Project Management
Project Management
CERTIFICATION
FORMULAS:
SSO Consultants
Content:
Cost Performance Schedule Estimate at
Cost Variance Schedule Variance
Index Performance Index Completion
Estimate at
Internal Rate of Completion (EAC)
Return on Assets Net Present Value Planned Value
Return with Bottom-Up
Estimation
Estimate at
Schedule Estimate to Variance at
Cost Performance Completion (EAC)
Performance Index Complete (ETC) Completion (VAC)
Index (CPI) Forecast with To-Complete
(SPI) Forecast Forecast Forecast
Performance Index
2
1. Cost Performance Index:
• Formula: CPI = EV / AC
• Explanation: CPI measures the cost efficiency of
work completed.
• Example: If the Earned Value (EV) is ₹50,000 and the
Actual Cost (AC) is ₹60,000, then CPI = 50,000 /
60,000 = 0.83.
• It helps us assess whether we are under or over
budget and provides insights into the financial
performance of our project.
3
2. Schedule Performance Index (SPI):
• Formula: SPI = EV / PV
• Explanation: SPI measures the schedule
efficiency of work completed.
• Example: If the Earned Value (EV) is ₹50,000
and the Planned Value (PV) is ₹60,000, then
SPI = 50,000 / 60,000 = 0.83.
• It helps us evaluate whether we are ahead or
behind schedule and provides insights into
our project's time performance.
4
3. Cost Variance (CV):
• Formula: CV = EV - AC
• Explanation: CV measures the variance
between the earned value and the actual
cost.
• Example: If the Earned Value (EV) is ₹50,000
and the Actual Cost (AC) is ₹60,000, then CV
= 50,000 - 60,000 = -₹10,000.
• It helps us assess whether we are under or
over budget and provides insights into the
financial performance of our project.
5
4. Schedule Variance (SV):
• Formula: SV = EV - PV
• Explanation: SV measures the variance
between the earned value and the planned
value.
• Example: If the Earned Value (EV) is ₹50,000
and the Planned Value (PV) is ₹60,000, then
SV = 50,000 - 60,000 = -₹10,000.
6
5. Estimate at Completion (EAC):
• Formula: EAC = BAC / CPI or EAC = AC + (BAC -
EV) Explanation: EAC predicts the total
project cost based on performance.
• Example: If the Budget at Completion (BAC) is
₹1,00,000 and the Cost Performance Index
(CPI) is 0.83, then EAC = 1,00,000 / 0.83 =
₹1,20,482.
• It gives us insights into the expected final cost
and helps us make informed decisions about
budgeting and resource allocation.
7
6. Estimate to Complete (ETC):
• Formula: ETC = EAC - AC
• Explanation: ETC estimates the cost required
to complete the remaining work.
• Example: If the Estimate at Completion (EAC)
is ₹1,20,482 and the Actual Cost (AC) is
₹90,000, then ETC = 1,20,482 - 90,000 =
₹30,482.
• It provides insights into the financial forecast
and helps us make informed decisions about
resource allocation and budget management. 8
7. Variance at Completion (VAC):
• Formula: VAC = BAC - EAC
• Explanation: VAC indicates the variance
between the budgeted cost and the
estimated cost.
• Example: If the Budget at Completion (BAC) is
₹1,00,000 and the Estimate at Completion
(EAC) is ₹1,20,482, then VAC = 1,00,000 -
1,20,482 = -₹20,482.
• It helps us assess the financial performance
and forecast of the project. 9
8. To-Complete Performance Index (TCPI):
13
12. Net Present Value (NPV):
• Formula: NPV = Sum of (Cash Flows / (1 +
Discount Rate)^n)
• Explanation: NPV calculates the present value
of future cash flows.
• Example: If the Cash Flows are -₹10,000,
₹3,000, ₹4,000, ₹5,000, and the Discount Rate
is 10%, then NPV = (-10,000 / (1 + 0.1)^0) +
(3,000 / (1 + 0.1)^1) + (4,000 / (1 + 0.1)^2) +
(5,000 / (1 + 0.1)^3).
14
13. Internal Rate of Return (IRR):
• Formula: Calculate the discount rate that
makes the NPV zero.
• Explanation: IRR determines the discount rate
that equates the present value of cash
inflows with the present value of cash
outflows.
• Example: Solve for the discount rate that
makes the NPV zero using the NPV formula.
15
14. Planned Value (PV):
16
15. Estimate at Completion (EAC) with Bottom-Up Estimation:
17
16. Cost Performance Index (CPI) Forecast:
18
17. Schedule Performance Index (SPI) Forecast:
19
18. Estimate to Complete (ETC) Forecast:
20
19. Variance at Completion (VAC) Forecast: