Lecture 7 Project Cost MGT
Lecture 7 Project Cost MGT
9
Types of Cost Estimates
Type of Estimate When Done Why Done How Accurate
Rough Order of Very early in the Provides rough –25%, +75%
Magnitude project life ballpark of cost
(ROM) cycle, often 3–5 for selection
years before decisions
project
completion
Budgetary Early, 1–2 years out Puts dollars in –10%, +25%
the budget plans
Definitive Later in the project, Provides details for –5%, +10%
< 1 year out purchases, estimate
actual costs
• A ROM estimate that actually cost $100,000 would range between $75,000 to $175,000.
• A budgetary estimate that actually costs $100,000 would range between $90,000 to
$125,000.
• A definitive estimate that actually costs $ 100,000 would rang between $95,000 to
10 $110,000.
Cost Estimation Tools and Techniques
12
Project managers must negotiate with project sponsors to
create realistic cost estimates
Cost Budgeting
15
Earned Value Management (EVM)
EVM.
16
Earned Value Management
18
work accomplished?
Earned Value Management Terms
⚫ Planned value (PV), formerly called the budgeted cost of
work scheduled (BCWS), also called the budget, is that portion of
the approved total cost estimate planned to be spent on an activity
during a given period.
⚫ Actual cost (AC), formerly called actual cost of work performed
(ACWP), is the total of direct and indirect costs incurred in
accomplishing work on an activity during a given period.
⚫ Earned value (EV), formerly called the budgeted cost of work
performed (BCWP), is the percentage of work actually
completed multiplied by the planned value
19
Earned Value Formulas
TERM FORMULA
Schedule Variance SV = EV – PV
To estimate what it will cost to complete a project or how long it will take
based on performance to date, divide the budgeted cost or time by the
appropriate index.
20
Rules of Thumb for EVA
Numbers
⚫ Negative numbers for cost and schedule variance indicate problems
in those areas.
⚫ The project is costing more than planned or taking longer than planned
⚫ Zero variance shows that the project is running according to the plan
its plan
21
Exampl
e⚫ Suppose you have a software project which is planned to
be completed in 9 months with a budget of Birr
900,000.
⚫ After a month,10% of the project is completed at a
total expense of Birr 100,000, but the planned
completion was 15%.
⚫ Given:
⚫Budget At Complete (BAC) = Birr 900,000
⚫AC = Birr 100,000
22
Compute
a) PV
b) EV
c) CV - interpretation
d) SV - interpretation
e) CPI - interpretation
f) SPI - interpretation
g) Forecast -Budget at complete
h) Forecast - Time at complete
i) Overall project’s traffic light
status
23
…solution
Warning
[0.94 -
Bad
29
Yello 0.85]
⚫Therefore, for the above example,
overall
project’s traffic light status is
= (CPI+SPI)/2
= (0.90+0.67)/2
= Bad
0.78
30
31