Introduction To Estimation
Introduction To Estimation
PREPARED BY,
MD TAYAB ALI
Sr Grade Lecturer
Department OF Mechanical Engineering
H.R.H. The Prince of Wales Institute of Engineering &
Technology, Jorhat-785001
Assam
Slide 1
THEORY SESSIONAL
Slide 2
Course Outcome
After learning this subject, the students should be able to:
1. Draw Jigs and Fixtures.
2. Know the fundamentals of estimating and costing.
3. Estimate the cost of production of machine or engine components.
4. Calculate the depreciation cost of a machine.
5. Estimate the machining, sheet metal ,Fabricating and welding time of a
final/simple product.
6. Draw the assembly drawing using part drawings so that students will be
able to produce the final product by procuring the units from various
sources/suppliers .
Slide 3
A
Presentation On
Introduction to Estimation
Presented by
Md Tayab Ali
Sr Grade Lecturer
Dept. of Mechanical Engineering
H.R.H. The POWIET, Jorhat
Slide 5
Estimation
Slide 7
Importance of estimation
Slide 8
Aims of estimation
Slide 9
Constituents of Estimation
Slide 11
2.Drafting cost
Slide 12
3.Planning and production cost.
Slide 13
4. Cost of experimental work.
Slide 14
5.Labour cost
Following steps involved
To estimate the labour cost, the estimator should have
the knowledge of various operations, machines,
sequence, tools & labour to be used.
Different allowances like personal, fatigue, tool
changing and grinding and checking measurement
allowances should also be taken into consideration.
Labour cost = Estimated labour time needed to the
product x Cost of the labour per hour
Slide 15
6.Material cost
Following steps involved
Prepare the list of all materials required to
manufacture the product
Estimate the weight of all the materials expected (the
allowance for the material wastage, spoilage and scrap
are also added)
Estimated materials cost = Estimated weight of each
part x Estimated future price
Finally, the estimated cost of all the parts is added to
get the total estimated material cost of the product.
Slide 16
7. Inspection cost
Slide 17
8.Procurement of special tools and equipment
Slide 18
9.Time allowances
Slide 19
9.Time allowances
Slide 22
9.Time allowances
Other allowances:
Allowances in time should be provided for the following
activities also:
Periodic cleaning and oiling of machines
Getting stocks
Delivering jobs
Disposing of scraps and surplus stock etc.
Slide 23
10.Overhead cost
Slide 24
11.Profit
Slide 25
Thank You
Slide 26