5.0 - Project Scheduling 1
5.0 - Project Scheduling 1
Project Scheduling
- is simply the project plan in an altered format. It is a
convenient form for monitoring and controlling project
activities.
TASK Predecessor
a none
b none
c a
d b
e b
f c,d
g e
AON Network Stage 1
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AON Network - Stage 2
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AON Network - Complete
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AOA Network – Stage 1
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AOA network – Stage 2
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AOA Network – Showing The Use of a Dummy Task
TASK Predece
ssor f
a none
b none
c a
d b
e b g
f c,d
g e
AOA Network - Complete
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d e
g e
Information Contents in an AON
Node
Calculating Activity Slack
Note : Ex for activity B, even though delay 7 days, it wouldn’t affect the OCT, still
can finish in 21 days
(b a)
6
2
(b a )
Var
2
6
95 Percent Level
Task will be a or lower 5 percent of the time
Task will be b or greater 5 percent of the time
(b a )
3.3
90 Percent Level
Task will be a or lower 10 percent of the time
Task will be b or greater 10 percent of the time
(b a )
2.6
Project Uncertainty & Risk
Management
Ex. of Probabilistic Network
A sample set of project activities with uncertain durations
Activity Pred. Opt Norm Pess TE VAR
a m b (a + 4m + b) / 6 ( (b-a) / 6 ) 2
A None 8 10 16
B A 11 12 14
C B 7 12 19
D B 6 6 6
E B 10 14 20
F C,D 6 10 10
G D 5 10 17
H E, G 4 8 11
Find the expected time and variance for each task :