Risk Management (1) 054114
Risk Management (1) 054114
The above points of cost, time and quality represent the key issues
in project management
Risks can also be transferred to another party for example from client
to contractor or contractor to subcontractor.
A contingency sum will most likely be set to deal with the residual
risks. These are defined as those risks that cannot be eliminated or
transferred to another party or are best retained by the organization.
o External where the risk come from outside of the project participants. This
might include such issues and adverse weather conditions or governmental
action or terrorism. These will often relate to economic or political factors
or climatic issues.
30/09/2024 Risk Management 11
Problem Analysis
Here risks are related to threats to the project achieving its objectives that have been
identified. This could include the threat of cost over-run on the project, the threat of
accidents, the threat of failing to meet revenue targets, etc.
This is looking at this from the viewpoint of the implications of the failure to meet the
objectives of the project.
Risk Charting
This seeks to combine some of the above approaches by listing the resources at risk.
An approach is to focus on the resources at risk This can start with the threats and
see which resources are affected. Alternatively it can start with the resources and see
what threats effect them.
30/09/2024 Risk Management 14
Techniques for Risk Identification
Brainstorming
Brainstorming is one technique often employed where ideas are
chewed over and refined in a semi-structured group discussion.
This should involve staff from a variety of levels along with
subject experts but should be led by someone with a good
knowledge of the technique. Problems should be dealt with in
turn and restate in as many different ways as the group members
can think. One of the restatements should be selected and
brainstormed upon.
Interviewing Techniques
This technique suggests that structured review meetings with key staff and risk audit interviews with key staff
could also be used. Face-to-face meetings can be held with project participants and stakeholders plus also
subject experts and those with experience of similar projects in the past.
SWOT Analysis
The approach involves examining the Strengths, Weaknesses, Opportunities, and Threats for the project or
organization. Obviously the weaknesses and opportunities will be the relevant items in the context of risk
management. It may be used to increase the breadth of the risk analysis.
2. To analyse risks which by their nature are never likely to produce the data for
a Quantitative Risk Analysis.
The most important risk will be Grade 1 that is high probability and high impact. The least important will be
Grade 4 risks that are low probability and low impact. Grade 3 risks are low probability high impact while a
Grade 3 risk is high probability low impact. The matrix below illustrates classification.
The qualitative risk classification approach allows the most important risks to be identified without enough
information to undertake a qualitative analysis. It should focus on the causes and effects of potential risks
especially in the early project stages.
This will end with the summarizing the material on a single sheet of paper as below:
a) Using a risk proforma sheet, identify 2 major risks associated with the
project
30/09/2024 Risk Management 24
Risk Response
Having computed the impact of the various types of risk affecting a
project, the following responses are possible:
1. Attempt to reduce or eliminate the risk.
2. Insure against the risk.
3. Transfer all or part of the risk to another party.
4. Retain all or part of the risk.
Ultimately, the project must be able to sustain all costs associated with
risk no matter whether the risk is reduced, retained, or transferred to
other parties. Effective risk management during the design and
construction stages aimed at keeping the project within budget may
involve setting a higher contingency and increasing the budget costs.
This may increase the risk of financial failure for the project by increasing
capital costs and hence debts. The general rule remains that risks are best
left with the party best able to control them.
30/09/2024 Risk Management 25
Risk Reduction
Reduction (or avoidance) of the risk may be accomplished by re-
design, changing the materials used to avoid untried technology,
or to change the project plan. This will generally be worthwhile
unless it results in an unacceptable increase in the base estimate.
The likely increase in the base estimate can be partially offset by a
reduction in the contingency.
1. Avoid innovative technology. Being at the cutting edge of
technology can carry a price tag.
2. Reduce reliance on imported components. Changes in currency
exchange rate can have a major impact.
3. Alternatively use some sort of currency hedge to reduce exposure
of the project to changing exchange rates.
4. Use Value Management techniques.
The contingency is the sum built into the budget price or tender sum to cover the
impact of risk variables. A contingency cannot be expected to cover all possible risk
factors. It is generally restricted to bridging the gap between the situation where no
risk variables impinge on the cost and the best estimate for the outcome. The
contingency should therefore be adequate 50% of the time.
The allowance for contingency may arise from confidence interval identified by the
quantitative risk analysis.
FOR
YOUR ATTENTION
30 September 2024 31