0% found this document useful (0 votes)
25 views22 pages

Project Management

Project Management formulas and methods.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views22 pages

Project Management

Project Management formulas and methods.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 22

TOP 20 PMP PM

CERTIFICATION
FORMULAS:
SSO Consultants
Content:
Cost Performance Schedule Estimate at
Cost Variance Schedule Variance
Index Performance Index Completion

Estimate to Variance at To-Complete Return on


Payback Period
Complete Completion Performance Index Investment

Estimate at
Internal Rate of Completion (EAC)
Return on Assets Net Present Value Planned Value
Return with Bottom-Up
Estimation

Estimate at
Schedule Estimate to Variance at
Cost Performance Completion (EAC)
Performance Index Complete (ETC) Completion (VAC)
Index (CPI) Forecast with To-Complete
(SPI) Forecast Forecast Forecast
Performance Index

2
1. Cost Performance Index:
• Formula: CPI = EV / AC
• Explanation: CPI measures the cost efficiency of
work completed.
• Example: If the Earned Value (EV) is ₹50,000 and the
Actual Cost (AC) is ₹60,000, then CPI = 50,000 /
60,000 = 0.83.
• It helps us assess whether we are under or over
budget and provides insights into the financial
performance of our project.

3
2. Schedule Performance Index (SPI):

• Formula: SPI = EV / PV
• Explanation: SPI measures the schedule
efficiency of work completed.
• Example: If the Earned Value (EV) is ₹50,000
and the Planned Value (PV) is ₹60,000, then
SPI = 50,000 / 60,000 = 0.83.
• It helps us evaluate whether we are ahead or
behind schedule and provides insights into
our project's time performance.
4
3. Cost Variance (CV):
• Formula: CV = EV - AC
• Explanation: CV measures the variance
between the earned value and the actual
cost.
• Example: If the Earned Value (EV) is ₹50,000
and the Actual Cost (AC) is ₹60,000, then CV
= 50,000 - 60,000 = -₹10,000.
• It helps us assess whether we are under or
over budget and provides insights into the
financial performance of our project.
5
4. Schedule Variance (SV):
• Formula: SV = EV - PV
• Explanation: SV measures the variance
between the earned value and the planned
value.
• Example: If the Earned Value (EV) is ₹50,000
and the Planned Value (PV) is ₹60,000, then
SV = 50,000 - 60,000 = -₹10,000.

6
5. Estimate at Completion (EAC):
• Formula: EAC = BAC / CPI or EAC = AC + (BAC -
EV) Explanation: EAC predicts the total
project cost based on performance.
• Example: If the Budget at Completion (BAC) is
₹1,00,000 and the Cost Performance Index
(CPI) is 0.83, then EAC = 1,00,000 / 0.83 =
₹1,20,482.
• It gives us insights into the expected final cost
and helps us make informed decisions about
budgeting and resource allocation.
7
6. Estimate to Complete (ETC):
• Formula: ETC = EAC - AC
• Explanation: ETC estimates the cost required
to complete the remaining work.
• Example: If the Estimate at Completion (EAC)
is ₹1,20,482 and the Actual Cost (AC) is
₹90,000, then ETC = 1,20,482 - 90,000 =
₹30,482.
• It provides insights into the financial forecast
and helps us make informed decisions about
resource allocation and budget management. 8
7. Variance at Completion (VAC):
• Formula: VAC = BAC - EAC
• Explanation: VAC indicates the variance
between the budgeted cost and the
estimated cost.
• Example: If the Budget at Completion (BAC) is
₹1,00,000 and the Estimate at Completion
(EAC) is ₹1,20,482, then VAC = 1,00,000 -
1,20,482 = -₹20,482.
• It helps us assess the financial performance
and forecast of the project. 9
8. To-Complete Performance Index (TCPI):

• Formula: TCPI = (BAC - EV) / (BAC - AC)


Explanation: TCPI represents the performance
required to achieve the desired project cost.
• Example: If the Budget at Completion (BAC) is
$150,000, the Earned Value (EV) is $100,000, and
the Actual Cost (AC) is $80,000, then the TCPI
would be:
• TCPI = ($150,000 - $100,000) / ($150,000 -
$80,000) = 0.7143
• It helps us assess the efficiency needed for the
remaining work to meet budget expectations. 10
9. Return on Investment (ROI):
• Formula: ROI = (Net Profit / Total
Investment) * 100
• Explanation: ROI measures the profitability of
an investment.
• Example: If the Net Profit is ₹50,000 and the
Total Investment is ₹2,00,000, then ROI =
(50,000 / 2,00,000) * 100 = 25%.
• It helps us assess the financial performance
and efficiency of our project or initiative.
11
10. Payback Period:
• Formula: Payback Period = Initial Investment /
Annual Cash Inflows
• Explanation: Payback Period determines the
time required to recover the initial investment.
• Example: If the Initial Investment is ₹1,00,000
and the Annual Cash Inflows are ₹25,000, then
the Payback Period = 1,00,000 / 25,000 = 4
years.
• It provides insights into the financial recovery
and risk associated with the investment. 12
11. Return on Assets (ROA):
• Formula: ROA = Net Income / Total Assets
• Explanation: ROA measures the efficiency of
utilizing assets to generate income.
• Example: If the Net Income is ₹50,000 and
the Total Assets are ₹5,00,000, then ROA =
50,000 / 5,00,000 = 0.1 or 10%.

13
12. Net Present Value (NPV):
• Formula: NPV = Sum of (Cash Flows / (1 +
Discount Rate)^n)
• Explanation: NPV calculates the present value
of future cash flows.
• Example: If the Cash Flows are -₹10,000,
₹3,000, ₹4,000, ₹5,000, and the Discount Rate
is 10%, then NPV = (-10,000 / (1 + 0.1)^0) +
(3,000 / (1 + 0.1)^1) + (4,000 / (1 + 0.1)^2) +
(5,000 / (1 + 0.1)^3).
14
13. Internal Rate of Return (IRR):
• Formula: Calculate the discount rate that
makes the NPV zero.
• Explanation: IRR determines the discount rate
that equates the present value of cash
inflows with the present value of cash
outflows.
• Example: Solve for the discount rate that
makes the NPV zero using the NPV formula.

15
14. Planned Value (PV):

• Formula: PV = BAC * Planned % Complete


• Explanation: PV represents the estimated
value of the work planned to be completed.
• Example: If the Budget at Completion (BAC) is
₹1,00,000 and the Planned % Complete is
40%, then PV = 1,00,000 * 0.4 = ₹40,000.

16
15. Estimate at Completion (EAC) with Bottom-Up Estimation:

• Formula: EAC = AC + Bottom-Up Estimate


• Explanation: EAC incorporates a new
estimate for the remaining work based on
detailed bottom-up estimation.
• Example: If the Actual Cost (AC) is ₹90,000
and the Bottom-Up Estimate is ₹30,000, then
EAC = 90,000 + 30,000 = ₹1,20,000.

17
16. Cost Performance Index (CPI) Forecast:

• Formula: CPI Forecast = EV / EAC


• Explanation: CPI Forecast predicts the future
cost efficiency of work.
• Example: If the Earned Value (EV) is ₹50,000
and the Estimate at Completion (EAC) is
₹1,20,482, then CPI Forecast = 50,000 /
1,20,482 = 0.4155.

18
17. Schedule Performance Index (SPI) Forecast:

• Formula: SPI Forecast = EV / EAC


• Explanation: SPI Forecast predicts the future
schedule efficiency of work.
• Example: If the Earned Value (EV) is ₹50,000
and the Estimate at Completion (EAC) is
₹1,20,482, then SPI Forecast = 50,000 /
1,20,482 = 0.4147.

19
18. Estimate to Complete (ETC) Forecast:

• Formula: ETC Forecast = EAC - AC


• Explanation: ETC Forecast estimates the cost
required to complete the remaining work
based on the current performance.
• Example: If the Estimate at Completion (EAC)
is ₹1,20,482 and the Actual Cost (AC) is
₹90,000, then ETC Forecast = 1,20,482 -
90,000 = ₹30,482.

20
19. Variance at Completion (VAC) Forecast:

• Formula: VAC Forecast = BAC - EAC


• Explanation: VAC Forecast indicates the
projected variance between the budgeted cost
and the estimated cost based on current
performance.
• Example: If the Budget at Completion (BAC) is
₹1,00,000 and the Estimate at Completion
(EAC) is ₹1,20,482, then VAC Forecast =
1,00,000 - 1,20,482 = -₹20,482.
21
20. Estimate at Completion (EAC) with To-Complete Performance
Index (TCPI):

• Formula: EAC = AC + (BAC - EV) / TCPI


• Explanation: EAC considers the required
performance to achieve the desired project cost
based on TCPI.
• Example: If the Actual Cost (AC) is ₹90,000, the
Budget at Completion (BAC) is ₹1,00,000, the
Earned Value (EV) is ₹10,000, and the To-Complete
Performance Index (TCPI) is 0.88, then EAC =
90,000 + (1,00,000 - 10,000) / 0.88 = ₹1,93,182.
22

You might also like