Chapter 4
Chapter 4
DEVELOPING A PROJECT
PLAN
DKV 40072 PROJECT MANAGEMENT
LEARNING OUTCOMES
The tool used for planning, scheduling, and monitoring project progress
The network is developed from the information collected for
the WBS and is a graphic flow chart of the project job plan
ACTIVITY An element of the project that requires time, may or may not
require resources
These various boxes or “nodes” are connected from beginning to end with
arrows to depict a logical progression of the dependencies between the
schedule activities
ACTIVITY-ON-NODE (AON)
Basic relationships that must be established for activities included in a
project network:
Which activities must be completed immediately before this activity? - Predecessor Activities
Which activities can occur while this activity is taking place? - Concurrent or Parallel Relationship
ACTIVITY-ON-NODE (AON) - Example
NETWORK COMPUTATION PROCESS
Forward Pass – Earliest Time
The forward pass requires three things when computing early activity times:
1. Add activity times along each path in the network (ES + DUR = EF)
2. Carry the early finish (EF) to the next activity where it becomes its early start (ES),
unless
3. The next succeeding activity is a merge activity. In this case select the largest early
finish number (EF) of all its immediate predecessor activities.
Backward Pass – Latest Time
1. Subtract activity times along each path starting with the project end activity
(LF — DUR = LS)
2. Carry the LS to the next preceding activity to establish its LF, unless 3
3. The next preceding activity is a burst activity; in this case select the smallest LS of all
its immediate successor activities to establish its LF
Slack / Float
Total slack tells the amount of time an activity can be delayed and not delay the project
The amount of time an activity can exceed its early finish date without affecting the
project end date or an imposed completion date
The critical path is the longest sequence of activities in a project plan which must be completed on
time for the project to complete on due date
An activity on the critical path cannot be started until its predecessor activity is complete; if it is
delayed for a day, the entire project will be delayed for a day unless the activity following the delayed
activity is completed a day earlier
The critical path is very useful in helping to manage any project. When the critical path has been
identified, it can clearly be seen where effort cannot be compromised. If any of the activities on the
critical path change, the end date of the project will be affected