Appraisal
Environment Clearance – Brief of New PARIVESH 2.0 portal
• Pro Active Responsive facilitation by Interactive and Virtuous Environmental Single window Hub
(PARIVESH) (https://parivesh.nic.in/) is single window integrated systems for Environment, Forest,
Wildlife and CRZ Clearances. MoEF&CC has recently upgraded the portal to PARIVESH 2.0 with
better data and user interface, online proposal tracking, know your clearances (KYC), etc.
Create User ID and Password of project proponent.
Fill the Common Application Form (CAF), common for all the required/applicable clearances of a
project (i.e., EC, FC, WL and CRZ). For EC the following forms are applicable.
Fill form-I part A and part B – Information for scoping and for ToR.
Fill form-I part C for EC application.
Fill form-3 for Amendment in TOR.
Fill form-4 for Amendment in EC.
Various sections and drop down menus interface to be filled as per requirements.
4
Basic EC CLEARANCE FLOW ON PARIVESH 2.0
Review EAC
Apply for Assign File Raise NO NO Approve EAC
TOR Requ Verify MoM Issue TOR
TOR No. EDS? MoM
Proposal ired? Letter
NO Publish
Apply for Reviews Raise Prepare Approve EAC Pu Draft EC Issued EC
EAC Stop
EC Form 2 EDS? Agenda MoM letter Letter
MoM
YES
Approval
Submits Draft MoM VVerify MoM Process
EDS
Project Proponent SO , MoEFCC DD , MoEFCC MS EAC, MoEFCC Chairman EAC Competent Authority
Forest Clearance process as per PARIVESH 2.0
Forest Documentation for filling proposal on PARIESH 2.0
Forest Documentation is largely dependent on following activities
• Project KML file and filling up of Common Application form (CAF)
• Identification of forest area and type (Reserve, protected, revenue forest, etc.)
• DGPS Survey of the Forest Land and verification by DFO, revenue dept.
• Preparation of KML & Shape file of the Forest Land to be Diverted.
• Identification of compensatory afforestation land and preparation of Map thereof.
• CA land required is as per new Forest guidelines (Equal CA area in case of Central Govt.
projects if non forest type). CA area approval by DFO.
• Checklist of trees to be shifted. Tree identification list (Species, girth, height, etc.)
• Cost Benefit Analysis in case area involved is >20Ha.
• Various undertakings. (Muck disposal, minimum forest uses, NPV payment, etc.)
Procedure of CRZ Clearance
1. Application to be submitted to the concerned State or the Union territory
Coastal Zone Management Authority with the following documents:
i. Project summary details as per Annexure-V to this notification.
ii. Rapid EIA Report including marine and terrestrial component, as applicable, except for
building construction projects or housing schemes
iii. Comprehensive EIA with cumulative studies for projects, if located in low and medium
eroding stretches, as per the CZMP to this notification.
iv. Risk Assessment Report and Disaster Management Plan
v. CRZ map in 1:4000 scale, drawn up by any of the agencies identified by the Ministry of
Environment, Forest and Climate Change vide its Office Order number J-17011/8/92-
IAIII, dated the 14th March, 2014 using the demarcation of the HTL or LTL, as carried
out by NCSCM.
vi. Project layout superimposed on the CRZ map duly indicating the project boundaries
and the CRZ category of the project location
vii. “Consent to establish” or NOC from the concerned SPCB or UT Pollution Control
Committee for the projects involving treated discharge of industrial effluents and
sewage
Procedure of CRZ Clearance
Examination of 3G Award
Determination of by RO and release of fund.
Compensation by CALA and Full powers to RO for
Publication of 3G Award approval/release of
compensation
DPR consultant
Update the URP submits the URP to
Authority
DPR Consultant
DPR Consultant follows reviews the cost based
up with Department on various guidelines
URP- Utility Relocation Plan, GPR- Ground Penetration Radar survey