The Basics of Capital Budgeting Evaluating Cash Flows
The Basics of Capital Budgeting Evaluating Cash Flows
Steps
1. Estimate CFs (inflows & outflows). 2. Assess riskiness of CFs. 3. Determine k = WACC for project. 4. Find NPV and/or IRR. 5. Accept if NPV > 0 and/or IRR > WACC.
The number of years required to recover a projects cost, or how long does it take to get the businesss money back?
2.4
3 80 50
60 100 -30 0
= 2.375 years
1.6 2
3 20 40
70 100 50 -30 0 20
Strengths of Payback: 1. Provides an indication of a projects risk and liquidity. 2. Easy to calculate and understand. Weaknesses of Payback: 1. Ignores the TVM. 2. Ignores CFs occurring after the payback period.
NPV !
t !1
CFt
1 k
CF0 .
NPVS = $19.98.
Calculator Solution
Enter in CFLO for L: -100 10 60 80 10 CF0 CF1 CF2 CF3 I NPV = 18.78 = NPVL
IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0.
1 10
2 60
3 80
Enter CFs in CFLO, then press IRR: IRRL = 18.13%. IRRS = 23.56%.
1 40
2 40
-100
PV
3 40
40
PMT
0
FV
9.70%
Q. A.
How is a projects IRR related to a bonds YTM? They are the same thing. A bonds YTM is the IRR if you invest in the bond.
1
IRR = ?
0 -1,134.2
10
...
90 90 1,090
NPV ($)
60 50 40 30 20 10 0 0 -10 5 10 15 20 23.6
NPVL 50 33 19 7 (4)
NPVS 40 29 20 12 5
IRRS = 23.6%
NPV and IRR always lead to the same accept/reject decision for independent projects:
NPV ($) IRR > k and NPV > 0 Accept. k > IRR and NPV < 0. Reject.
k (%) IRR
k < 8.7: NPVL> NPVS , IRRS > IRRL CONFLICT k > 8.7: NPVS> NPVL , IRRS > IRRL NO CONFLICT
IRRS
8.7
%
IRRL
Managers like rates--prefer IRR to NPV comparisons. Can we give them a better IRR?
Yes, MIRR is the discount rate which causes the PV of a projects terminal value (TV) to equal the PV of costs. TV is found by compounding inflows at WACC. Thus, MIRR assumes cash inflows are reinvested at WACC.
1 10.0
10% MIRR = 16.5%
2 60.0
10%
-100.0 PV outflows
To find TV with 10B, enter in CFLO: CF0 = 0, CF1 = 10, CF2 = 60, CF3 = 80 I = 10 NPV = 118.78 = PV of inflows. Enter PV = -118.78, N = 3, I = 10, PMT = 0. Press FV = 158.10 = FV of inflows. Enter FV = 158.10, PV = -100, PMT = 0, N = 3. Press I = 16.50% = MIRR.
k = 10%
Enter CFs in CFLO, enter I = 10. NPV = -386.78 IRR = ERROR. Why?
We got IRR = ERROR because there are 2 IRRs. Nonnormal CFs--two sign changes. Heres a picture:
NPV
NPV Profile
IRR2 = 400%
Could find IRR with calculator: 1. Enter CFs as before. 2. Enter a guess as to IRR by storing the guess. Try 10%: 10 STO IRR = 25% = lower IRR Now guess large IRR, say, 200: 200 STO IRR = 400% = upper IRR
When there are nonnormal CFs and more than one IRR, use MIRR:
0 -800,000 1 5,000,000 2 -5,000,000
Accept Project P?
NO. Reject because MIRR = 5.6% < k = 10%. Also, if MIRR < k, NPV will be negative: NPV = -$386,777.
S and L are mutually exclusive and will be repeated. k = 10%. Which is better? (000s) 0 1 2 60 33.5 33.5 33.5 3 4
NPVL > NPVS. But is L better? Cant say yet. Need to perform common life analysis.
Note that Project S could be repeated after 2 years to generate additional profits. Can use either replacement chain or equivalent annual annuity analysis to make decision.
(000s)
60 60
60 60
NPV = $7,547.
If the cost to repeat S in two years rises to $105,000, which is best? (000s) 0 1 2 3 4
Project S: (100) 60
60 (105) (45)
60
60
Consider another project with a 3-year life. If terminated prior to Year 3, the machinery will have positive salvage value. Year 0 1 2 3 CF ($5,000) 2,100 2,000 1,750 Salvage Value $5,000 3,100 2,000 0
1. No termination
0 (5)
2 2 4
3 1.75
Assuming a 10% cost of capital, what is the projects optimal, or economic life?
Conclusions The project is acceptable only if operated for 2 years. A projects engineering life does not always equal its economic life.
(More...)
If external funds will be raised, then the NPV of all projects should be estimated using this higher marginal cost of capital.
Capital Rationing
Capital rationing occurs when a company chooses not to fund all positive NPV projects. The company typically sets an upper limit on the total amount of capital expenditures that it will make in the upcoming year.
(More...)
Reason: Companies want to avoid the direct costs (i.e., flotation costs) and the indirect costs of issuing new capital. Solution: Increase the cost of capital by enough to reflect all of these costs, and then accept all projects that still have a positive NPV with the higher cost of capital.
(More...)
Reason: Companies dont have enough managerial, marketing, or engineering staff to implement all positive NPV projects. Solution: Use linear programming to maximize NPV subject to not exceeding the constraints on staffing.
(More...)
Reason: Companies believe that the projects managers forecast unreasonably high cash flow estimates, so companies filter out the worst projects by limiting the total amount of projects that can be accepted. Solution: Implement a post-audit process and tie the managers compensation to the subsequent performance of the project.