0% found this document useful (0 votes)
18 views

Preconstruction Activities

Uploaded by

aseem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

Preconstruction Activities

Uploaded by

aseem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 26

Preconstruction activities, Statutory

Clearances, Land Acquisition and


Utility shifting.
PRE-
CONSTRUCTION
ACTIVITES

ALIGNMENT SATUTORY UTILITY OTHER


LAND ACQUISITION
FINALISATION CLEARANCES CLEARANCES

Study 3 options Environment Notification for Overground/


Appointment of underground Airport authority
CALA - 3a utilities
Ground Surveys Electrical – LT,
–Environment, Forest
Details of Land HT, GRID, Defence
Geological, Transformers
intended for
Hydrological, Railways
Wild life/ESZ Acquisition 3A
Traffic Irrigation –
Notification
Canals, Wells,
tubewells, Dams TTZ
Socio-economic, CRZ
Notification by
CALA with Oil and gas Aravalli belt
Details of land to pipelines
DPR preparation be Acquired – 3D
Water lines - Archeological
3G and PHED
compensation Biosphere
award reserves
Telecommunicati
on – Lines,
Possesion of land optical fibre, etc. State community
and Mutation reserves
Process of Environment Clearance

Screening (not applicable for Submission of Final Report to


Highway Projects) MoEF&CC / SEIAA

CAF, Form 1, PFR and proposed ToR Appraisal by EAC / SEAC

Scoping & ToR Approval by EAC / Issuance of Environment


SEAC Clearance by MoEF&CC / SEIAA

Draft EIA report including ToR Screening


compliance to SPCB / UTPCC
based on 3 months Baseline Scoping
Monitoring
Draft EIA
Public Hearing as per Process
specified in EIA Notification Public Consultation

Appraisal
Environment Clearance – Brief of New PARIVESH 2.0 portal
• Pro Active Responsive facilitation by Interactive and Virtuous Environmental Single window Hub
(PARIVESH) (https://parivesh.nic.in/) is single window integrated systems for Environment, Forest,
Wildlife and CRZ Clearances. MoEF&CC has recently upgraded the portal to PARIVESH 2.0 with
better data and user interface, online proposal tracking, know your clearances (KYC), etc.
 Create User ID and Password of project proponent.
 Fill the Common Application Form (CAF), common for all the required/applicable clearances of a
project (i.e., EC, FC, WL and CRZ). For EC the following forms are applicable.
 Fill form-I part A and part B – Information for scoping and for ToR.
 Fill form-I part C for EC application.
 Fill form-3 for Amendment in TOR.
 Fill form-4 for Amendment in EC.
 Various sections and drop down menus interface to be filled as per requirements.
4
Basic EC CLEARANCE FLOW ON PARIVESH 2.0

Prepare Publish EAC Draft ToR Approval


Submits Draft MoM
Agenda MoM letter Process
Start EDS
YES
YES

Review EAC
Apply for Assign File Raise NO NO Approve EAC
TOR Requ Verify MoM Issue TOR
TOR No. EDS? MoM
Proposal ired? Letter

No, Std. ToR

Sends Report to Submit EIA PP gets Draft EIA EM P


Public Hearing
MoEFCC Copy to EMP to Report prepared by
based on EIA EMP
Project Proponent SPCB consultant

NO Publish
Apply for Reviews Raise Prepare Approve EAC Pu Draft EC Issued EC
EAC Stop
EC Form 2 EDS? Agenda MoM letter Letter
MoM

YES
Approval
Submits Draft MoM VVerify MoM Process
EDS

Project Proponent SO , MoEFCC DD , MoEFCC MS EAC, MoEFCC Chairman EAC Competent Authority
Forest Clearance process as per PARIVESH 2.0
Forest Documentation for filling proposal on PARIESH 2.0
Forest Documentation is largely dependent on following activities
• Project KML file and filling up of Common Application form (CAF)
• Identification of forest area and type (Reserve, protected, revenue forest, etc.)
• DGPS Survey of the Forest Land and verification by DFO, revenue dept.
• Preparation of KML & Shape file of the Forest Land to be Diverted.
• Identification of compensatory afforestation land and preparation of Map thereof.
• CA land required is as per new Forest guidelines (Equal CA area in case of Central Govt.
projects if non forest type). CA area approval by DFO.
• Checklist of trees to be shifted. Tree identification list (Species, girth, height, etc.)
• Cost Benefit Analysis in case area involved is >20Ha.
• Various undertakings. (Muck disposal, minimum forest uses, NPV payment, etc.)
Procedure of CRZ Clearance
1. Application to be submitted to the concerned State or the Union territory
Coastal Zone Management Authority with the following documents:
i. Project summary details as per Annexure-V to this notification.
ii. Rapid EIA Report including marine and terrestrial component, as applicable, except for
building construction projects or housing schemes
iii. Comprehensive EIA with cumulative studies for projects, if located in low and medium
eroding stretches, as per the CZMP to this notification.
iv. Risk Assessment Report and Disaster Management Plan
v. CRZ map in 1:4000 scale, drawn up by any of the agencies identified by the Ministry of
Environment, Forest and Climate Change vide its Office Order number J-17011/8/92-
IAIII, dated the 14th March, 2014 using the demarcation of the HTL or LTL, as carried
out by NCSCM.
vi. Project layout superimposed on the CRZ map duly indicating the project boundaries
and the CRZ category of the project location
vii. “Consent to establish” or NOC from the concerned SPCB or UT Pollution Control
Committee for the projects involving treated discharge of industrial effluents and
sewage
Procedure of CRZ Clearance

2. Concerned CZMP shall examine the documents


3. If the project require Environment Clearance, CZMP shall forward it’s recommendation
to the MoEFCC for Category “A” project and SEIAA for Category “B” projects
4. CZMP shall shall forward it’s recommendation to the MoEFCC for projects not covered
in the EIA Notification but located in CRZ-I or CRZ-IV areas
5. Projects not covered in the EIA Notification but attracting CRZ Notification and located
in CRZ-II and CRZ-III area shall be considered for clearance by the concerned CZMP
6. Construction projects attracting CRZ Notification but with built-up area less than the
threshold limit stipulated for attracting the provisions of the EIA Notification, CZMP
shall forward their recommendations to the concerned State or Union territory planning
authorities, to facilitate granting approval by such authorities.
7. The clearance accorded to the projects under this notification shall be valid for a period
of seven years, provided that the construction activities are completed and the
operations commence within seven years from the date of issue of such clearance. The
validity may be further extended for a maximum period of three years.
PARIVESH 2.0 BASIC CRZ CLEARANCE FLOW 1/3
PARIVESH 2.0 BASIC CRZ CLEARANCE FLOW 2/3
PARIVESH 2.0 BASIC CRZ CLEARANCE FLOW 3/3
WILDLIFE CLEARANCE PROCESS FLOW ON PARIVESH 2.0
The Process of LA Under NH Act, 1956
Identifying of LA Proposal for 3A Notification
Requirement by Feasibility by CALA with Details of
Study Land intended for
Notification for Acquisition
Appointment of CALA 3A Notification

Proposal for 3D Notification


Invitation of Objections by
by CALA with Details of
CALA giving 21 days time.
land to be Acquired
Disposal of Objections.
3D Notification

Examination of 3G Award
Determination of by RO and release of fund.
Compensation by CALA and Full powers to RO for
Publication of 3G Award approval/release of
compensation

Payment of Compensation Physical Possession and


to Land Owners by CALA Mutation of Land by
and 60 days Notice for NHAI after deposit of
surrender of the land compensation with CALA
Process flow for Utility shifting work
Carry out Topo survey
Start to identify over ground
utilities

Carry out GPR survey Carry out to ascertain


to identify under the utilitiReccees
ground utilities identified

DPR consultant
Update the URP submits the URP to
Authority

DPR Consultant Carries Utility department


out Joint Site Visit with prepares the Estimate
identified departments & Cost

DPR Consultant
DPR Consultant follows reviews the cost based
up with Department on various guidelines
URP- Utility Relocation Plan, GPR- Ground Penetration Radar survey