Itpm 1
Itpm 1
Management
Principles and
Practices
– Introductions
– Course Objective
– Unit 1: Introduction to Project Management
Introductions
Introduction to Project
Management
Introduction to Project Management
– Project Failures
– Project Successes
– What is Project Management?
– Key Functional Areas of Project Management
– Project Life Cycle
Project Failure
– On time
– On budget
– Meeting the goals that have been agreed upon
Iron Triangle
Pick Any Two
What is a Project?
Trait 1
Enthusiasm for the project
Trait 2
Ability to manage change effectively
Trait 3
A tolerant attitude toward ambiguity
Trait 4
Team – building and negotiating skills
Seven Traits of Good Project
Managers
Trait 5
A customer-first orientation
Trait 6
Adherence to the priorities of business
Trait 7
Knowledge of the industry or technology
Project Success
12 Golden Rules
Rule #1
– Thou shalt gain consensus on project outcome.
Rule #2
– Thou shalt build the best team possible.
Rule #3
– Thou shalt develop a comprehensive, viable plan and keep it up-
to-date.
Rule #4
– Thou shalt determine how much stuff you really need to get
things done.
Project Success
12 Golden Rules
Rule #5
Rule #6
– Thou won’t try to do more than can be done.
Rule #7
– Thou will remember that people count.
Rule #8
– Thou will gain the formal and ongoing support of management an
stakeholders.
Project Success
12 Golden Rules
Rule #9
Rule #10
– Thou must keep others informed of what you’re up to.
Rule #11
– Thou must be willing to try new things.
Rule #12
Project Management
– Project Management
– The “application of knowledge, skills, tools and techniques to
project activities to meet project requirements.”
– 9 Knowledge areas
1. Integration Management
Partial Execution
Solution
Know Answer
Pr Space
oje
ct
HOW Pla
nn
ing
Problem Partial
Don’t Know
Space Answer
Project Definition
:
Plan drafted Requirement gathered Best
practice researched Draft 1
prepared Distributed to
stakeholders
Plan approved Feedback gathered
Amendments made Final
plan prepared
Distributed to stakeholders
Sign-off obtained
WORK-BREAKDOWN STRUCTURE
WBS
Hierarchy of tasks required to complete project
Each task is broken into smaller tasks that can be managed and
estimated
Define task dependencies
▪ Some tasks must begin at the same time, some must end at
the same time and some cannot start until the other tasks
have finished.
Estimate task durations and cost
May be inputted into project management software
• Final WBS plan is called baseline WBS
• Risks:
• Plan is not approved after first round of feedback
• Resources are not available at the required time
• Plan is not given consent
• For each of the above, you should have a contingency plan, or do
some activity that may prevent it happening in the first place.
• Issues:
– If any of the above actually happens, then it becomes an issue to
solve.
• Gantt Chart:
• Stakeholder:
– House owner, Builder, Council, ???
–A successful Project Manager must simultaneously manage the four basic
elements of a project:
–resources, time, money, and most importantly, scope.
–All these elements are interrelated. Each must be managed effectively. All
must be managed together if the project is to be a success. The resource that
can be leveraged to the greatest extent in all projects is the people involved