CH 02
CH 02
2-2
Introduction
Project selection is the process of evaluating individual projects or groups
of projects and then choosing to implement some set of them so that the
objectives of the parent organization will be achieved
Rarely a project manager is involved in project selection but it is important
to the success of the PM that he/she fully understands the parent
organization’s objectives in undertaking that project.
The project manager who does not understand what a given project is
expected to contribute to the parent organization lacks the critical
information needed to manage the project in order to optimize its
contribution
2-3
Project Selection Criteria and Models
Project selection…
Evaluating
Choosing
Implementing
Project selection is usually based on models. The model allows us to strip away
almost all the reality from a problem, leaving only the relevant aspects of the
“real” situation for us to deal with. This process of carving away the unwanted
reality from the bones of a problem is called modeling the problem.
2-4
Project Selection Criteria and Models
When a firm chooses a project selection model, the following
criteria, based on Souder (1973), are the most important
Realism
Capability
Flexibility
Ease of use
Cost
Easy computerization
2-5
Types of Project Selection Models
There are two basic types of project selection models, numeric and non-numeric
Nonnumeric models, as the name implies, do not use numbers as inputs. Numeric
models do, but the measured criteria may be objective or subjective.
Before examining specific kinds of models let us consider the two critically important,
but often overlooked, facts.
• Models do not make decisions—people do. The manager, not the model, bears responsibility
for the decision. The manager may “delegate” the task of making the decision to a model, but
the responsibility cannot be abdicated.
• All models, however sophisticated, are only partial representations of the reality they are
meant to reflect. Reality is far too complex for us to capture more than a small fraction of it in
any model. Therefore, no model can yield an optimal decision except within its own, possibly
inadequate, framework.
2-6
Types of Project Selection Models
Of the two basic types of selection models (numeric and non-
numeric), non-numeric models are older and simpler and have
only a few subtypes to consider. We examine them first.
Nonnumeric Models
2-7
Types of Project Selection Models
The Operating Necessity:- If the project is required in order to keep the
system operating, the primary question becomes: Is the system worth
saving at the estimated cost of the project? If the answer is yes, the project
will be funded.
The Competitive Necessity:- A project that is required in order to
maintain the company’s position in the marketplace
Nokia CEO Stephen Elop ended his speech saying, “we didn't do
anything wrong, but somehow, we lost.”
Product Line Extension:- In this case, a project to develop and distribute
new products would be judged on the degree to which it fits the firm’s
existing product line, fills a gap, strengthens a weak link, or extends the
line in a new, desirable direction.
2-8
Types of Project Selection Models
Comparative Benefit:- For this situation, assume that an organization
has many projects to consider, perhaps several dozen. Senior
management would like to select a subset of the projects that would most
benefit the firm, but the projects do not seem to be easily comparable.
Projects are prioritized through scores and ranks and the most suitable
group of projects is selected.
Sustainability:- More and more organizations are building sustainability
into the set of criteria that must be met for proposed projects to be
selected for funding. Sustainability focuses on long-run profitability
rather than a short-run payoff.
Customers don’t want to buy products from child or “slave” labor.
2-9
Types of Project Selection Models
Numeric Models: Profit/Profitability
A large majority of all firms using project evaluation and selection models use
profitability as the sole measure of acceptability. We will consider these models first,
and then discuss more comprehensive models.
Payback Period:- The payback period for a project is the initial fixed investment in
the project divided by the estimated annual net cash inflows from the project. The
ratio of these quantities is the number of years required for the project to repay its
initial fixed investment. For example, assume a project costs $100,000 to
implement and has annual net cash inflows of $25,000. Then
Payback period= $100,000/$25,000 =4 years
This method assumes that the cash inflows will persist at least long enough to pay
back the investment, and it ignores any cash inflows beyond the payback period.
The faster the investment is recovered, the less the project risk
2-10
Types of Project Selection Models
2-11
Types of Project Selection Models
2-12
Types of Project Selection Models
Numeric Models: Profit/Profitability (cont..)
Internal Rate of Return:- If we have a set of expected cash
inflows and cash outflows, the internal rate of return is the
discount rate that equates to the present values of the two sets
of flows. The value of the internal rate of return (k) is found
by trial and error.
2-13
Types of Project Selection Models
Numeric Models: Profit/Profitability (cont..)
Profitability Index:- Also known as the benefit–cost ratio, the
profitability index is the net present value of all future
expected cash flows divided by the initial cash investment.
(Some firms do not discount the cash flows in making this
calculation.) If this ratio is greater than 1.0, the project may be
accepted.
Other profitability Models:- There are a great many variations of
the models just described
2-14
Example
Example (Continue)
Types of Project Selection Models
Numeric Models: Scoring
In an attempt to overcome some of the
disadvantages of profitability models,
particularly their focus on a single decision
criterion, a number of evaluation/selection
models that use multiple criteria to evaluate a
project have been developed.
Unweighted 0–1 Factor Model:- A set of
relevant factors is selected by management and
then usually listed in a preprinted form. One or
more raters score the project on each factor,
depending on whether or not it qualifies for an
individual criterion.
Figure 2-2 shows an example of the rating sheet
for an unweighted, 0–1 factor model. 2-17
Types of Project Selection Models
Numeric Models: Scoring
Unweighted 0–1 Factor Model (Cont…):-
The columns of Figure 2-2 are summed and
those projects with a sufficient number of
qualifying factors may be selected
The main advantage of such a model is that it
uses several criteria in the decision process.
The major disadvantages are that it assumes
all criteria are of equal importance and it
allows for no gradation of the degree to
which a specific project meets the various
criteria.
2-18
Types of Project Selection Models
Numeric Models: Scoring
Unweighted Factor Scoring Model:- the disadvantages of the previous
method are handled by this one.
The x marks in Figure 2-2. would be replaced by numbers. Often a five-
point scale is used, where 5 is very good, 4 is good, 3 is fair, 2 is poor, and
1 is very poor. Any other scale is also applicable
The second column of Figure 2-2 would not be needed. The column of
scores is summed, and those projects with a total score exceeding some
critical value are selected.
However, the criticism that the criteria are all assumed to be of equal
importance still holds.
2-19
Types of Project Selection Models
Numeric Models: Scoring The quality of the final product is:-
Unweighted Factor Scoring Model:-
Consider the following two simple Score Performance Level
examples. Using the criterion “ estimated 5 Significantly and visibly improved
annual profits in dollars,” we might 4 Significantly improved, but not visible to
construct the following scale: the buyer
Score Performance Level
3 Not significantly changed
5 Above $1,100,000
2 Significantly lowered, but not visible to the
4 $750,001 to $1,100,000 buyer
3 $500,001 to $750,000 1 Significantly and visibly lowered
2 $200,000 to $500,000
1 Less than $200,000
This scale is an example of a scoring
model
For the criterion “ no decrease in quality of
the final product” can be scaled on a 5-point
scale as follows 2-20
Types of Project Selection Models
2-21
Types of Project Selection Models
2-22
Types of Project Selection Models
2-23
Types of Project Selection Models
Problem 6. Solution
In this example, Project C has the
highest score, so the decision-maker
would regard it as the best option.
Note:- it is not necessary for the weights
to sum to 100. It is only necessary that
the model use the same scoring
categories to evaluate each option.
2-24
Types of Project Selection Models
2-26
THE PROJECT PORTFOLIO PROCESS (PPP)
Organizations typically maintain a portfolio of projects, and trying to keep a
proper balance among this portfolio is the real task of upper management.
With limited resources, management must choose between long-term and
short-term projects, safe and risky projects manufacturing and marketing
projects, and so on.
To help choose between the myriad of project proposals, in competition
with ongoing projects as well as each other, management needs some
measures to evaluate each of the projects, and those measures are
commonly related to the organization’s mission, goals, and strategy.
2-27
THE PROJECT PORTFOLIO PROCESS (PPP)
Symptoms of a Misaligned Portfolio (Deloitte Consulting)
Many more projects than management expected
Inconsistent determination of benefits, including double counting
Projects that don’t contribute to the strategy
Competing projects; no cross-comparison of projects
Costs exceed benefits
No risk analysis of projects
Lack of tracking against the plan, at least quarterly
No identified “client” for many projects
2-28
THE PROJECT PORTFOLIO PROCESS (PPP)
Project Portfolio Process Steps
1. Establish a project council
2-30
THE PROJECT PORTFOLIO PROCESS (PPP)
Step 2: Identify Project Categories and Criteria Figure 2-3:- Aggregate Project Plan
Wheelwright et al. (1992) have developed a matrix called (Wheelwright et al. (1992)
the aggregate project plan illustrating these changes, as
shown in Figure 2-3. Based on the extent of product
change and process change, they identified four separate
categories of projects:
Derivate projects:- These are projects with
objectives or deliverables that are only
incrementally different in both product and process
from existing offerings. They are often meant to
replace current offerings or add an extension to
current offerings
Platform projects:- The planned outputs of these
projects represent major departures from existing
offerings in terms of either the product/service itself
or the process used to make and deliver it, or both
THE PROJECT PORTFOLIO PROCESS (PPP)
Step 2: Identify Project Categories and Figure 2-3:- Aggregate Project Plan
Criteria (Wheelwright et al. (1992)
Breakthrough projects:-Breakthrough
projects typically involve a newer
technology than platform projects.
Examples here include the use of fiber-
optic cables for data transmission, cash-
balance pension plans, and hybrid
gasoline-electric automobiles.
R&D projects:- These projects are “blue-sky,”
visionary endeavors oriented toward using
newly developed technologies, or existing
technologies in a new manner
THE PROJECT PORTFOLIO PROCESS (PPP)
Step 2: Identify Project Categories and Figure 2-3:- Aggregate Project Plan
Criteria (Wheelwright et al. (1992)
Step 2: Identify Project Categories and Criteria Figure 2-3:- Aggregate Project Plan
(Wheelwright et al. (1992)
Next, the council should develop separate criteria and
cost ranges for each category that determine those
projects that will support the organizational strategy
and goals. Example criteria might include, but are not
limited to,:-
alignment with the organization’s goals/strategy
2-37
THE PROJECT PORTFOLIO PROCESS (PPP)
2-38
THE PROJECT PORTFOLIO PROCESS (PPP)
If the project has slipped in its desirability since the last evaluation
2-39
THE PROJECT PORTFOLIO PROCESS (PPP)
2-42
THE PROJECT PORTFOLIO PROCESS (PPP)
Step 8: Implement the Process
The first task in this final step is to make the results of the PPP widely
known, including the documented reasons for project cancellations,
deferrals, and non-selection as was mentioned earlier.
Top management must now make their commitment to this project
portfolio process totally clear by supporting the process and the results
Senior management must fully fund the selected projects.
2-43
Techniques/Softwares
Delphi method
Analytical Hierachy Process (AHP)
Softwares
Expert Choice
Super Decisions
2-44