Site Office - KNPC L&T Project-08092021

The document provides information about construction projects for replacing substations and constructing a site office at an oil refinery. It includes package details, a project synopsis with timeline, records of layout drawing revisions, status of design drawing submissions and approvals, and a list of issues.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
76 views23 pages

Site Office - KNPC L&T Project-08092021

The document provides information about construction projects for replacing substations and constructing a site office at an oil refinery. It includes package details, a project synopsis with timeline, records of layout drawing revisions, status of design drawing submissions and approvals, and a list of issues.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 23

Replacement Of Old & Obsolete Substations In MAA

Refinery
Subcontract For Construction of Site Office for
KNPC at MAA
Project Status as on: 4th Sep 2021

Al Jazirah Industrial Projects Co.


Al-Jazirah Industrial Projects
COVERAGE

1. PACKAGE DETAILS

2. PROJECT SYNOPSIS

3. KNPC LAYOUT REVISION RECORDS

4. DESIGN DRAWINGS SUBMISSION VS APPROVAL STATUS

5. RAM APPROVAL STATUS

6. ISSUES & REQUISITES LIST

Apr 24, 2024 Al-Jazirah Industrial Projects 2


PACKAGE DETAILS
PACKAGE DESCRIPTION:

Subcontract For Construction of Site Office for KNPC at MAA

SCOPE OF WORKS:

Design & Engineering of Site Offices, Car Park, Electrical (Small Power & Lighting),
Plumbing, Air-conditioning (Split AC Type), Sanitary, Fire alarm,
Data/Telecom(Passive Components only).

Construction of site offices including Earth Works, Foundations, Structure, Cladding,


Internal Partitions, False Ceiling, Toilets, Doors & Windows, Small Power & Lighting
Electrical Works, Split AC, Fire alarm, Fire Extinguishers & Data/Telecom Cabling.

External Works: Car park, walkway, water piping, OH Tank, Sewage System, Laying
of Milled Asphalt, Electrical power cable connection with existing facility, Fire alarm
connectivity with existing system.

Apr 24, 2024 Al-Jazirah Industrial Projects 3


PROJECT SYNOPSIS
1. JIP RECEIVED THE LOI ON 26-JAN-2021
2. PLACED ORDER FOR STRUCTURAL AND SHEET TO KIRBY ON 5-FEB-2021
3. FINILAZNED ALL THE MAJOR SUPPLIERS BY END OF FEB
4. SUBMITTED MAJORITY OF RAM BY END OF MARCH
5. ARCHITECHURE DRAWINGS SUBMITTED BY 14-FEB-2021
6. CIVIL DESIGN AND DRAWING SUBMIITED BY 25-MARCH-2021
7. STRUCTURAL DESIGN AND DRAWINGS SUBMITTED BY 28- MARCH -2021
8. ELECTRICAL & INSTRUMENTATION DESIGN AND DRAWING SYBMITTED BY 28-FEB-
2021
9. PLUMPLING AND SEWAGE DESIGN AND DRAWING SUBMITTED BY 29APRIL-2021
10. HVAC DESIGN AND CALCULATION SUBMITTED BY 24- MARCH-2021

Apr 24, 2024 Al-Jazirah Industrial Projects 4


KNPC LAYOUT DRAWINGS REVISIONS RECORDS

Description of Drawings Date of issuance Major Changes

Building Layout Drawings 20-Jan2021


Building Layout Drawings 8-May-2021 Dimensional Change
Building Layout Drawings 20-May-2021 Curtain wall & Future
Expansion Provisions
Drainage & Water Supply Rev C 27- July - 2021 Location Change
Overhead Tank Rev C 27- July - 2021 Location Change
Septic Tank Location and Orientation 31-Aug-21 Location and Orientation

Apr 24, 2024 Al-Jazirah Industrial Projects 5


DESIGN DRAWING SUBMISSION VS APPROVAL STATUS

Date of Date of
Approva
Description of drawing Document No Submissio last
l Status
n response
KNPC PD SITE OFFICE FLOOR 31-Aug- To be
KNPC-TCF-CS-AR-ARD-0001 14- Feb-2021
PLAN 2021 Submitted
KNPC PD SITE OFFICE
24-Jun- To be
DOOR,WINDOWS ROOF FLOOR KNPC-TCF-CS-AR-ARD-0002 14-Feb-2021
2021 Submitted
& WALL FINISHING SCHEDULE
GA&RC DETAILS OF FOOTING,
TIE BEAM & FLOOR SLAB FOR KNPC-TCF-CS-GC-RCD-0001 10-Mar-2021 3-Jun-2021 Approved
SITE OFFICE BUILDING
KNPC PD OFFICE EXCAVATION
Awaiting
LAYOUT & DETAILS FOR 3-Jun-2021
KNPC-TCF-CS-GC-LYD-0003 14-Mar-2021 Approval
FOUNDATION AND GROUND
IFC
BEAM
Awaiting
GA&STRUCTURAL STEEL
Approval
DETAILS OF SITE OFFICE KNPC-TCF-CS-GC-GAD-0001 28-Mar-2021 25-Jul-2021
IFC
BUILDING (kriby)

KNPC PD SITE OFFICE LAYOUT To be


30-Mar-2021 26-Jul-2021
& DETAILS OF PATHWAY / KNPC-TCF-CS-GC-RCD-0004 Submitted
WALKWAY
Apr 24, 2024 Al-Jazirah Industrial Projects 6
DESIGN DRAWING SUBMISSION VS APPROVAL STATUS

Date of
Date of Approva
Description of drawing Document No last
Submission l Status
response
WATER SUPPLY PLAN & 11-Aug- Awaiting
KNPC-TCF-CS-UG-SDT-0001 06-April-2021
SCHEMATIC DIAGRAM 2021 Approval
KNPC PD SITE OFFICE GA & RC
11-Aug- Awaiting
DETAILS FOUNDATION FOR KNPC-TCF-CS-GC-RCD-0003 14-April-2021
2021 Approval
OVER HEAD WATER TANK
KNPC PD SITE OFFICE
SUPPORTING STRUCTURAL 11-Aug- Awaiting
KNPC-TCF-CS-GC-GAD-0003 19-April-2021
STEEL DETAILS FOR OVER 2021 Approval
HEAD WATER TANK
24-Aug- Awaiting
DRAINAGE LAYOUT KNPC-TCF-CS-GC-LYD-0001 29-April-2021
2021 Approval
KNPC PD SITE OFFICE
11-Aug- Awaiting
EXCAVATION DETAILS FOR KNPC-TCF-CS-CC-LYD-0012 29-Jun-2021
2021 Approval
OVER HEAD WATER TANK
KNPC PD SITE OFFICE 24-Jun-
KNPC-TCF-EL-CC-LYD-0004 28- Feb -2021 Approved
EARTHING LAYOUT 2021
KNPC PD SITE OFFICE SMALL
KNPC-TCF-EL-CC-LYD-0001 3-Mar-2021 6-May-2021 Approved
POWER LAYOUT

Apr 24, 2024 Al-Jazirah Industrial Projects 7


DESIGN DRAWING SUBMISSION VS APPROVAL STATUS
Date of
Date of Approva
Description of drawing Document No last
Submission l Status
response
KNPC PD SITE OFFICE INDOOR & KNPC-TCF-EL-CC-LYD- 24-Jun-
24-Mar-2021 Approved
OUTDOOR LIGHTING LAYOUT 0003 2021
KNPC PD SITE OFFICE FIRE ALARM
KNPC-TCF-ME-FF-LYD- Approved
SYSTEM DEVICE LAYOUT 3-Mar-2021 28-Jul-21
0001
DRAWING
GA & STRUCTURAL STEEL DETAILS KNPC-TCF-CS-GC-GAD- To be
30-Aug-21 7-Sep-21
OF CAR PARKING SHELTER 0002 submitted
GA & RC DETAILS OF FOOTING FOR KNPC-TCF-CS-GC-RCD- 7-Sep-21 To be
30-Aug-21
CAR PARKING 0002 submitted
KNPC PD SITE OFFICE EXCAVATION KNPC-TCF-GE-CC-LYD- 7-Sep-21 To be
30-Aug-21
DETAILS FOR CAR SHELTER 0013 submitted
KNPC PD SITE OFFICE DATA / KNPC-TCF-IC-TL-LYD- Awaiting
3-Mar-21 22-Aug-21
TELECOM LAYOUT 0001 Approval
KNPC PD SITE OFFICE AIR KNPC-TCF-ME-AC-LYD- Awaiting
24-Mar-21 7-Aug-21
CONDITION EQUIPMENT LAYOUT 0002 Approval
KNPC PD SITE OFFICE LIGHTING & KNPC-TCF-EL-CC-LYD-
31-Mar-21 28-Jul-21 Approved
SMALL POWER WIRING DIAGRAM 0005
KNPC PD SITE OFFICE SMALL Awaiting
KNPC-TCF-EL-CC-STT-
POWER ,LIGHTING & EARTHING 5-Apr-21 21-Jun-21 IFC
0001
INSTALLATION DETAILS Approval
Apr 24, 2024 Al-Jazirah Industrial Projects 8
DESIGN DRAWING SUBMISSION VS APPROVAL STATUS
Date of
Date of Approva
Description of drawing Document No last
Submission l Status
response
KNPC PD SITE OFFICE FIRE ALARM KNPC-TCF-IC-IN-BLD- Awaiting
8-May-21 7-Jul-21
SYSTEM LOOP WIRING DIAGRAM 0001 approval
KNPC PD SITE OFFICE TYPICAL
Awaiting
INSTALLATION AND WIRING KNPC-TCF-IC-FG-STT-
5-Jun-21 21-Aug-21 approval
DETAILS OF FIRE ALARM SYSTEM 0001
DEVICES

Apr 24, 2024 Al-Jazirah Industrial Projects 9


RAM APPROVAL STATUS
Date of Date of Status of
Description of Items
Submission Response RAM
PRE - ENGINEERED BUILDING 06-April-2021 8-Aug-2021 Approved

WELDED WIRE FABRIC MESH 22-Feb-2021 7-Apr-2021 Approved

INTERLOCK,KERBSTONE AND SAND Approved With


22-Feb-2021 12-Aug-21
CEMENT BLOCK Comments

WATER TANK FIBER GLASS 23-Feb-2021 7-Apr-2021 Approved

REBAR 23-Feb-2021 22-Mar-2021 Approved

POLYTHENE SHEET 23-Feb-2021 14-Apr-2021 Approved

Awaiting
CERAMIC TILE 24-Feb-2021 2-Aug-21
Approval
Awaiting
GYPSUM BOARD PARTITION WALL 2-Mar-2021 31-Aug-21
Approval
Approved With
GYPSUM CEILING/False Ceiling 2-Mar-2021 19-Aug-21
Comments

Apr 24, 2024 Al-Jazirah Industrial Projects 10


RAM APPROVAL STATUS
Date of Date of Status of
Description of Items
Submission Response RAM
GYPSUM BOARD CLADDING 2-Mar-2021 24-Jul-2021 Rejected

BINDING WIRE 13-Mar-2021 7-Apr-2021 Approved

DRAINAGE PIPES AND ACCESSORIES 16-Mar-2021 14-Jul-2021 Approved

BONDING AGENT 16-Mar-2021 22-May-2021 Approved

FORM REALESE AGENT 16-Mar-2021 22-May-2021 Approved

BITUMEN PAINT 16-Mar-2021 22-May-2021 Approved

JOINT SEALANT 16-Mar-2021 22-May-2021 Approved

REPAIRING CEMENT 16-Mar-2021 29-May-2021 Approved

PAINT SYSTEM FOR STRUCTURAL


STEEL MEMBERS (PRE ENGINEERED 30-Mar-2021 22-May-2021 Approved
BUILDING)

Apr 24, 2024 Al-Jazirah Industrial Projects 11


RAM APPROVAL STATUS
Date of Date of Status of
Description of Items
Submission Response RAM
PAINT SYSTEM FOR STRUCTURAL
STEEL MEMBERS (PRE ENGINEERED 30-Mar-2021 22-May-2021 Approved
BUILDING)

SPACER (COVER BLOCK) 03-April-2021 14-Mar-2021 Approved

UPVC PIPES AND FITTINGS (Duct Bank) 03-April-2021 9-May-2021 Approved

Approved with
GATCH MATERIAL 03-April-2021 06-Jun-2021
Comments
NON SHRINK CEMENTOUS GROUT
06-April-2021 29-May-2021 Approved
(WEBERTEC 304 VHS)
READY MIX CONCRETE SUPPLIER FOR
06-April-2021 26-May-2021 Approved
MIX DESIGN (C20 SRC& C35 SRC)

MASTER FLOW 18-April-2021 22-May-2021 Approved

WATER PIPES AND ACCESSORIES 22-April-2021 14-Jul-2021 Approved

BITULEX BOARD 27-April-2021 29-May-2021 Approved

Apr 24, 2024 Al-Jazirah Industrial Projects 12


RAM APPROVAL STATUS
Date of Date of Status of
Description of Items
Submission Response RAM
Awaiting
WOODEN DOORS AND ACCE 01-Jun-2021 06-Jun-2021
Approval
Approved with
SANITARY FIXTURES 08-Jun-2021 16-Aug-2021
Comments
Approved with
UNDERGROUND SEPTIC TANK 22-Jun-2021 28-Jul-21
Comments

TERRAZZO TILE 30-Jun-2021 19-Aug-21 Approved

PRE-MIXER CEMENTITIOUS FILLER-


04-July-2021 12-July-2021 Approved
WEBEREP 360FFR
19-Aug-21 Approved with
CARPET 08-July-2021
Comments
ALLUMINIUM DOORS,WINDOWS & Awaiting
10-July-2021 30-Aug-21
CURTAIN WALL Approval
Approved with
CARPET TILE 10-July-2021
Comments
Awaiting
WALL BASE / SKIRTING 12-July-2021
Approval

Apr 24, 2024 Al-Jazirah Industrial Projects 13


RAM APPROVAL STATUS
Date of Date of Status of
Description of Items
Submission Response RAM
CEMENT Board Partition Wall & Cladding Awaiting
16-Aug-21
Wall Approval

WOODEN DOORS AND ACCE 23-Aug-21 28-Aug-21 Rejected

Awaiting
PAINTING SYSTEM OF INTERNAL 25-Aug-21
Approval
WALL

25-Aug-21
OPC & SRC 30-Aug-21 Approved

Awaiting
TILE ADHESIVE & CEMENT GROUT 31-Aug-21
Approval
To be Submitted
Exhaust Fan

Resubmission
HVAC Unit 6-Mar-21 3-Aug-21 After Approval of
tech Query

Apr 24, 2024 Al-Jazirah Industrial Projects 14


RAM APPROVAL STATUS

Description of Items Status of RAM PO Status Delivery

GI Conduit Approved Done

Done
Earthing System Approved

Cable Trunking Approved Done

Wiring Devices Approved Done

CAT 6 Cable Approved Done Delivered

Light Fixtures Approved Done

Wires Approved Done Delivered

DATA TELECOM FACE PLATE Approved Done

FIRE ALARM FIELD DEVICES Approved Done

Apr 24, 2024 Al-Jazirah Industrial Projects 15


RAM APPROVAL STATUS

Description of Items Status of RAM PO Status Delivery

FIRE ALARM CABLE APPROVED DONE

DISTRIBUTION BOARDS APPROVED DONE

AWAITING
POWER CABLE
APPROVAL

THERMOWELD NR

Apr 24, 2024 Al-Jazirah Industrial Projects 16


MATERIAL LOG

Description of Items Status of RAM PO Status Delivery

Wall Partitions Approved Done Pending

Wall Cladding Gypsum Awaited

Awaited
Wall Cladding Cement

False Ceiling Rejected

Wooden Doors

Aluminum Doors and Windows Awaiting Approval Done Pending

Awaiting Approval
Paint

Awaiting Approval
Terrazo Tile

Awaiting Approval
Ceramic Tile

Apr 24, 2024 Al-Jazirah Industrial Projects 17


MATERIAL LOG

Description of Items Status of RAM PO Status Delivery

Vitrified Tile Awaiting approval

Awaiting approval
Carpet Tile

Awaiting approval
Carpet

Awaiting approval
Sanitary Fixtures

Bathing Area and Counter Type Wash Basin To Submit

Awaiting approval
Interlock and Kerbstone

Awaiting approval
Air Condition

Awaiting approval
Man Hole Covers

To Submit
Exhaust Fan

Apr 24, 2024 Al-Jazirah Industrial Projects 18


EQUIPMENT LOG

Description of Items Qty Status Remark

Crane 25 Ton 1 Working

1 Ton Roller 1 Working

Bob cat 1 Working

Bus 1 Working

SUV 1 Working

CAR 1 Working

Boom Truck 1 Working

Apr 24, 2024 Al-Jazirah Industrial Projects 19


MAJOR CONCERNS AND REQUIREMENTS

1. MISSING MATERIAL AND DOCUMENTS DELIVERY FROM KIRBY/CAPITOL


2. DELIVERY OF TRUNKING MATERIAL
3. DELIVERY OF GI CONDUIT AND ACCESSORIES
4. SUBMISSION OF RAM FOR EXHAUST FAN
5. MATERIAL APPROVAL FOR WOODEN DOORS
6. MATERIAL APPROVAL FOR FALSE CEILING

Apr 24, 2024 Al-Jazirah Industrial Projects 20


INVOICE

INVOICE SUMMARY KNPC MAA

As on 5-Sep-
21
Submission GROSS Invoice Amount Received Amount
Sl No Invoice No. Cumulative
Date Amount IN KD IN KD IN KD

1 INV-001 1-Apr-21 25,800.00

2 INV-002 11-Jul-21 23,458.00 15,480.00 13,071.31 13,071.31


3 INV-003 29-Jul-21 27,802.62 12,322.62 10,473.73 10,473.73

4 INV-004 31-Aug-21 74,820.00 46,956.00 39,649.65 39,649.65

Total Amount In KD 74,758.62 88,994.69 63,194.69

Apr 24, 2024 Al-Jazirah Industrial Projects 21


MAJOR MILESTONES & LOOK AHEAD PLAN
Description Current Status Planned
Completion
Excavation Completed
Building Foundation Completed
Plinth Beam Completed
Backfilling Partially Completed 2nd August 2021
Slab on Grade Zone-1 28th July 2021
Slab on Grade Zone -2 & 3 4th August 2021
Steel Structure Delivery Completed 4th August 2021
Steel Structure Erection Completed 30th August 2021
Sheeting Delivery Partially Completed 15th August 2021
Sheeting Erection On going 14th September 2021
Partition, Plumbing & Electrical Works 28th September 2021
Flooring Works 04th October 2021
Door and Windows 10th October 2021
False Ceiling & Painting 20th October 2021
Electrical & Plumbing Fixtures 30th October 2021
HVAC Works 30th October 2021
Outside Works 30th October 2021

Apr 24, 2024 Al-Jazirah Industrial Projects 22


END OF PRESENTATION