Project Analysis - Construction Claim Management
Project Analysis - Construction Claim Management
Mr
Project Analysis
PROJEC
IMPLEMENT DESIGN
T
TESTING DEVELOP
CONSTRUCTION CLAIMS MANAGEMENT PLANNING
EOT DELAYS ANALYSIS • ENGINEER
CONTRACT MODULE
CONTRACT IS ONE OF THE MOST IMPORTANT REFERENCES
AND DOCUMENTS FOR ANY CLAIM , YOU HAVE TO REFER
PART 1
INTRODUCTION ABOUT CONTACTS &
CONTRACTS TYPES
Construction Claims Management ( Contract Module – Part 1 )
Agend
a
• Introduction
• Construction Industry Parties
• What is Contract ?
• Contract Strategy
• Contract Need Documents
• Contract Documents Priorities
• Contract
• Construction Contract Forms
• Contracting Process
• Types of Contract
• Conditions of Contract
• Legal Laws
Construction Claims Management ( Contract Module – Part 1 )
Employer
Engineer
Contractor
Construction Claims Management ( Contract Module – Part 1 )
What is a Contract
A contract is defined as: “An agreement made
between two or more parties which is enforceable by
law to provide something in return for something
else from a second party".
Contract Strategy
Contract strategy means selecting organizational
and contractual policies required for the execution
of a specific project.
Contract Strategy
A proper contract strategy for a project involves Four
key decisions:
Do you think …
Consideration
There must be
a lawful and
valuable
consideration
Agreement
given to contract,
For valid both there must be a mutual agreement.
parties. A is considered to have been reached
An agreement
consideration
when an offer made by one party is accepted by the
often calledBoth parties must
second party. and intend their
wish
"Something for
Construction Claims Management ( Contract Module – Part 1 )
Proper Form
The terms of a contract must be written so that both
parties are very sure of what their rights and
responsibilities are.
Contract Need
Contracts provide a description of responsibilities and
liabilities.
Contract Documents??
Construction Claims Management ( Contract Module – Part 1 )
Contract Documents
The contract is defined by the contract documents,
which are developed from the tender documents.
Contract
Document
s
Contract Documents
1- Contract Agreement.
Which represent the final agreement document that is signed by both
parties and contains the full detailed information about them.
2- Letter of Tender.
Letter of Tender is the letter which is completed by the contractor and
contains the signed offer to the Employer.
3- Letter of Acceptance.
Letter of Acceptance” is the letter sent from the Employer to the
contractor including any annexed attached agreed between both parties.
If the Letter of Acceptance is not available it will be referred to
the
Contract Agreement and related dates.
Construction Claims Management ( Contract Module – Part 1 )
Contract Documents
4- Conditions of Contract.
1. Special Conditions.
2. General Conditions
Which represents the rights and obligations for both parties
5- Specifications.
Which should contain a detailed description on design and material used
in execution.
6- Drawings.
Which Indicates to the drawings specified in the Specification
Document and any drawing modifications written by the Consultant.
Construction Claims Management ( Contract Module – Part 1 )
Contract Documents
7- Programme
Means the document(s) entitled schedules, completed by the
Contractor and submitted with the Letter of Tender, as included in
the Contract. Such document may include the Bill of Quantities,
data, lists, and schedules of rates and/or prices.
Construction Claims Management ( Contract Module – Part 1 )
For Example :
Contracting Process
Identify Project
Prepare Scope
Select Contract
Prepare Tender Documents
Invite Tenders
Tender Meetings
Tender Evaluation
Place Contract
Construction Claims Management ( Contract Module – Part 1 )
Types of Contracts
Cost Plus
Cost based
Target Cost
Contract
Unit Price
Price based
Lump Sum
Construction Claims Management & EOT Delay Analysis – Part 1
Lump-sum contract
Contract Value: Single tendered price is given for the
completion of specified work by a certain date.
Lump-sum contract
Using : This contract may be used for a turn key
construction
Construction Claims
• A construction claim is a request for payment or
time extension to which the contractor considers
him/herself entitled under the contract conditions
and terms . There are three types under which
claims are required:
Additional cost.
Legal systems
Legal Systems
Arbitration Law
Law 89 and its Law 119 year 2008 (Law 27 year 1997)
Amendments () دحومال ءانبال ( نوناق
نوناق )
ميكحتال
Construction Claims Management & EOT Delay Analysis – Part 1
Thank You