HEMP Lesson 4
HEMP Lesson 4
plans and forms a key component of the overall risk management plan. The
There are numerous steps that make up the risk response plan, including
Therefore, a response plan fits within the project plan and outlines actions
required. This plan increases the likelihood and outcome of the identified
opportunities, while decreasing the impacts of risks. The response plan is a
strategy used to consider proactive actions, whereby risk responses are about
preventing risk rather than cancelling the project all together. Within the
PMBOK, there are 2 types of risk response plans: contingency and mitigation.
Contingency plan The contingency response plan outlines the responses
and actions to be implemented if or when a risk occurs (Heimann 2000).
Triggers are defined as the cues to execute contingency risk plans.
It is mandatory to track and define the risk triggers to develop the risk
contingency responses. As different triggers occur in the environment,
the reserves can be used. Both opportunities and risks should be
planned for within contingency plans (Heimann 2000). This includes any
event which poses a risk or a threat to the project – defined as a
negative risk. Whereas any event which offers an opportunity for the
project is defined as a positive risk. Across both these events, the
response planning is in place to ensure that the most is made out of any
opportunity and to provide a strategy to respond to and overcome risks.
Steps for creating the contingency plan:
4. Monitor and report the contingency plan, ensuring it is up-to-date with all
potential risks.
There are 6 primary components of a contingency plan:
There are 4 common challenges that project managers and project teams
face when trying to use contingency planning for risks:
• project team and stakeholders may be more confident in their original plan
3. Risk prioritisation: all identified risks are prioritised and ranked by the
most critical to the least.
5. Risk tracking: throughout the project, the risks are identified and added
to the register.
Mitigation plan content should include:
• Roles and responsibilities: this includes documenting who is responsible for identifying
and implementing risks.
◦ How will the actions decrease the levels of likelihood and consequence for the potential
risks if they were to occur?
The actions required should be completed through one of the
processes below:
• Understanding clients and stakeholder needs: who are the risk decision-
makers and who has the authority to accept and avoid risks?
• Liaising with subject matter experts: seek input from experts inside and
outside of the organisation.
• Not all risks require mitigation: low ranked risks do not require
considerable mitigation planning; however, they need to be tracked,
monitored and controlled in case of changes. The post-project review
should include the risk management process, including learnings from the
project, an analysis of how the project went, an evaluation of what occurred
during the project, whether there needs to be improvements, and what
went well.
Monitoring and controlling process
• Regular risk reviews. At least once a week, the project manager and team
should allocate time to review the identified risks, identify new risks and
monitor progress of all the risks which have been triggered or up/down
graded. This process should include a periodic, in-detail review of the entire
• Project risk reporting. This involves ensuring that risk exposure levels are
outlined within the status and performance reporting. This includes any
These include:
• Risk response plan: outlines the current state of risks, the potential future impacts
if the risk was to occur and the responses required.
• Change requests: a log which includes the variations, change orders and changes
implemented throughout the project.
• Post project review: understanding the effectiveness of the project risk responses
and overall management process within the project. This includes identifying
opportunities for improvement.
Tools for project risk monitoring and controlling There are many tools
which can be used to support monitoring and controlling in the project
risk management space. The tools can be either manual or automated.
These tools include project risk audits, status reporting and meetings,
project risk assessments, change variance, and risk trend analysis.
These processes can be run manually or streamlined to be automated,
depending on the size of the project, the complexity and the industry.