Module 1 - Planning
Module 1 - Planning
Planning- a thinking process that determines the course of action to be taken to achieve a specific
purpose/goal
Planning involves the breakdown of the project into definable, measurable, and identifiable
tasks/activities, and then establishes the logical interdependences among them.
“THERE IS NEVER A PLAN TO FAIL, BUT FAILURE IS GUARANTEED WITHOUT PLANNING”
Generally, planning answers these main questions:
What is to be done?
How to do it?
Who does it?
When must it be done
How much will it cost?
The answers are then used to decide when to employ the available resources of men, materials,
machines, methods and money.
Then decisions are made in the light of objectives and the best standards of cost, profit and time.`
TASK Example: Question 1 Example: Question 2 Is there an alternative?
Machine and work space Where is the work to be Why there? Can it be done
performed? anywhere else?
Method How should the work be Why that way? Would another way be
performed? more effective?
Money What money is required? When will it be required? Can other arrangements
be made?
Planning Objectives
Page 10
It is broadly accepted that among the main characteristics of an effective plan are that:
it is based on clearly defined objectives
it is simple
it establishes standards
it is flexible
it is balanced
it uses available resources to the utmost.
Planning is an executive function which helps to provide purpose and direction for the members of an
organisation.
Obstacles to effective planning
All of us are used to making plans, even if it's just for a future social gathering or a yearly vacation. However,
planning done by an individual is probably going to be easier than planning done by even a small builder, let alone
a company with locations all over the world.
External forces such as laws, government regulations, trade associations and the actions of competitors may
impede or influence the effectiveness of planning.
Managers frequently fall short of the planning standards required for maximum productivity. Given that many
circumstances that result in inadequate planning are outside of their control, this is not wholly their fault. Managers
may, however, make their planning better by first comprehending the challenges and then taking deliberate action
to lessen their impact.
Pre-Tender Planning
A duration of 21 days min is allowed between tender advert and tender opening.
What happens during that time? Pre-Tender planning
Tendering is a vital part of the company’s activities. It is therefore important to plan the tender properly
and to carry out a systematic scrutiny of the tender documents - irrespective of project size,
contract/tender form and the extent of ‘own production’.
Objectives:
Reduce, or eliminate the risk of inaccurate opinions influencing decisions which affect the pricing
of the Tender
To identify construction methods
To assess method related items which affect tender price
To aid the build up of contract preliminaries and plant expenditure
To aid the tendering process
(See tender advert)
Pre-Tender Planning Steps:
1. Decision to tender:
Tender Qualification: CIDB Grading, BBBEE, Tax Clearance certificate, H&S certificates etc.
Site visit/briefing- compulsory or not? (See briefing example)
Technological factors
Contractual factors- Upon reception of the tender documents, the contractor analyses the documents
in order to identify any conditions that may not be expedient to the main contractor.
Legal factors- zoning, Heritage sites etc. (regulations in the area)
Economical factors- is it worth investing in this project (competitiveness)
Financial factors- profit, availability of reserve funds
Resource factors- check availability of resources and what can be done
Public relations- so company can be known
Political factors- what is governments focus?
any possibility of strikes?
any possibility of clashes with community organisations?
5. Method statement
It describes how each work task is to be performed and analyses the different methods of doing that
item of work.
It is submitted together with other tender documents when tendering for a project.
It becomes part of the contract documents that serve as a basis for agreement between the client and
contractor when tender is awarded.
Important for programming pricing
Determining plant and
Labour requirements
Objectives of method statement:
Predict anticipated project quality, risk, health and safety and environmental requirements.
Assess the adequacy of the stipulated project time stated by the contractor and contractor’s
knowledge of planning
Gives the client an ability to assess the contractor’s knowledge/know-how of the project
Determines how realistic the contractors bid is
Record agreed intentions with the client
Critical aspects of method statement preparation:
The methodology i.e. a brief description of how the activity is to be done
Duration estimation
Operational Sequence (Networks)
Work program (Gantt/Bar charts)
Labour/plant requirement (resources)
Cost/Pricing (most cost-effective method)
Pre-requisites of a method statement
Scope of work(BOQ)
Contract/work duration
Site inspection report
Site location, resource availability, area regulations, level of skills, soil conditions etc
Work productivity/output rates
Method statement must meet the project performance requirements of:
Quality (specified standards)
Time (within schedule)
Cost (within budget)
Health, safety and environment record (safety first)
Risk mitigation
Construction approach/method
2 main types:
Labour intensive/based method- By hand using small tools/equipment
Capital/equipment intensive method- Mechanically using heavy plant & equipment
Ensure Compliance of method statement with the following:
Contract Method Specifications
SANS 2001 Series
Contract Conditions:
GCC 2010
Construction health & safety standards
OHSA/Construction Regulations
Construction code of practice
(SAFCEC/CIDB/MBSA/NHBRC/EPWP)
“Successful projects are those with zero lost time and injuries at completion”
Management techniques used to prepare a construction method statement are the basic planning
functions of:
Planning
Forecasting
Organising
Method statement preparation:
Traditionally the method statement was presented in tabular form with seven columns, however
nowadays the number of columns is determined by the use and purpose of the method statement.
(may include health and safety requirements, identified risks etc.)
See table on Page 18
This made up of a sequence of construction Operations
Example: Activity: pipe trench excavation
Construction method- labour intensive
Construction operations:-E.L.H.U.D.
Excavate
Load
Haul
Unload
Dispose
Activity:
Excavation and dispose at a distance not exceeding 50m
Method statement/Methodology: 3 operations:
Exc. by hand using hand-held tools such as shovels/spades, fork/fork hoe.
Load exc. material by hand into wheelbarrows.
Haul & dispose by wheelbarrows at a distance not exceeding 50m.
Labour Output rates Per Hour for Construction Operations (Reproduced)
Example of method statement:
1. Excavation
Description: Excavate trench to receive foundation wall footings (10m 3 assumption)
Methodology:
Excavation
Excavate manually using hand-held tools such as picks, shovels etc. (soil quality)
or
Excavate using plant such as back-actor (depending on scope and volume of work)
Disposal
Load excavated material manually or mechanically into mechanical transport (dumpers, lorries)
or
Manual transport (wheelbarrow)
METHOD STATEMENT
CONTRACT TENDER NO: XXX
Operation No. Operation Quantity Method Sequence of Operations Plant & Labour Output Labour
mark area to be excavated,
excavate using picks and
shovels. Excavated material to
be heaped next to trench, 1Skilled
manual excavation for loaded into wheelbarrows and pick, shovels, and 8
1 Excavation 10m3 trenches transported to dump site wheelbarrows 2.7m3/h unskilled
2.
Concrete foundation footing
Description: Vibrated reinforced concrete 1:2:4 in foundation footing
Methodology: concrete operations will include the following
batching
Mixing
Transporting
Placing and
Curing
METHOD STATEMENT
CONTRACT TENDER NO: XXX
Operation No. Operation Quantity Method Sequence of Operations Plant & Labour Output Labour
A 'time-related charge' is for work, the cost of which is to be considered dependent on duration.
This is as opposed to a 'fixed charge', which is for work, the cost of which is to be considered independent
of duration.
Time-Related Items
O& M of site facilities( Contractors and Engineers offices)
Site Supervision(Supervisor)
Security/Lighting
Welfare and safety provisions( Toilets/Kitchen)
Site transport services/Travel Expenses(Operators)
Site accommodation
Water
Head office charges,
Employment of CLO/Labour Officer
Add profit & overheads(%) on employment of CLO/Labour officer
Priced on a TIME-BASIS(price per month/day/weeks)
Specified Provisional Sums( SPS)
Are estimates of additional work that have a high likelihood of being required but were not
quantified at the time the Bill of Quantities was drawn up.
Cost of work which at the tender stage has not been sufficiently defined to enable it to be priced
by tenderers. Eg. water supply, piling etc.
Cost of work to be done by specialist firms/sub-contractors eg. geotechnical investigations by
geotechnical engineers, Setting out, supply
of Mechanical plant and hoisting, Scaffolding and gantries
Provisional sums are a way of adding some extra money to the construction budget.
The work itself is only undertaken on instruction from the Engineer.
It may or may not be carried out by the contractor
QC & QA Inspections and testing
A LUMPSUM is written into the Bill.
Contractor only tenders a % of the Lumpsum for overheads, attendance charges and profit.
Prime costs (PC)
Are fixed sums added to the Bill to compensate for delays incurred on items (like special
materials, services by local authorities, items with a long delivery lead time) normally
ordered by the Client and that are to be paid for through the contract and may be installed
by the Contractor.
The Prime Cost is shown as a LUMPSUM in the Bill
Contractor is asked to tender a % of the lumpsum to cover his overheads, charges and profit+ a sum
for the transport, plant and labour needed to install the item.
Day works
Method of valuing work on the basis of time spent by the workmen, materials used and the
plant employed
Is a work or material item which cannot in terms of the contract be measured in terms of
dimensions.
Has to be measured in terms of time and cost eg. dewatering
A day work schedule is often included.
– A schedule of rates(cost/unit) for the various types of labour, plant and materials that may
be used.
The Contractor is asked to price the day work schedule, or a % (to cover his overheads,
charges and profit) to be added to actual costs of labour, materials and plant.
Temporary Works/Items
Coffer dams and access roads
Notice Boards
Road Signs
Fencing
Temporary utility lines connections
Temporary services and reinstatement
Public Services – electric, gas, telephones, fees and rates
Temporary water installations
Priced as a LUMPSUM
Environmental Management
The cost of additional works not covered elsewhere required to ensure compliance with the EMP
and Record of Decision
Priced as a LUMPSUM