10 Time and Work
10 Time and Work
Contents
1.Introduction
2.Basic Concepts
3.Rules and Tricks
4.Practice Questions
1. Introduction:
Time and Work problems are most
frequently asked problems in quantitative
aptitude. To solve these problems very
quickly, you should understand the concept
of Time and Work and some shortcut
methods.
Before starting:
Example:
If A can repair 50 cycles in 5 days then A can
repair 50/5 = 10 cycles in one day.
Rule 3:
If A can do a piece of work in X days and B can
do the same work in Y days, then both of them
working together will do the same work in
XY days.
X+y
Example:
If A can do a piece of work in 10 days and B can do the
same work in 15 days then how long will they take if
they both work together?
Solution 1:
A can finish the work in D1 = 10 days.
B can finish the work in D2 = 15 days.
A and B working together = D1 * D2
D1 + D2
= 10 * 15/ 10 + 15
= 150/25 = 6 days.
Solution 2: (UNITARY METHOD)
Let the total work be assumed as LCM(10,15)= 30 Units
Ans: D
2. A can do a work in 15 days and B can do it in
18 days. With the help of C, all of them
complete the work In 6 days. How long will it
take C to finish the work alone?
a)30 days
b)45/2 days
c)90/2 days
d)40 days
Ans: B
3. A can do a work in 15 days and B can do it in 18
days. With the help of C, all of them complete the
work In 6 days. A, B and C received total Rs.27,000
for the whole work. What is the share of C, If the
money is distributed in the ratio of amount of
work done, individually?
a)2700
b)14400
c)7200
d)6300
Ans: C
4. A can do 1/3rd of a work in 5 days and B can
do 2/5th of the work in 10 days. In how many
days both A and B together can do the work?
a)13 2/3 days
b)9 3/8 days
c)18 5/8 days
d)13 days
Ans: B
5. Ram can do a piece of work in 14 days, while Rani
can do the same work in 21 days. They started the
work together but 3 days before the completion of
the work, Ram left the work. The total number of
days to complete the work is:
a)7
b)8.5
c)5
d)10.2
Ans: D
6. A piece of work can be done by A and B in 10 days,
by B and C in 15 days and by C and A in 30 days. All
three worked for 6 days and then A withdrew. B and C
worked for another 4 days and then B stopped
working. How many more days will C take to complete
the remaining work?
a)12
b)12.5
c)10.33
d)10
Ans: D
7. A can finish a work in 24 days, B in 9 days and
C in 12 days. B & C start the work but are forced
to leave after 3 days. The remaining work done
by A in:
a)10
b)12.5
c)20
d)7
Ans: A
8. A alone can complete a work in 16 days and B
alone can complete the same in 12 days. Starting
with A, they work on alternate days. The total
work will be completed in how many days?
a)12 days
b)12 ½ days
c)13 ¾ days
d)13 days
Ans: C
9. Fatima and Zahira can do a piece of work in 12
days and 15 days respectively. If they work for
alternate day and Fatima starts the work first, then
in how many days the work will be completed?
a)12 1/5 days
b)13 ¼ days
c)13 1/5 days
d)15 days
Ans: B
10. Manoj and Harvinder can complete a piece of
work in 16 days, which Harvinder can complete in
32 days. If Manoj & Harvinder work on alternate
days, starting with Harvinder, in how much time
would the work be completed?
a)16 days
b)17 days
c)32 days
d)None of these
Ans: C
11. A can do a piece of work in 36 days, B in 54 days
and C in 72 days. All three began the work together
but A left after 8 days and B left 12 days before the
completion of the work. Total number of days to
complete the work?
a)25 2/11 days
b)30 6/7 days
c)30 days
d)28 days
Ans: B
12. 45 men complete a piece of work in 30 days
working 12 hours a day. In how many days will
60 men complete the work if working 10 hours a
day?
a)27 days
b)30 days
c)24 days
d)22 days
Ans: A
13. 45 men can complete a work in 16 days. Six
days after they started working, 30 more men
joined them. How many days will they now take
to complete the remaining work?
a)4
b)5
c)6
d)7
Ans: C
14. If 7 maids with 7 mops cleaned 7 floors in 7
hours, how long would it take 3 maids to mop 3
floors with 3 mops?
a)3 hours
b)7/3 hours
c)49/3 hours
d)7 hours
Ans: D