CH 07
CH 07
6-1
Outline
• Introduction
• How to estimate project budgets
• Traditional Category Budgeting Versus
Program/Activity Budgeting
• Improving the process of cost estimating
• Other related concepts
6-2
Budgeting (Slide 1 of 2)
7-3
Budgeting (Slide 2 of 2)
A budget implies many things
Constraints: Thus, it implies that managers will not get everything they
want or need
Support:-The budget for an activity implies management support for that
activity
The higher the budget, the higher the importance of the activity, and
thus the higher the managerial support
The budget is also a monitoring & control mechanism
7-8
Estimating Project Budgets
Advantages:-
management has more control over
budgets.
Disadvantages
May lead to under-resourced or over-
resourced some of the WBS
units/activities
Lower management perceives a
strong bias towards under-estimating
by senior managers
7-9
Estimating Project Budgets
Bottom-up budgeting:-
In this method, elemental tasks, schedules, and
individual budgets are constructed, again following
the WBS.
The people doing the work are consulted regarding
times and budgets for the tasks to ensure the best
level of accuracy.
Initially, estimates are made in terms of resources,
such as labor hours and materials. These are later
converted to the dollar equivalents.
The PM adds the indirect costs as general and
administrative (G&A). And possibly a project
reserve for contingencies, and then a profit figure to
arrive at the final project budget.
Estimating Project Budgets
Advantages:-
Greater buy-in by low-level managers
Should be more accurate than top-down
budgeting
Disadvantages:-
7-13
Estimating Project Budgets
An Iterative Budgeting Process–Negotiation-in-Action
Advantages
Allows a free flow of ideas up and down the system at all levels
Disadvantages
Time-consuming process, not efficient, especially if there are multiple projects running
simultaneously
7-14
Cost Category Budgeting VS. Project/Activity Budgeting
The traditional organizational budget is Table 7-1 Typical Monthly Category Budget for a Real Estate
Project (page 1 of 6)
category oriented often following the
traditional accounting system.
Individual expenses are classified and
assigned to basic budget lines such as
phones, materials, utilities, direct labor,
and so on.
Table 7-1 shows one page of a typical,
category-oriented monthly budget report
for a real estate project
7-15
Traditional Category Budgeting Versus Program/Activity
Budgeting
Under traditional budgeting methods, the budget Table 7-2 Project Budget by Task and Month
for a project could be split up among many
different organizational units, which diffused
control so widely that it was frequently
nonexistent. It was often almost impossible to
determine the actual size of major expenditure
activities in a project’s budget.
In light of this problem, ways were sought to
alter the budgeting process so that budgets could
be associated directly with the projects that used
them. This need gave rise to project budgeting.
Table 7-2 shows a project-oriented budget
divided by task/activity and expected time of
expenditure
7-16
Improving the process of cost estimating
Turning now to the problem of estimating Figure 7-3 Form for gathering data on project resource
direct costs, project managers often find it needs.
helpful to collect direct cost estimates on a
form that not only lists the estimated level
of resource needs, but also indicates when
each resource will be needed, and notes if it
is available (or will be available at the
appropriate time).
Figure 7-3 shows such a form. It also has a
column for identifying the person to contact
in order to get specific resources
Note that Figure 7-3 contains no
information on overhead costs
Learning Curves
7-19
Learning Curves
7-20
Learning Curves
7-21
Learning Curve Tables
Learning Curves
7-23
Learning Curves
How to estimate project budgets
Uncertainty
The accuracy of single-point cost estimates
may be improved by considering estimation
uncertainty and risk and using three estimates
to define an approximate range for an
activity’s cost:
Most likely: The cost of the activity, based on
realistic effort assessment for the required
work and any predicted expenses.
Optimistic: The cost is based on an analysis of
the best-case scenario for the activity.
Pessimistic: The cost based on analysis of the
worst-case scenario for the activity. 7-25
Improving the process of cost estimating
The matter of what overhead costs are to be added and in what amounts is unique to the
firm, beyond the PM’s control, and generally a source of annoyance and frustration to one
and all. The allocation of overhead is arbitrary by its nature and it could lead a
presumably winning (profitable) project to fail.
Nevertheless, sometimes firms support projects that are not profitable for different reasons:-
To develop knowledge of a technology
All these reasons are adequate
To get the organization’s “foot in the door” to fund projects that, in the
To obtain the parts or service portion of the work short term, may lose money
but provide the organization
To be in a good position for a follow-on contract
with real options for future
To improve a competitive position growth and profitability
To broaden a product line or a line of business
Other Factors
Cost changes in resource prices over time: a solution to this is to increase the potential cost
estimates of the resources that are suspected to increase, or have a high impact on project
success.
Prices of various inputs change at different rates and in different directions:- according to the
Bureau of labor statistics (LBS) states that even in a period of stable prices, the prices of some
items rise, while others fall, and still others do not change. This the PM might use a possible set
of deflators/inflators for each of the different classes of labor types of commodities in for
maintaining their bids competitive.
Waste and Spoilage:- an allowable waste percentage has to be included in the cost-estimating
process. Keep in mind that no single builder will order just enough lumber to build a house.
Ethical problems: Sometimes bidders submit an underestimated cost for the purpose of winning
the contract, counting on the opportunity to plead for higher costs later on due to project
circumstances once the project is underway.
Bad Luck:- delays occur for reasons that cannot be predicted. Some machinery that has an
outstanding reliability rate fails. To buffer against such issues, each project should have an
allowance for contingencies.
7-27
On making Better Estimates
Project estimates are always subject to
error. Figure 7-5:- Estimation template using ratios
There are two types of errors
Random error:- over which overestimates
and underestimates are equally likely. Thus,
these errors tend to cancel each other.
Bias/systematic error:-for these errors, the
chances of overestimates and underestimates
are not equally likely, and their sum, either
positive or negative, will increase as the
number of estimates increases.
A measure of bias, the tracking signal
(TS), is shown in raw 4 of Figure 7-5
We can use an Excel spreadsheet to
analyze the estimator performance.
7-28
On making Better Estimates
7-29
On making Better Estimates
If the sum of the ratios is positive/negative then the
forecaster is either overestimating or
underestimating. Figure 7-5:- Estimation template using ratios
Column E shows the absolute value of Column D.
Whereas column F is the mean absolute ratio
(MAR) which is the running average of the values
of column E up to that period.
The tracking signal listed in column G is the ratio
of the running sum of the values in column D
divided by the MAR for that period.
If the estimates are unbiased, the running sum in
column D will be close to zero, and diving this over
the MAR will give a very small tracking signal
(close to zero).
If there is considerable bias, the tracking signal will
be either <1, or >1.
If the bias is large, the tracking signal will be
correspondingly large positive or negative
7-30
Risk Estimation
The duration of project activities, the amounts of various resources that will be required
to complete a project, the estimates made of the value of accomplishing a project, all these
and many other aspects of a project are uncertain.
While a project manager may be able to reduce uncertainty, it cannot be eliminated.
Risk estimation and analysis does not remove the ambiguity; it simply describes the
uncertainties in a way that provides the decision maker with a useful insight into their
nature.
To apply risk analysis, one must make assumptions about the probability distributions
that characterize key parameters and variables associated with a decision and then use
these to estimate the risk profiles or probability distributions of the outcomes of the
decision.
This can be done analytically or by Monte Carlo simulation
7-31
Converting Estimates into Project Budgets
7-33
Cost Baseline
Management reserve is a
portion of the project budget
that’s used as a reserve for
management control and
unexpected costs
7-34
Cost Baseline
Development of S-curve: example
7-35
Cost Baseline
Development of S-curve: example
7-36
Cost Baseline
Development of S-curve: example
7-37