FINALdt28-04-2015 Design of Canals-Examples & Exercises - 1
FINALdt28-04-2015 Design of Canals-Examples & Exercises - 1
Presented
by
Er. Baba Sharfuddin
Faculty member
WALAMTARI
Joined in Walamtari as Worked as DEE in Designs Circle,
Faculty Member in cadre Pranahita-Chevella Project, dealing
of DEE with Alignment, HPs & CM & CD
Structures of Gravity Canals of Lift
Worked in CE/CDO, as AEE & DEE, Irrigation Schemes(Ongoing)
dealing with Designs & Drawings
of Spillway DAM, Earth Dam, Weir,
Worked in Spl. Designs Circle, dealing
CM & CD Structures of Major &
with Designs & Drawings of
Medium Projects
Jalasoudha Building
Note:
Flatter slopes have to be adopted if the velocity
generated is higher than permissible one due
to adoption of average slope of the ground
• Critical Velocity(Vo): in metre per second
this velocity is the velocity(upper limit)
corresponding to depth of water/flow in the
canal
Adopting Kannedy’s expression, Vo is given by
Vo = C d 0.55 ( for clear water)
Where C = 0.47 for B.C, silty and softer soil
= 0.60 for murram, gravelly and hard
soils
d = depth of flow in the canal in metres
• Minimum Permissible Velocities: (V)
Type of Soil value of ‘v’(m/sec)
(1)Silts - - - - - - - - - - - - - - - - - - 0.5 - 0.6
(2)Fine sand - - - - - - - - - - - - - - 0.7 - 0.8
(3)Clayey Sand - - - - - - - - - - - - - 1.0
(4) Hard Sandy clay - - - - - - - - - - 1.0 - 1.2
(5)Ordinary Clay - - - - - - - - - - - - 1.2 - 1.4
NOTE:
All soils - - - - - - -0.60 to 1.10 m/s
SDR - - - - - - - - - -1.40 m/s
HDR - - - - - - - - - -2.4 m/s
HR - - - - - - - - -- - 4.5 m/s
• Bank top Width:
for canals carrying less than 1.5 cumecs it is
generally not economical to construct a
service road on top of bank as this requires
more materials than the excavation provides.
In such cases service road may be provided on
natural ground surface adjacent to the bank.
• Berms:
Berms along earthen channels are provided to
reduce the bank loads which may cause
sloughing off earth in to the canal section.
Note:
(1) Silting problem arise in channels taking off from
diversion works. These Channels are to be
designed on the principles of minimum
permissible velocity
Design of Canals
(2) Channels taking off from storage works usually
carry silt free water. These channels are to be
designed on the principles of maximum
permissible velocity.
(3) Lined Canals are designed for a maximum
velocity of about 2.70 metres per second
Design of Canals
• Calculation of Discharge based on CA, using Dicken’s
formula
Q=C M3/4,
Where ‘M’= Catchment Area
‘C’ = a co-efficient depending on CA
CA ‘C’ Value
0 – 2.5 km2 19.50
2.5 – 7.5 16.70
7.5 – 12.5 14.60
Contd….
23
Design of Canals
• Bed Fall is to be maintained
• Value of ‘n’
for lined canal, n = 0.018
for unlined canal, n = 0.0225 to 0.035
• side slopes
for canal in embankment, SS = 2:1
for canal in partial cutting & banking, SS =1.5:1
for canal in deep cut portion, SS = 1:1
contd…
Design of Canals
• Calculate Depth of water in canal(d)
(Hint:d(in m) = C Q1/3 )
Note:-
The width at FSL should be more than the calculated
Lacey’s waterway bed width
Contd…
Design of Canals
• Manning’s formula(being adopted in design of open
channel)
V = 1/n R2/3 S1/2
Where
V = mean velocity of flow in m/sec
‘n’ = roughness coefficient, called as ‘coefficient
of rugosity
R = Hydraulic mean depth
( area over perimeter i.e A/P)
S = Slope of channel or Bed Fall, 1 in S
Contd….
Design of Canals
• Discharge(Q)
• Q = V A in Cumecs
Note:
Designed discharge should be more than the
required discharge
If above factors are taken care of, the canal
section is considered as safe
Co-Efficient of rugosity’n’
For value of ‘n’
Lined canal 0.018
Normal alluvial soils 0.0225
Murum 0.025
Rocky strata 0.03 to 0.035
Design of Canal Section
STEPS:
1. Calculation of Discharge(Q) when CA is given
2. Calculation of Bed width, using Lacey’s water –
way equation
3. Calculation of depth of flow(d)
4. Check Width at F.S.L(more than Bw)
5. Adopt suitable side slope depending on whether
canal in embankment, partial cutting/banking or
deep cut portion
6. Calculation of Area and perimeter
contd…
Design of Canal Section-Contd
(7)Calculate Hydraulic mean depth (R)i.e A/P
(8)Calculate Bed Fall or Bed slope using L.S.
furnished or assume a suitable Slope
eg. 1 in 6000
(9)Adopt value of ‘n’ (whether it is lined or unlined)
(10)Calculation of Velocity, using Manning’s formula
(11)Check the permissible velocity as per standards
contd….
Design of Canal Section-Contd
(12)Calculation of designed Discharge(Qd)
i.e Qd = V A in cumecs
(14)In case ‘V’ & ‘Q’ are not within limits, revise
the canal section, by changing ‘FSD’
Design of Canal Section
Example-1
Design of Canal Section
Example-1:
Design a lined Canal of 15 Cumecs
carrying Capacity, assuming Bed Fall as
1 in 6000 and canal is in cutting and adopting
Fluming as 60%.
Design of Canal Section
Example-1(worked-out Calculations)
Contd….
Design of Canal Sections
• Examples & Exercises:
(5)Design a unlined Canal of 35 Cumecs
carrying Capacity, assuming Bed Fall as 1 in
4000, value of ‘n’ as 0.025 & Canal in cutting
(6)Design lined canal for 35 Cumecs of
carrying Capacity, assuming Bed Fall as 1 in 2000
& Canal in cutting
(7)Design lined canal for 35 Cumecs of
carrying Capacity, assuming Bed Fall as 1 in 4000
& Canal in cutting
Contd….
Design of Canals
Examples & Exercises:
(8)Design Lined Canal for Q = 15 Cum (n=0.018)
1 Guide for Plan ing layout of canal system for Ir igation IS:5968-1987
2 Criteria for design of cros section for unlined canals in al uvial soils IS:71 2-1973
3 Code of practice for design or cros section of lined canals IS:4745-1968
4 Code of practice for laying in situ cement concrete lin g on canals IS:3873-1978
5 Guide lines for lin g of canals in Expensive soils IS:9451-19 4
6 Criteria for hydraulic design of Regulators for canals IS:71 4-1973
7 Guide for location sel ction and hydraulic design of canal escapes IS:6936-19 2
8 Code of practice for design of cros drainage works (General features) IS:7 84(part-I)-19 3
9 Code of practice for design of cros drainage works (section -1,Aqueducts) IS:7 84 (part-2/section-1)-19 5
10 Code of practice for design of cros drainage works (section -2 superpas ages) IS:7 84 (part-2/section-2)-20 0
1 Code of practice for design of cros drainage works (section-3 canal syphons) IS:7 84 (part-2/1983-section-3)-19 6
12 Code of practice for design of cros drainage works (section-4 Level crosing) IS:7 84 (part-2/-section-4)-19 9
13 Code of practice for design of cros drainage works (section-5 syphon Aqueducts) IS:7 84 (part-2/-section-5)-20 0
14 Cur ent practices in canal design in India CBIP Technical report No-3
15 Design Practices for unlined incised canals CBIP Technical report No-7
16 Manual on Ir igation and Power Chan els CBIP -171
17 Text bo k of Ir igation Manual W.M.EL IS
49
THANK YOU
50