Rule 11
Rule 11
PROTECTION OF
PEDESTRIANS DURING
CONSTRUCTION OR
DEMOLITION
TABLE OF CONTENTS
• 1101 - General Requirements
• 1102 - Storage in Public Property
• 1103 - Mixing Mortar on Public Property
• 1104 - Protection of Utilities
• 1105 - Walkway
• 1106 - Pedestrian Protection
• 1107 - Maintenance and Removal of Protective Devices
• 1108 - Demolition
SECTION 1101.
GENERAL REQUIREMENTS
1. No person shall use or occupy a street, alley or public
sidewalk for the performance or work covered by a building
permit except in accordance with the provisions of this Rule.
2. No person shall perform any work or any building/structure
adjacent to a public way in general use for pedestrian travel,
unless the pedestrians are protected as specified in this Rule.
3. Any material, building/structure temporarily occupying public
property, including fence, canopies and walkways, shall be
adequately lighted between sunset and sunrise.
SECTION 1102.
STORAGE IN PUBLIC PROPERTY
1. Materials and equipment necessary for work to be done under a permit when
placed or stored on public property shall not obstruct free and convenient
approach to and use of any fire hydrant, fire or police alarm box, utility box, catch
basin, or manhole and shall not interfere with any drainage of any street or alley,
gutter, and with the safe and smooth flow of vehicular and pedestrian traffic.
2. Materials to be stored at or near construction sites shall be piled or stacked in
an orderly manner to avoid toppling over or being otherwise displaced. No
materials shall be piled or stacked higher than 1.80 meters, except in yards or
sheds intended especially for storage. When piles exceed 1.20 meters in height,
the material shall be so arranged that the sides and ends of the piles taper back.
SECTION 1103.
MIXING MORTAR ON PUBLIC PROPERTY
● The mixing of mortar,
concrete, or similar
materials on public streets
shall not be allowed.
SECTION 1104.
PROTECTION OF UTILITIES
1. All public or private utilities and services above or below the ground shall be protected
from any damage by any work being done under the permit.
2. The protection shall be maintained while such work is being done and shall not obstruct
the normal functioning of any such utility.
3. Temporary Light and Power
a) Temporary wiring for light, heat and/or power shall be adequately protected against
mechanical or over-current failures. All conductive materials enclosing fixed or portable
electric equipment, or forming a part of such equipment, shall be properly grounded.
b) Temporary electric service poles shall be self-supporting or adequately braced or guyed
at all times.
SECTION 1105.
WALKWAY
1. When the Building Official authorizes a sidewalk to be fenced or closed, or in case there is no sidewalk in
front of the building/structure site during construction or demolition, a temporary walkway of not less than
1.20 meters shall be provided.
2. Such walkway shall be capable of supporting a uniform live load of 650.00 kilogram per sq.
meters.
3. Durable wearing surface shall be provided and must remain safe throughout the construction period.
4. Where the sidewalk is permitted by the Building Official to be fully occupied and fenced-off or enclosed, a
temporary walkway adjacent to the curb line shall be required. Where the street has no sidewalk, a
temporary walkway adjacent to the street line not less than 600 millimeters wide shall be provided.
Where the RROW is 5.00 meters or less, no temporary walkway shall be allowed.
5. Where only partial occupancy and fencing-off of the sidewalk is necessary, a temporary walkway will
not be required provided that a width of at least 600 millimeters of the sidewalk with protective
railing on road side shall be left open for the use of pedestrians.
SECTION 1106.
PEDESTRIAN PROTECTION
1. Where the walkway occupies part of the roadway or is adjacent to an excavation, protective railings
on the street side or on the side of the excavation shall be required.
2. Railings where required, shall be built substantially strong and sturdy and shall not be less than 1.00
meters in height.
3. Fences
Fences shall entirely enclose the construction/demolition site and shall be erected on the building side of
sidewalks or walkways and shall be made of approved materials (e.g. G.I. sheet, wooden boards and/or
planks, plywood or Lawanit, sawali), not less than 2.40 meters in height above the curb line. Fences shall
be built solid for its full length except for such openings as may be necessary for proper execution of the
work. Such openings shall be provided with doors, which shall be kept closed at all times except when in
actual use.
SECTION 1106.
PEDESTRIAN PROTECTION
a. When the horizontal distance between the outermost face of the building/structure area and the
inner edge of the sidewalk is more than one-half (1/2) the height of the building, a 2.40 meters
fence is required. (Figure XI.1.)
b. When the horizontal distance between the outermost face of the building and the inner edge of
the sidewalk is equal to or less than one-half (1/2) the height of the building, a canopy shall be
required in addition to a fence. (Fig. XI.2.)
4. Canopies
a. The protective canopy shall have a clear unobstructed height of 2.40 meters above the
walkway and shall be made of sufficient strength and stability to sustain safely the weight of
materials that may be placed thereon, and to withstand shocks incident to the handling of such
SECTION 1106.
PEDESTRIAN PROTECTION
materials or their preparation for use, and accidental jars from trucks passing or delivering
materials.
b. When the canopy is used for the storage of materials or for the performance of work of any kind,
substantial railings not less than 1.00 meters high and solid toe boards not less
than 300 millimeters high shall be placed along the street side and ends of the canopy. The
canopy shall be capable of safely sustaining a load of 4800 Pascal or the intended load to be
placed thereon, whichever is bigger.
c. The deck flooring of a canopy shall consist of planking not less than 50 millimeters in thickness,
closely laid. All members of the canopy shall be adequately braced and connected to resist
displacement of members or distortion of the framework.
SECTION 1106.
PEDESTRIAN PROTECTION
d. Canopies shall be constructed solid for its entire length except for such openings as may be
necessary for loading purposes. Such openings shall be kept closed at all times except during
actual loading operation.
e. Unless the top deck of the canopy is built solidly against the face of the building/structure to be
constructed/demolished, the vertical face of the canopy supports next to the building shall be
solidly fenced throughout, except for such openings as may be necessary for the execution of
work. Such openings shall be provided with sliding or swinging gates which shall be kept closed
at all times except when in actual use. (Figs. XI.3., XI.4., XI.5., XI.6.).
SECTION 1106.
PEDESTRIAN PROTECTION
PROTECTIVE
NETTING/COVERING
SECTION 1106.
PEDESTRIAN PROTECTION
b. All entrances/exits to
and from the construction/demolition
site shall be kept closed at all times
except during actual passage of men,
materials or equipment.
ENTRANCES/EXITS
SECTION 1106.
PEDESTRIAN PROTECTION
i. Gas welding and cutting and arc welding in construction/ demolition operations shall be
restricted to experienced workers accredited by the Technical Education Skills Development
Authority (TESDA). Suitable goggles, helmets and gloves shall be provided for and worn by
workers engaged in gas welding or cutting or arc welding. Incombustible shields shall be provided
to protect the workers when exposed to falling hot metal oxide.
ii. Gas welding or cutting or arc welding shall not be done above pedestrians and workers. When
unavoidable, an incombustible shield shall be provided between the work and workers below. A
watchman shall be stationed to give warning at places where pedestrians and workers, in the
course of their activity, are likely to pass under a gas welding or cutting or an arc welding
operation.
iii. Gas welding or cutting shall not be carried out in any place where ample ventilation is not
provided or from which quick escape is difficult. When unavoidable, workers engaged in such
work in confined spaces shall be allowed frequent access to fresh air. A relief worker shall be
stationed close at hand to assist the worker in case of accident and to shut off the gases.
iv. Tanks of fuel gas shall not be moved or allowed to stand for any extended period when not in
use unless the caps of such tanks are in place.
v. Suitable cradles shall be used for lifting or lowering oxygen or fuel tanks, to reduce to a
minimum the possibility of dropping tanks. Ordinary rope slings shall not be used.
vi. Tanks supplying gases for welding or cutting shall be located at no greater distance from the
work than is necessary for safety.
vii. Such tanks shall be securely fastened in place and in upright position. They shall be stored or
set in place for use so that they are not exposed to the direct rays of the sun or to high
temperature.
viii. Before steel beams or other structural shapes or elements of construction are cut by means
of a gas flame, they shall be secured by cables or chains to prevent them from dropping or
swinging.
ix. Where, in the course of demolition work, steel work or ironwork is being cut, released or
dismantled, all necessary precautions shall be taken to prevent danger from sudden twist, spring
or collapse.
d. Hoisting Machinery
i. Every hoisting engine shall be provided with adequate brakes capable of holding the maximum
load at any point of travel.
ii. Hoisting machinery shall be enclosed to exclude unauthorized persons. If placed outside the
building, further protection against falling objects shall be provided.
iv. Guards shall be provided with exposed gears and other moving parts and around
hoisting cables at all points to prevent workers from tripping or getting their clothing caught.
v. Ample room shall be provided around hoisting engines, motors or machineries or
apparatus to allow the free and safe movement of the operators.
vi. When hoisting machinery is set on an elevated platform, such platform shall be of
substantial and sturdy construction. Guardrails and toe boards shall be provided along all
open sides of such platform.
vii. Electrical machinery and equipment to be used for construction work shall be installed
and operated in accordance with the Philippine Electrical Code.
viii. Steam boilers used in construction work shall be installed, equipped and maintained in
accordance with the Philippine Mechanical Code. ix. A tag line or guide rope shall be used
on all loads being hoisted or lowered.
e. Platform Hoists
i. Platform hoists for the handling of materials in buildings under construction shall
have the car substantially constructed and provided with covers, either solid or wire
mesh.
ii. If suitable overhead protection is provided, the covers may be omitted.
iii. Hoists shall be equipped with a broken-rope safety device.
iv. Where wheelbarrows or buggies are used for handling material on platform hoists,
cleats shall be nailed to the platform to fix the proper position so that handles shall not
project beyond platform edges.
v. Supports for the overhead sheave of the hoist shall be designed to carry two (2)
times the weight of the hoist and its maximum load.
f. Hoist Towers
i. Hoist towers erected in connection with construction work shall be substantially
constructed. All members shall be so proportioned that the stresses shall not exceed
those specified for the material when carrying the dead load of the tower plus two
times the weight of the platform or bucket or its maximum load.
ii. Every hoist tower shall rest on a sufficiently solid foundation to prevent injurious
settlement or distortion of its framework.
iii. The base of every hoist tower shall be screened or otherwise protected on all sides
to a height of not less than 1.80 meters.
iv. Every hoist tower shall be secured in not less than four (4) directions against
swaying or tipping at intervals of not more than 10.00 meters in its height, by steel
cable guys adequately anchored or by other satisfactory means.
v. Such towers which are constructed adjacent to buildings shall be secured to
the building frame at each floor as the construction progresses.
vi. Hoist towers erected within the building, but not occupying the entire opening
through which they pass, shall be completely enclosed on all sides and shall be
provided with doors at the unloading points unless the platform hoist is solidly
enclosed on all sides to the height to which material is to be loaded or unloaded.
vii. Landing platforms in hoist towers or platforms connecting a hoist tower to a
building or other structure shall be provided with guardrails and toe boards.
g. Derricks and Cranes
i. Derricks shall be so designed and assembled that no part shall be stressed beyond
the safe working stress for the material under its maximum rated load in any possible
position. Such maximum load shall be conspicuously posted on each derrick.
ii. The foot-block of every derrick shall be firmly secured against motion in any
direction.
iii. Guy derricks shall have the top of the mast held by not less than six (6) steel guy
cables secured by firm anchorages and so placed that the angle of the guy with the
mast shall be as large as possible.
iv. The moving parts of derricks and cranes shall be kept well lubricated. All parts
shall be inspected at least every other day.
v. Use and operation of cranes shall be in accordance with Rule XIII.
vi. In the operation of cranes and similar devices, a standard signal system shall be
used and all men assigned to the operation of such equipment shall be fully
instructed on the signals.
h. Cables, Ropes, Chains and Blocks
i. All ropes and cables used in connection with scaffolds, derricks and hoisting
apparatus shall be tested before being put to use and at least once every thirty (30)
days while in use, to insure their safety and suitability for the purpose.
ii. Cables, ropes, chains and blocks shall be of such size that the maximum load
supported by them will not exceed one-sixth (1/6) of their breaking strength.
iii. Blocks designed for use with abaca ropes shall not be used for steel cables.
iv. Blocks used at or near floors or in other exposed places to change the direction of
cables shall be enclosed or otherwise effectively guarded.
v. Chains shall not be used for slings, bridles or other similar purposes, but shall be
restricted to only a straight pull.
vi. Hooks shall not be used for hoisting buckets, cages or skips.
i. Ladders and Temporary Stairways
i. Except where either permanent or temporary stairways or runways are required,
ladders shall be provided to give access to all floors, stagings or platforms where
work is being done more than five (5) storeys above ground or above a permanent or
temporary floor.
ii. Ladders shall not be extended by joining two (2) or more together. No single ladder
shall exceed 6.00 meters in length. When greater heights are to be reached,
intermediate platforms shall be erected.
iii. Ladder landings shall be at least 1.20 meters square and equipped with handrails
and toe boards.
iv. Ladder rungs shall be spaced uniformly and as near to 300 millimeters as
practicable.
v. Ladders leading to floors, stagings or platforms shall extend at least 900
millimeters above the level of such floors, stagings or platforms. vi. When used
temporarily in place of stairways or runways, ladders serving traffic in both directions
simultaneously shall be at least 1.00 meters wide. If separate ladders are provided for
going up and coming down, they shall be marked "UP" and "DOWN" respectively at
each floor and platform level.
viii. Ladders shall not be placed or used in shafts of operative elevators or hoists except
by workers engaged in the erection, construction, alteration or repair of any such shafts,
hoistways or equipment.
ix. Ladders shall not be painted, but may be oiled or treated with preservatives so as to
permit the detection of faults.
x. Every ladder shall be inspected by the superintendent or foreman in charge before
being put to use on a construction operation and thereafter at least once every thirty (30)
days while in continued use.
xi. Permanent stairways shall be installed in all buildings under construction as soon as
conditions will permit.
xii. When the work on a building has progressed to a height in excess of 18.00 meters and
it has not been practicable to install the permanent stairways, at least one temporary
stairway shall be provided for the full height and continued upward as rapidly as the work
progresses.
xiii. Stairs and stairways shall be of sufficient strength to support a load of at least 4800
Pascal. All stairways shall be guarded on all open sides with handrails and toe boards.
xiv. Temporary stairs shall be constructed so that treads and risers are uniform in width
and height in any one (1) flight.
xv. The sum of the height of the two (2) risers and the width of one (1) tread shall be not
less than 460 millimeters nor more than 700 millimeters.
xvi. Temporary stairways shall be not less than 900.00 millimeters wide.
xvii. Landings shall be not less than 750 millimeters long. No flight of stairs of temporary
stairways shall have a vertical rise in excess of 3.60 meters. Whenever necessary,
intermediate landings shall be provided.
xviii. Temporary and permanent stairways shall be adequately lighted.
xix. Permanent stairs that are to be used during construction and on which treads are to
be filled in later shall have wooden treads firmly fitted in place for the full area of the tread.
xx. The top surfaces of the temporary treads shall be maintained above the tops of the
risers or nosings.
xxi. No door shall open directly onto a flight of stairs, but a landing equal at least the width
of the door shall be provided between the door and the stairs.
9. Chutes
a. Chutes for the removal of materials and debris shall be provided in all
parts of demolition operations, which are more than 6.00 meters above
the point from which material is to be removed. Chutes shall be so
situated and constructed so as not to pose any danger to the public or to
workmen.
9. Chutes
c. Chutes which are at an angle of more than 45 degree from the horizontal shall be completely
enclosed on all four (4) sides, except for openings at or about floor level at each floor, for the
receiving of materials or debris.
d. Chutes at an angle of less than 45 degree with the horizontal may be left open on the upper side.
However, where such a chute discharges into another chute steeper than 45 degree with the
horizontal, the top of the steeper chute shall be covered at the junction point of the two (2) chutes to
prevent the spillage of materials or debris.
e. Openings into which materials or debris are dumped at the top of a chute shall be protected by a
substantial guardrail extending at least 1.80 meters above the level of the floor.
f. At chute openings where materials or debris are dumped from wheelbarrows, a toe board or
bumper not less than 150 millimeters high and 50 millimeters nominal thickness shall be
provided.
SECTION 1108. DEMOLITION
9. Chutes
g. Any space between the chute and edges of floor openings through which the chute passes shall
be solidly planked over.
h. Chutes, as well as floors, stairways and other places, shall be effectively wet down at frequent
intervals, whenever the dust from demolition operations would cause a menace or hardship to
residents of adjoining buildings or premises.
i. The bottom of each chute shall be equipped with an adjustable gate or stop for regulating the flow
of materials.
j. Except when in actual use in the discharge of materials, the gate or stop shall be kept closed. A
reliable person shall be designated to control the gate and the backing up and loading of trucks. He
shall see to it that no person is allowed to stand or pass under the discharge end of the chute at any
time.
SECTION 1108. DEMOLITION
9. Chutes
k. The area at the discharge end of each chute shall be completely enclosed with a substantial fence
at all times or otherwise made inaccessible. A danger sign shall be placed at the discharge end of
every chute.
SECTION 1108. DEMOLITION
d. No walls or section of walls whose height is more than twenty-two (22) times its thickness shall
be permitted to stand without lateral bracing unless such wall is in good condition and was originally
designed to stand to a greater height without such lateral support.
e. Workmen shall not be permitted to work on top of a wall when weather conditions constitute a
hazard.
f. Before demolishing any interior or exterior wall which is within 3.00 meters of any opening in the
floor immediately below, such opening shall be substantially planked over unless all workmen are
removed from all floors below and access to such floors is positively prevented.
g. At the completion of each day’s work, all walls undemolished shall be left stable and in no danger
of overturning or falling.
SECTION 1108. DEMOLITION
h. Foundation walls which serve as retaining walls to support earth and adjoining structures shall not
be demolished until such adjoining structures have been underpinned or braced, and earth either
removed or supported by sheet piling or other suitable materials.
i. In the demolition of brick and/or masonry chimneys which cannot safely be toppled or dropped, all
materials shall be dropped down through the inside of such chimneys.
j. The loading point at the discharge end chute, at or near the bottom of a chimney, shall be
completely protected by means of any overhead timber canopy.
k. To enable workmen to reach or leave their work on any wall or scaffold, walkways shall be
provided. Such walkways shall not be less than three (3) planks, properly tied or nailed to bearers
of not less than 560 millimeters in width, such that the planks do not deflect more than 50
millimeters under normal loading.
SECTION 1108. DEMOLITION
l. In buildings of skeleton construction, the steel framing may be left in place during the demolition of
masonry work. When this is done, all steel beams, girders and the like shall be cleared of all loose
materials as the demolition progresses.
SECTION 1108. DEMOLITION
e. Where workmen are engaged in the removal of floors, planks of ample strength which are
supported independently of the flooring shall be provided for the workmen to step on. The planks
shall be so placed as to give the workmen a firm support in case the floor gives way or collapses
unexpectedly. Where it is necessary for a workman to straddle a space between two planks, such
space shall not exceed 400 millimeters. To enable workmen to reach any workplace without the
necessity of walking on exposed beams, planks shall be provided to serve as catwalks.
f. Planks used for temporary protection shall be sound, and at least 25 millimeters thick. They
shall be laid close together, with the ends overlapping by at least 100 millimeters over solid
bearings to prevent tipping under a load.
g. Where floors are being removed, no workmen shall be allowed to work in the area directly
underneath. Such areas shall be barricaded to prevent access to it.
SECTION 1108. DEMOLITION
h. Structural or load-supporting members at any floors shall not be cut or removed until all stories
above that floor have been demolished and removed.
i. Where any floor has been removed, the entire tier of beams on which any device is supported
shall be completely planked over, except for such openings as are required for the handling of
materials or equipment.
j. Stairs and stair railings shall be kept in place and in usable condition as long as it is practicable.
k. Steps and landings shall be kept free from debris and obstructions.
SECTION 1108. DEMOLITION
a. Where applicable, the Building Official shall require strict compliance with the minimum safety
standards as prescribed under Administrative Order of DOLE. The construction, alteration and
removal of scaffolds and the application, installation and setting up of safeguard devices shall be
done by skilled workmen under the supervision of a person, qualified by experience or training for
such work.
c. Scaffolds, ladders, stairs, fuel gas tanks and other devices or equipment falling within the scope of
this Rule shall be maintained in a good, safe and usable conditions as long as in use.
SECTION 1108. DEMOLITION
d. Scaffolds, temporary floors, ramps, stairway landings, stair treads, and all other walkway surfaces
shall be kept free from protruding nails/splinters.
e. Protruding nails and tie wire ends shall be removed, hammered in or bent in a safe condition.
f. Electric lines, moving ropes and cable gears, or similar hazards with which a person might come in
contact with shall be encased or protected.
g. No person, firm or corporation, either personally or through an employee or agent of another, shall
operate or move any machinery, equipment, materials, scaffolds, closer than 5.00 meters to any
energized high voltage overhead electrical facilities unless authorized by the Electrical Inspector.
h. All workmen on any demolition job shall be required to wear industrial safety helmets and body
protective gears.
SECTION 1108. DEMOLITION
i. Construction sheds and toolboxes shall be so located as to protect persons from dangerous falling
walls and objects.
j. The Building Official may permit the use of alternative methods and/or devices depending on local
conditions provided that the minimum standard of safety sought to be achieved under this Rule is
not jeopardized.
k. In Fire Zones of Types I, II and III Construction, only heaters with enclosed flames shall be used
for the heating of any roofing or other similar materials.
l. Wherever any enclosed flame heaters or open fires are used, there shall be a workman in
constant attendance, whose duty shall be to have such heater or fire under proper control at all
times.
SECTION 1108. DEMOLITION
12. Other Safeguards
m. In all buildings in which standpipes are required, such standpipes shall be installed as the
construction progresses in such a manner that they are always ready for Fire Department use, to the
topmost constructed floor. Such standpipes shall be provided with a Siamese twin dry standpipe
outside the building and with one (1) outlet at each floor connected to a fire hose cabinet.
n. In every construction operation, wherever a tool house, storeroom or other shanty is built or a
room or space is used for storage, dressing room or workshop, at least one (1) approved hand
pump, tank or portable chemical or dry powder fire extinguisher shall be provided and maintained in
an accessible location.
o. During construction operations, free access from the street to fire hydrants and to outside
connections for standpipes, sprinklers or other fire extinguishing equipment, whether permanent or
temporary shall be provided and maintained at all times. No material or construction equipment shall
be placed within 3.00 meters of such hydrant or connection, nor between it and the centerline of
the street.
SECTION 1108. DEMOLITION
12. Other Safeguards
p. Toilet facilities at the construction/demolition site, as an ancillary to the bunkhouse and operation,
shall be maintained in a clean/sanitary condition for the use of the workers.
q. Supply of potable water and sanitary washing facilities shall be provided for workers’ and other
uses during workdays.
s. Unless competent medical attention is quickly available, where more than two hundred (200)
workers are employed, a properly equipped first-aid room shall be provided, and a physician or
competent nurse shall be in constant attendance.
SECTION 1107. Maintenance and Removal of Protective Devices
1. Maintenance. All protective devices shall be properly maintained in place kept in good order for the entire length of time pedestrians
may be endangered.
ii. In passageways, stairways and corridors, the average light intensity measured at floor level shall be not less than 200
LUX. At locations where tools and/or machinery are used, the average light intensity measured at floor level shall be not less than 500
LUX.
ii. shall not be done above pedestrians and workers. A watchman shall be stationed to give warning at places where
pedestrians and workers, in the course of their activity, are likely to pass under a gas welding or cutting or an arc welding operation.
iii. shall not be carried out in any place where ample ventilation is not provided or from which quick escape is difficult.
iv. Tanks of fuel gas shall not be moved or allowed to stand for any extended period when not in use unless the caps of such
tanks are in place.
v. Suitable cradles shall be used for lifting or lowering oxygen or fuel tanks, to reduce to a minimum the possibility of
dropping tanks. Ordinary rope slings shall not be used.
vi. Tanks supplying gases for welding or cutting shall be located at no greater distance from the work than is necessary for
safety.
vii. Such tanks shall be securely fastened in place and in upright position. They shall be stored or set in place for use so that
they are not exposed to the direct rays of the sun or to high temperature.
viii. Before steel beams or other structural shapes or elements of construction are cut by means of a gas flame, they shall be
secured by cables or chains to prevent them from dropping or swinging.
ix. Where, in the course of demolition work, steel work or ironwork is being cut, released or dismantled, all necessary
precautions shall be taken to prevent danger from sudden twist, spring or collapse.
ii. Construction sheds, construction materials and equipment shall be secured by guying, shoring, or by tying down.
iii. Where a full complement of personnel is employed or engaged for such protection purposes, in accordance with warnings or
advisories issued by the (PAGASA).
d. Hoisting Machinery
i. Every hoisting engine shall be provided with adequate brakes capable of holding the maximum load at any point of travel.
ii. Hoisting machinery shall be enclosed to exclude unauthorized persons. If placed outside the building, further protection
against falling objects shall be provided.
iii. Guards shall be provided with exposed gears and other moving parts and around hoisting cables at all points to prevent
workers from tripping or getting their clothing caught.
iv. Ample room shall be provided around hoisting engines, motors or machineries or apparatus to allow the free and safe
movement of the operators.
v. When hoisting machinery is set on an elevated platform, such platform shall be of substantial and sturdy construction.
Guardrails and toe boards shall be provided along all open sides of such platform.
vi. Electrical machinery and equipment to be used for construction work shall be installed and operated in accordance with
the Philippine Electrical Code.
vii. Steam boilers used in construction work shall be installed, equipped and maintained in accordance with the Philippine
Mechanical Code.
viii. A tag line or guide rope shall be used on all loads being hoisted or lowered.
e. Platform Hoists
i. Platform hoists for the handling of materials in buildings under construction shall have the car substantially constructed
and provided with covers, either solid or wire mesh.
iv. Where wheelbarrows or buggies are used for handling material on platform hoists, cleats shall be nailed to the platform to
fix the proper position so that handles shall not project beyond platform edges.
v. Supports for the overhead sheave of the hoist shall be designed to carry two (2) times the weight of the hoist and its
maximum load.
f. Hoist Towers
i. Hoist towers erected in connection with construction work shall be substantially constructed.
iii. Every hoist tower shall be secured in not less than four (4) directions against swaying or tipping at intervals of not more
than 10.00 meters in its height, by steel cable guys adequately anchored or by other satisfactory means.
iv. Such towers which are constructed adjacent to buildings shall be secured to the building frame at each floor as the
construction progresses.
v. Hoist towers erected within the building, but not occupying the entire opening through which they pass, shall be completely
enclosed on all sides and shall be provided with doors at the unloading points unless the platform hoist is solidly enclosed on all sides to
the height to which material is to be loaded or unloaded
vi. Landing platforms in hoist towers or platforms connecting a hoist tower to a building or other structure shall be provided
with guardrails and toe boards.
g. Derricks and Cranes
i. Derricks shall be so designed and assembled that no part shall be stressed beyond the safe working stress for the material
under its maximum rated load in any possible position. Such maximum load shall be conspicuously posted on each derrick.
ii. The foot-block of every derrick shall be firmly secured against motion in any direction.
iii. Guy derricks shall have the top of the mast held by not less than six (6) steel guy cables secured by firm anchorages and
so placed that the angle of the guy with the mast shall be as large as possible.
iv. The moving parts of derricks and cranes shall be kept well lubricated. All parts shall be inspected at least every other day.
v. Use and operation of cranes shall be in accordance with Rule XIII (RULE XIII - ELECTRICAL AND MECHANICAL
REGULATIONS)
vi. In the operation of cranes and similar devices, a standard signal system shall be used and all men assigned to the
operation of such equipment shall be fully instructed on the signals.