024 Prepared by Kedir 79


Financial Aspects
• The financial aspects of project preparation and analysis
encompass the financial effects of a proposed project on each
of its various participants.

• In agricultural and pastoral projects the participants include:

– farmer, pastoral and agro-pastoral households,


– private sector firms,
– public corporations,
– project agencies, and
– perhaps the national treasury
• On the basis of these budgets, judgments are formed about the
project's financial efficiency, incentives…

01.04.2024 Prepared by Kedir 80


Cont…

• The analyst will need budget projections that estimate year by year
future gross receipts and expenditures.

 Including the costs associated with production and the credit


repayments farm families must make,
• To determine what remains to compensate the family for its own labor,
management skills, and capital.

• Part of the income the family will receive may be in food that is
consumed directly in the household, so a judgment must be made about
this quantity and its value.

 Think of the cash to repay the production credit and to make a policy judgment
about how much to subsidize families with very low incomes

01.04.2024 Prepared by Kedir 81


Cont…
• The analyst must judge whether HHs will need loans:

– To finance on-farm investment


– To meet some production costs
– Whether seasonal short-term credit should be provided for working
capital to finance inputs and pay for hired labor
– Also think of whether HHs have enough income to live on

 The objective of all these judgments is to shape credit terms that


will be generous enough to encourage farmers to participate in
the project.

01.04.2024 Prepared by Kedir 82


Cont…

• An analysis of the financial aspects of the project‘s must


answer

• What investment funds will the project need and


when?
• What will be the operating expenses when the
project is under way?
• Will these expenses depend on budget
allocations or will the project produce sufficient
revenue to cover its administrative costs?

01.04.2024 Prepared by Kedir 83


Objectives of Financial Analysis

• Six major objectives for financial analysis occur in


analyzing agricultural, pastoral and agro-pastoral projects.

Assessment of financial impact


Judgment of efficient resource use
Assessment of incentives
Provision of a sound financing plan
Assessment of financial management competence

01.04.2024 Prepared by Kedir 84


Economic Aspects
The question is:
• Will the proposed project contribute significantly to the
development of the total economy? and

• Will its contribution be great enough to justify using the


scarce resources it will need?

• Consideration taken into account in the economic analysis is


that of the society as a whole.
• The financial and economic analyses are thus complementary
 The financial analysis takes the viewpoint of the individual
participants and
 The economic analysis that of the society.

01.04.2024 Prepared by Kedir 85


Cont…
• There are very important distinctions between Financial and
Economic analysis.
1. In economic analysis taxes and subsidies are treated as transfer
payments.
In financial analysis taxes are usually treated as a cost and
subsidies as a return.

2. In financial analysis market prices are normally used

 In economic analysis, however, some market prices may be changed so that


they more accurately reflect social or economic values.

These adjusted prices are called "shadow" or "accounting" prices

01.04.2024 Prepared by Kedir 86


Identifying Project Costs and
Benefits

01.04.2024 Prepared by Kedir 87


Cont…
• The costs and benefits of a proposed project must be identified.

• Once costs and benefits are known, they must be priced, and
their economic values determined.

• In project analysis, the objectives of the analysis provide the


standard against which costs and benefits are defined.

• A cost is anything that reduces an objective, and a benefit is


anything that contributes to an objective.

01.04.2024 Prepared by Kedir 88


Approaches in comparing situations in project

• "With" and "Without" Comparisons

• Project analysis tries to identify and value the costs and benefits
that will arise with the proposed project and to compare them with
the situation as it would be without the project.

 The difference is the incremental net benefit arising from the


project investment.

• This approach is not the same as comparing the situation


"before" and "after" the project.

01.04.2024 Prepared by Kedir 89


Costs of Projects
• In examining costs
– Physical goods
– Labor
– Land
– Contingency allowances
• Physical contingencies are included in the project costs to allow for
uncertainties and to compensate for possible inaccuracies in the estimates of
work quantities.
• Price contingencies may also be estimated to demonstrate the probable
escalating effect of relative price change and inflation on project costs..
– Taxes
– Debt service
– Sunk costs

01.04.2024 Prepared by Kedir 90


Tangible Benefits of Projects
• Tangible benefits of projects can arise either from an increased
value of production or from reduced costs.

 Increased production
 Quality improvement
 Change in time of sale
 Change in location of sale
 Changes in product form (grading and processing)
 Cost reduction through mechanization
 Reduced transport costs
 Losses avoided
 Other kinds of tangible benefits

01.04.2024 Prepared by Kedir 91


Intangible Costs and Benefits

• Almost every project has costs and benefits that are intangible.

• Quantification and valuation

• Every project decision will have to take intangible factors into


account through a subjective evaluation:

• Because intangible costs can be significant and

• Because intangible benefits can make an important


contribution to many of the objectives of rural
development.

01.04.2024 Prepared by Kedir 92


Pricing project costs and benefits

• Once costs and benefits have been identified, if they are to be


compared they must be valued.

• Money value and the proper prices for the costs and benefits

 Underlying all financial and economic analysis is an


assumption that prices reflect value-or can be adjusted to
do so.

01.04.2024 Prepared by Kedir 93


Cont…
a) The first step in valuing costs and benefits is finding the market
prices for the inputs and outputs
 Points of first sale and farm-gate price

 Predicting future price


• Project analysis is about judging future cost & returns
• Starting point would be to observe the past years trend and
current prices
• Judgment is also important,
• Note that distant future reduce prediction power of a model

01.04.2024 Prepared by Kedir 94


cont…
 Inflation: an increase in general prices of goods & services

• To overcome this we use constant price in project analysis


assuming inflation affects all equally

01.04.2024 Prepared by Kedir 95


Economic Analysis

01.04.2024 Prepared by Kedir 96


Cont…
• Economic and financial analysis are similar, in both we
assess the profit of an investment.

• The concept of financial profit is not the same as social


profit of economic analysis.

The financial –money profit

Social profit measures the effect of a project on


fundamental objectives of the whole economy.

01.04.2024 Prepared by Kedir 97


Cont…

• Some costs and benefits that may appear in the financial


accounts may not appear in the economic accounts-vise
vera

• Some costs and benefits may be lower (higher) in financial


but higher(lower) in economic analysis even though that
the costs and benefits appear in both economic and
financial accounts.

01.04.2024 Prepared by Kedir 98


.
 The extent to which economic costs and benefits diverge from their counterpart
financial costs and benefits rests on:

The presence and extents of market imperfections


(Market power, externality and public good (non-excludability), property right,
information asymmetry)
• A market in which individual suppliers or consumers have an impact on
supply or demand.
» For example, a market characterized by a monopoly or
oligopoly is imperfect.

• A market in which information is incomplete.


» Participants in an imperfect market are more likely to make
poor decisions than they would be if information were more
readily available.

01.04.2024 99
Prepared by Kedir
Cont…

Government interventions of various forms

 taxes, subsidies, bailouts, wage and price controls, and regulations

The fundamental policy objectives

 saving, income distribution, employment, price stabilization, etc

01.04.2024 Prepared by Kedir 100


Purposes of Economic Analysis
i. Selection of alternatives:
– In this context economic analysis:
• helps to design and select projects that contribute to the welfare
of a country.
• considers the project’s impact on many issues.
• helps to undertake optimal decision by considering the merits of
different aspects.

ii. Identification of winners and losers:


• Who enjoys the music? Who pays the piper?
• Identifying those who will gain and lose helps the analyst to
have insight into the incentives that various project entities have
to see that the project is implemented as planned.

iii. Fiscal impact


vi. Environmental impact
01.04.2024 Prepared by Kedir 101
Monitoring and Evaluation

01.04.2024 Prepared by Kedir 102


Cont…
• Monitoring:

 It can be defined as the ongoing process by


which stakeholders obtain regular feedback
on the progress being made towards achieving
their goals and objectives.

01.04.2024 Prepared by Kedir 103


Cont…
• Evaluation:

– It is a rigorous and independent assessment of either


completed or ongoing activities.

– To determine the extent to which they are achieving stated


objectives .

01.04.2024 Prepared by Kedir 104


Cont…
• Evaluations, like monitoring, can apply to many things,
including an:
– activity,
 project,
 programme,
– strategy,
– policy,
– topic,
– theme,
– sector or
– organization
01.04.2024 Prepared by Kedir 105
Cont…
• The key distinction between the two:
– Evaluations are done independently to provide managers
and staff with an objective assessment of whether or not
they are on track.
• They are also more accurate in their procedures,
design and methodology, and generally involve more
extensive analysis.

01.04.2024 Prepared by Kedir 106


Cont…
• However, the aims of both monitoring and evaluation
are very similar:

– to provide information that can help inform decisions,


improve performance and achieve planned results
Cont…
• Monitoring provides real-time information required by
management, evaluation provides more in-depth assessment.
 The monitoring process can generate questions to be answered
by evaluation.
• Evaluation draws heavily on data generated through
monitoring during the programme and project cycle, including,
for example:
– baseline data,
– information on the programme or
– project implementation process and measurements of result.

01.04.2024 Prepared by Kedir 108


Cont…
• Evaluation complements monitoring by
providing an independent and in-depth
assessment of:

– what worked and


– what did not work, and
– why this was the case

01.04.2024 Prepared by Kedir 109


Cont…

• Without effective planning, monitoring and evaluation, it would be


impossible to judge:

 If work is going in the right direction,


 Whether progress and success can be claimed, and
 How future efforts might be improved

 M&E establish clear links between past, present and future


initiatives and development results

01.04.2024 Prepared by Kedir 110


 M&E help extract relevant information from past and ongoing
activities that can be used as the basis for project or programme:

 modification,
 reorientation and
 future planning.

 Programmes and projects with strong monitoring and evaluation


components:
• Tend to stay on track
• Problems are often detected earlier,
– which reduces the likelihood of having major cost overruns or
time delays later.

01.04.2024 Prepared by Kedir 111


Cont…

• Good planning helps us focus on the results that matter

• Good monitoring and evaluation:

• Help us learn from past successes and challenges and

• Inform decision making so that current and future


initiatives are better able to improve people’s lives and
expand their choices.

01.04.2024 Prepared by Kedir 112


Cont…

 Without proper planning and clear articulation of intended


results, it is not clear what should be monitored and how;
hence monitoring cannot be done well.

 Without effective planning clear results frameworks, the basis


for evaluation is weak; hence evaluation cannot be done well.

 Without careful monitoring, the necessary data is not


collected; hence evaluation cannot be done well.

01.04.2024 Prepared by Kedir 113


Cont…

 Monitoring is necessary, but not sufficient, for evaluation

 Monitoring facilitates evaluation, but evaluation uses additional new


data collection and different frameworks for analysis

 Monitoring and evaluation of a programme or project will often lead


to changes in programme or project plans.

This may mean further changing or modifying data


collection for monitoring purposes

01.04.2024 Prepared by Kedir 114


Why monitor and evaluate?
 In the absence of effective monitoring and evaluation, it would
be difficult to know:

– whether the intended results are being achieved as planned


– what corrective action may be needed to ensure delivery of
the intended results
– whether initiatives are making positive contributions
towards human development.

 Help determine exactly when a programme or project is on


track and when changes may be needed.

01.04.2024 Prepared by Kedir 115


Cont…

 Essential in helping managers, planners, implementers, policy


makers and donors acquire the information and understanding
they need to make informed decisions about programme
operations.

 M&E together provide the necessary data to guide strategic


planning, to design and implement programmes and projects,
and to allocate, and re-allocate resources in better ways

 Monitoring and evaluation always relate to pre-identified


results in the development plan.

01.04.2024 Prepared by Kedir 116


Cont…
 The key questions that monitoring seeks to answer include the following:

• Are the pre-identified outputs being produced as planned and efficiently?

• What are the issues, risks and challenges that we face or foresee that need to be
taken into account to ensure the achievement of results?

• What decisions need to be made concerning changes to the already planned


work in subsequent stages?

• Will the planned and delivered outputs continue to be relevant for the
achievement of the envisioned outcomes?

• Are the outcomes we envisaged remaining relevant and effective for achieving
the overall national priorities, goals and impacts?

• What are we learning?


01.04.2024 Prepared by Kedir 117
Monitoring and evaluation framework

 A clear framework is essential in order to carry out monitoring and


evaluation systematically.

• This framework serves as a plan for monitoring and evaluation, and should
clarify:

 What is to be monitored and evaluated


 The activities needed to monitor and evaluate
 Who is responsible for monitoring and evaluation activities
 When monitoring and evaluation activities are planned (timing)
 How monitoring and evaluation are carried out (methods)
 What resources are required and where they are committed

01.04.2024 Prepared by Kedir 118


Cont…
• In general, the M&E framework has main
components:
• Narrative component:

– This describes how the partners will undertake


monitoring and evaluation and the accountabilities
assigned to different individuals and agencies.

01.04.2024 Prepared by Kedir 119


cont…
• Planning matrices for monitoring and
evaluation. These are strategic and consolidate
the information required for monitoring and
evaluation for easy reference.

01.04.2024 Prepared by Kedir 120


Follow-up, Monitoring and Evaluation
Follow-up
• Follow-up is a method by which a project promoter keeps a
watch on the progress or project implementation.

• In follow-up of project implementation, there is no need to


hurry.
• What is required is diligence and caution
• to know and analyze the sequential relationship of
activities
• to identify the important and critical ones.

01.04.2024 Prepared by Kedir 121


Project Monitoring and Evaluation
• The essential first steps of feedback are the processes of
monitoring and evaluation.

• Monitoring provides project management with information


about current and emerging project, problems and data to
assess if the project objectives remain valid.

• Evaluation, in the context of project implementation, is an


ongoing activity used to reassess components necessary to
meet project objectives in the light of experience as
implementation proceeds.
01.04.2024 Prepared by Kedir 122
Primary issues of monitoring
• Are the right inputs being supplied/delivered at the right time?
• Are the planned inputs producing the planned outputs?
• Are the outputs leading to the achievement of the planned
objectives?
• Is the policy environment consistent with the design
assumptions?
• Are the project objectives still valid?

01.04.2024 Prepared by Kedir 123


Primary issues of Evaluation

• Were the commitments honored from all sides?

• Did the activities that were planned actually occur?

• What should have been planned (rather than what was actually
planned) to reach the projects objectives more
effectively/efficiently?

• This requires a critique of the planning process, and of the


coherence between program and objectives.

01.04.2024 Prepared by Kedir 124


Cont…
• What could have been achieved with the same resources
and in the same time if the project had been managed more
efficiently and effectively?

• Here the evaluation makes a judgment as to whether the


project’s objective(s) could have been achieved more
economically or realized more fully.

• Evaluation (ex post analysis) including impact assessment

01.04.2024 Prepared by Kedir 125


Steeps in Monitoring and Evaluation
• First, a readiness assessment should be
conducted.
• The assessment involves understanding the
needs and characteristics of the area or region
to be targeted.
• As well as the key players
Cont….
• Second, program evaluators should agree on
specific outcomes to monitor and evaluate.
• As well as key performance indicators to
monitor outcomes.

• Doing so involves collaboration with


stockholders.
– Example :Girls Schooling
Cont…
• Third, evaluators need to decide how trends in these
outcomes will be measured.
• For example, if Girls schooling were an important
outcome for a program.
• How schooling achievement be measured by the:
– proportion of girls enrolled in school
– test scores,
– school attendance, or another metric?
 Qualitative and quantitative assessments can be
conducted to address this issue.
Cont…
• Fourth, the instruments to collect information
need to be determined.
• Base line survey etc
• Fifth, targets need to be established; these
targets can also be used to monitor results.
Cont…
• This effort includes setting periodic targets
over time (for example, annually or every two
years).
• Considering the duration of the likely effects
of the program.
• Other factors that might affect program
implementation political considerations is
also important.
Cont…
• The seventh step relates to the timing of monitoring.
• The eighth step involves careful consideration of the
means of reporting, including the audience to
whom the results will be presented.
• The ninth step involves using the results to create
avenues for feedback such as input from:
– independent agencies, local authorities, and targeted and
nontargeted communities
Cont…
• Effective M&E systems will endure and are
based on, among other things:
– continued demand;
– transparency and
– Accountability in evaluation procedures;
– effective management of budgets; and
– well-defined responsibilities among program staff
members
Cost Control
• The goal is to detect and correct deviation
from desired „ Budget.

• The early detection of actual or potential cost


overruns is vital to management.

• It provides the opportunity to initiate remedial


action.
Cost…
• Project cost control includes:-
– Monitor cost performance
– Comparing “budgeted” and “actual”
– Determine the appropriate project changes to
be included in a revised cost baseline
– Inform project stakeholders of authorized changes
to the project that will affect costs.
Cost…
• Cost reporting and control responsibilities:-

 Identifying and allocating responsibilities in


cost reporting is required.
Elements to Control
 Manpower-related control
 Machinery-related control
 Money-related control
 Material-related control
Manpower
• Also referred to as ”Human Resource
Control”
- Lay-off/fire any under-performing staff
- Hire staff with needed skills
- Assign staff with specific skills to specific
activities
• Fix problems without blaming people
Machinery
• Also referred to as ”Physical Asset Control”

- Change any under-performing equipment


- Bring in equipment with appropriate
capabilities
- Re-assign specific equipment to specific
activities
Cont…
• Also referred to as ”Financial Resource Control”
• How much money should be spent?
• How should it be spent?
Project Manager assisted by:
- Project accountant
- Project Finance Manager
Evaluation of Activities
• Weekly review of activity status and estimates.
• Each current activity will be reviewed.

• Weekly review of unplanned requirements


such as equipment, staff, or consulting
resources.
Cont…
• The adequacy of current resources, human and
equipment, must be reviewed.

• A potential cost increase occurs when the need


for additional resources is identified.
• Weekly review of risks and changes to risks.
– The current status of risks will be reviewed as
described in the Risk Management Plan.
Cont…
• A potential cost increase occurs when existing
risks have become riskier or when new risks
have been identified.
• Weekly review of changes to scope, approved.
• A potential cost increase occurs when
unapproved scope changes are being carried
out.
Impact Evaluation

Ch-9

01.04.2024 Prepared by Kedir 143


Cont…
• Evaluation approaches for development
programs have evolved considerably over the
past two decades.

01.04.2024 Prepared by Kedir 144


Cont…
• Comparing program effects across different
regions and countries is also receiving greater
attention.

• As programs target larger populations and


become more ambitious in scope, and
researchers acquire enough data to be able to
test specific policy questions across localities.

01.04.2024 Prepared by Kedir 145


Cont…
• Public programs/Projects are designed to reach
certain goals and beneficiaries.

• Methods to understand whether such


programs actually work, as well as the level
and nature of impacts on intended
beneficiaries.

01.04.2024 Prepared by Kedir 146


Cont…
• Programs might appear potentially promising
before implementation yet fail to generate
expected impacts or benefits.

• The obvious need for impact evaluation is to


help policy makers decide:
– whether programs are generating intended effects

01.04.2024 Prepared by Kedir 147


Cont…
• In the context of development, impact
evaluations have been defined as:
– “systematic identification of the effects . . . on
individuals, households, institutions, and the
environment caused by a given development
activity such as a program or project.”

(World Bank 2002, pg. 20).

01.04.2024 Prepared by Kedir 148


Cont…

– Impact evaluation studies whether the changes in


well-being are indeed due to the program
intervention and not to other factors.
Cont…
• Impact evaluation span qualitative and quantitative
methods, as well as ex ante and ex post methods.
• The mechanisms of such impacts, and the extent of
benefits to recipients from in-depth and group-based
interviews.
• Whereas quantitative results can be generalizable,
the qualitative results may not be.

01.04.2024 Prepared by Kedir 150


Cont…
• A qualitative assessment on its own cannot assess
outcomes against relevant alternatives or
counterfactual outcomes.

– It cannot really indicate what might happen in the


absence of the program.

01.04.2024 Prepared by Kedir 151


The Problem of the Counterfactual

• The main challenge of an impact evaluation is


to determine what would have happened to the
beneficiaries if the program had not existed.

• A beneficiary’s outcome in the absence of the


intervention would be its counterfactual.

01.04.2024 Prepared by Kedir 152


Cont…
• A mixture of qualitative and quantitative methods (a
mixed-methods approach) might therefore be useful in
gaining a comprehensive view of the program’s
effectiveness.

• Quantitative techniques attempt to determine whether


impacts occurred.

• Qualitative methods can add rich detail and permit a


grounded analysis of the underlying causes of outcomes.
Cont…
• Impact evaluation can be distinguished from other
approaches to evaluation, such as M&E.

• M&E does not spell out whether the impact indicators


are a result of program intervention.

• Impact evaluations often depend on knowing how the


program is designed, how it is intended to help the
target audience.

01.04.2024 Prepared by Kedir 154


It answers Questions like…..
 Can conditional cash-transfer programs in Somaliland improve
health outcomes for poor women Girls?
 Can conditional cash-transfer programs in Somaliland improve
schooling outcomes for Girls?
 Does a new road actually raise welfare in a remote area in
Somaliland or is it a “highway to nowhere”?
 Do community-based programs in Somaliland project create
long-lasting improvements in employment and income for the
poor?

01.04.2024 Prepared by Kedir 155


Cont…
• Impact evaluation studies whether the changes
in well-being are indeed due to:-

– Program/project intervention and


– Not to other factors

01.04.2024 Prepared by Kedir 156


Cont…

• The aim is to compare what was planned with what was


actually delivered.

• Operation evaluation can be based on interviews with


program beneficiaries and with officials responsible for
implementation.

01.04.2024 Prepared by Kedir 157


Impact evaluation

01.04.2024 Prepared by Kedir 158


Approaches to impact evaluation: an
overview
• Quantitative impact evaluation: analysis based
on a representative survey.
• It has both treatment group and a comparison
group, preferably both before and after the
intervention.

 Participatory impact evaluation: analysis based


on participatory methods amongst
beneficiaries.
01.04.2024 Prepared by Kedir 159
Quantitative impact evaluation
• The cornerstone of quantitative impact
evaluation is data collection from a statistically
representative sample using a structured
questionnaire.
• It is strongly preferable that data are collected
both before the intervention (baseline) and after
(endline).

• A midterm survey is also an advantage.


01.04.2024 Prepared by Kedir 160
Different Evaluation Approaches
1. Randomized evaluations
2. Matching methods, specifically propensity
score matching (PSM)
3. Double-difference (DD) methods
4. Instrumental variable (IV) methods
5. Regression discontinuity (RD) design and
pipeline methods
6. Distributional impacts
7. Structural and other modeling approaches
Designing and Implementing Impact
Evaluations
• Data availability and quality are also integral
to assessing program/ project effects.

• Data requirements will depend on whether


evaluators are applying a:-
– quantitative or
– qualitative approach or
– both
Cont…
• Data should be collected from both the
affected population (the treatment group) and
a comparison group.

• Project impact is then calculated as either a


single difference.

01.04.2024 Prepared by Kedir 163


Cont…
• Selection of an appropriate comparison group
is one of the main challenges in impact
evaluation:

– They should be identical to the treatment group


except that the latter receive the intervention and
the former do not.

01.04.2024 Prepared by Kedir 164


Cont…
• Propensity score matching: Selection may be
based on a set of characteristics rather than just
one.
• Hence the comparison group need be matched
on all these characteristics.
• PSM uses statistical modeling to identify a
group of individuals, households or firms with
the same observable characteristics as those
participating in the project.
01.04.2024 Prepared by Kedir 165
Cont…

• Participants are then matched on the basis of


this probability, or propensity score, to
nonparticipants.

01.04.2024 Prepared by Kedir 166


Cont….
• Regression-based approach: The regression
based approach models the determinants of
outcomes.

• The approach has the advantage of flexibility


it does not lump different activities under the
single heading of the intervention.
Cont…

Yi = αXi + βTi + εi

• Here, T is a dummy equal to 1 for those who


participate and 0 for those who do not
participate.
• X is set of other observed characteristics of the
individual and perhaps of his or her household
and local environment.
Cont…
• ε is an error term reflecting unobserved
characteristics that also affect Y.
• The equation reflects an approach commonly
used in impact evaluations.

• It is to measure the direct effect of the program


T on outcomes Y .
How is an Impact Evaluation Conducted?

• Conducting a successful impact evaluation


requires advance planning.
• Insufficient planning can unnecessarily
compromise an evaluation effort, weakening
findings and their subsequent policy value.
• A good evaluation plan will:
(i) establish evaluation objectives;
(ii) determine appropriate evaluation methods;
Cont…
(iii) provide a data collection strategy and
identify available sources; and
(iv) establish a timeline for producing and
disseminating findings
• Each of the elements is discussed below, with
attention to the pros and cons associated with
the available choices.
Cont…
Objectives
• The principal objective is always to determine
whether the program is helping beneficiaries.
• Therefore, the program objectives are central.
• Some examination of available data and
measurable indicators should be conducted.
Thank you !!!

01.04.2024 Prepared by Kedir 173

You might also like