Risk Management
copyright © 1996, 2001, 2005
R.S. Pressman & Associates, Inc.
1
Project Risks
What can go wrong?
What is the likelihood?
What will the damage be?
What can we do about it?
2
Reactive Risk Management
project team reacts to risks when they occur
mitigation—plan for additional resources in
anticipation of fire fighting
fix on failure—resource are found and applied when
the risk strikes
crisis management—failure does not respond to
applied resources and project is in jeopardy
3
Proactive Risk Management
formal risk analysis is performed
organization corrects the root causes of risk
4
Seven Principles
Maintain a global perspective—view software risks within the context of system and
the business problem
Take a forward-looking view—think about the risks that may arise in the future;
establish contingency plans
Encourage open communication—if someone states a potential risk, don’t discount
it.
Integrate—a consideration of risk must be integrated into the software process
Emphasize a continuous process—the team must be vigilant throughout the software
process, modifying identified risks as more information is known and adding new
ones as better insight is achieved.
Develop a shared product vision—if all stakeholders share the same vision of the
software, it likely that better risk identification and assessment will occur.
Encourage teamwork—the talents, skills and knowledge of all stakeholder should be
pooled
5
Risk Management Paradigm
control
track
plan
RISK identify
analyze
6
Risk Identification
Product size—risks associated with the overall size of the software to be built
or modified.
Business impact—risks associated with constraints imposed by management or
the marketplace.
Customer characteristics—risks associated with the sophistication of the
customer and the developer's ability to communicate with the customer in a
timely manner.
Process definition—risks associated with the degree to which the software
process has been defined and is followed by the development organization.
Development environment—risks associated with the availability and quality of
the tools to be used to build the product.
Technology to be built—risks associated with the complexity of the system to be
built and the "newness" of the technology that is packaged by the system.
Staff size and experience—risks associated with the overall technical and project
experience of the software engineers who will do the work.
7
Assessing Project Risk-I
Have top software and customer managers formally
committed to support the project?
Are end-users enthusiastically committed to the project
and the system/product to be built?
Are requirements fully understood by the software
engineering team and their customers?
Have customers been involved fully in the definition of
requirements?
Do end-users have realistic expectations?
8
Assessing Project Risk-II
Is project scope stable?
Does the software engineering team have the right mix
of skills?
Are project requirements stable?
Does the project team have experience with the
technology to be implemented?
Is the number of people on the project team adequate to
do the job?
Do all customer/user constituencies agree on the
importance of the project and on the requirements for
the system/product to be built?
9
Risk Components
performance risk—the degree of uncertainty that the
product will meet its requirements and be fit for its
intended use.
cost risk—the degree of uncertainty that the project
budget will be maintained.
support risk—the degree of uncertainty that the resultant
software will be easy to correct, adapt, and enhance.
schedule risk—the degree of uncertainty that the project
schedule will be maintained and that the product will be
delivered on time.
10
Risk Projection
Risk projection, also called risk estimation, attempts to rate
each risk in two ways
the likelihood or probability that the risk is real
the consequences of the problems associated with the risk,
should it occur.
The are four risk projection steps:
establish a scale that reflects the perceived likelihood of a risk
delineate the consequences of the risk
estimate the impact of the risk on the project and the product,
note the overall accuracy of the risk projection so that there will be
no misunderstandings.
11
Building a Risk Table
Risk
Mitigation
Monitoring
&
Management
12
Building the Risk Table
Estimate the probability of occurrence
Estimate the impact on the project on a scale of 1
to 5, where
1 = low impact on project success
5 = catastrophic impact on project success
sort the table by probability and impact
13
Risk Exposure (Impact)
The overall risk exposure, RE, is determined using the
following relationship [HAL98]:
RE = P x C
where
P is the probability of occurrence for a risk, and
C is the cost to the project should the risk occur.
14
Risk Exposure Example
Risk identification. Only 70 percent of the software components
scheduled for reuse will, in fact, be integrated into the application.
The remaining functionality will have to be custom developed.
Risk probability. 80% (likely).
Risk impact. 60 reusable software components were planned. If
only 70 percent can be used, 18 components would have to be
developed from scratch (in addition to other custom software that
has been scheduled for development). Since the average component
is 100 LOC and local data indicate that the software engineering
cost for each LOC is $14.00, the overall cost (impact) to develop the
components would be 18 x 100 x 14 = $25,200.
Risk exposure. RE = 0.80 x 25,200 ~ $20,200.
15
Risk Mitigation, Monitoring,
and Management
mitigation—how can we avoid the risk?
monitoring—what factors can we track that will
enable us to determine if the risk is becoming more
or less likely?
management—what contingency plans do we have
if the risk becomes a reality?
16
Risk Due to Product Size
Attributes that affect risk:
• estimated size of the product in LOC or FP?
17
Risk Due to Business Impact
Attributes that affect risk:
• affect of this product on company revenue?
• visibility of this product by senior management?
• reasonableness of delivery deadline?
• number of customers who will use this product
• interoperability constraints
• sophistication of end users?
• amount and quality of product documentation that
must be produced and delivered to the customer?
• governmental constraints
• costs associated with late delivery?
• costs associated with a defective product?
18
Risks Due to the Customer
Questions that must be answered:
• Have you worked with the customer in the past?
• Does the customer have a solid idea of requirements?
• Has the customer agreed to spend time with you?
• Is the customer willing to participate in reviews?
• Is the customer technically sophisticated?
• Is the customer willing to let your people do their
job—that is, will the customer resist looking over your
shoulder during technically detailed work?
• Does the customer understand the software
engineering process?
19
Risks Due to Process Maturity
Questions that must be answered:
• Have you established a common process framework?
• Is it followed by project teams?
• Do you have management support for
software engineering
• Do you have a proactive approach to SQA?
• Do you conduct formal technical reviews?
• Are CASE tools used for analysis, design and
testing?
• Are the tools integrated with one another?
• Have document formats been established?
20
Technology Risks
Questions that must be answered:
• Is the technology new to your organization?
• Are new algorithms, I/O technology required?
• Is new or unproven hardware involved?
• Does the application interface with new software?
• Is a specialized user interface required?
• Is the application radically different?
• Are you using new software engineering methods?
• Are you using unconventional software development
methods, such as formal methods, AI-based approaches,
artificial neural networks?
• Are there significant performance constraints?
• Is there doubt the functionality requested is "do-able?"
21
Staff/People Risks
Questions that must be answered:
• Are the best people available?
• Does staff have the right skills?
• Are enough people available?
• Are staff committed for entire duration?
• Will some people work part time?
• Do staff have the right expectations?
• Have staff received necessary training?
• Will turnover among staff be low?
22
Recording Risk Information