Ra 9184 Final Report
Ra 9184 Final Report
9184,
OTHERWISE KNOWN AS THE
GOVERNMENT PROCUREMENT
REFORM ACT
Group 4:
Bicomong, Lourdes Liezl M.
Carandang, Amielle R.
Cortez, Jamaica C.
Delgado, Joseph Ian C
Estorel, Maria Vernie Q.
Guevarra, Kirby Clifford C.
INVITATION TO BID
Pre-Procurement Conference
• Purpose: Determine readiness to proceed
with the bidding process
• Conducted before advertisement/posting of the Invitation to
Bid
t
Eligibility Requirements
Class “A” Documents
Mayor’s Permit
t
Eligibility Requirements
Class “A” Documents
Tax clearance per Executive Order 398, series of 2005, as
finally reviewed and approved by the BIR;
(GPPB Resolution No.21-2013)
t
Eligibility Requirements
Class “A” Documents
Net Financial Contracting Capacity; and Audited
Financial Statement
t
Eligibility Requirements
Class “B” Documents
Joint Venture Agreement or notarized statement from the partners
that they will enter into joint venture if awarded the contract.
t
Eligibility Requirements
I. THE FIRST ENVELOP (Technical Proposal)
⮚ Preliminary Conceptual Design Plans in accordance with the degree of details
specified by the procuring entity;
⮚ Design and construction methods;
⮚ List of design and construction personnel, to be assigned to the contract to be
bid, with their complete qualification and experience data; and
⮚ Value engineering analysis of design and construction method.
II. THE SECOND ENVELOP (Financial Proposal)
⮚ Lump sum bid prices, which shall include the detailed engineering cost, in the
prescribed Bid Form;
⮚ Detailed estimates including a summary sheet indicating the unit prices of
construction materials, labor rates and equipment rentals used in coming up with
the bid; and
⮚ Cash flow by the quarter and payments schedule.
BID EVALUATION
Bid Evaluation for the Procurement of Goods and Infrastructure
Projects
First-Step Procedure:
• Review of the preliminary conceptual designs and track record submitted by the
contractor
• Make an oral presentation within fifteen (15) calendar days after the deadline for
submission of technical proposals.
Second-Step Procedure:
• Only those bids that passed the above criteria shall be subjected to the second step of
evaluation.
• The BAC shall open the financial proposal of each “passed” bidder and shall evaluate it
using non-discretionary criteria - including arithmetical corrections for computational
errors - as stated in the Bidding Documents, and thus determine the correct total
calculated bid prices.
• The BAC shall automatically disqualify any total calculated bid price which exceeds the
ABC.
• The total calculated bid prices (not exceeding the ABC) shall be ranked, in ascending
order, from lowest to highest. The bid with the lowest total calculated bid price shall
be identified as the Lowest Calculated Bid (LCB).
POST-QUALIFICATION
and
AWARD OF THE CONTRACT
POST-QUALIFICATION and AWARD OF THE
CONTRACT
• The LCB shall be subject to post-qualification in accordance with Section
34, Rule X of this IRR to determine its responsiveness to the eligibility and
bid requirements.
• If after post-qualification the Lowest Calculated Bid is determined to be
post-qualified it shall be considered the Lowest Calculated and
Responsive Bid (LCRB) and the contract shall be awarded to the bidder.
• In case of post-disqualification of the LCB, the procedure under Section 34
shall also be followed.
• The Head of the Procuring Entity shall approve or disapprove the
recommendations of the BAC within a period not exceeding fifteen (15)
calendar days from the determination and declaration by the BAC of the
LCRB.
• The Head of the Procuring Entity concerned shall award the contract to
the said bidder pursuant to the provisions of Section 37, Rule XI of this
IRR.