0% found this document useful (0 votes)
24 views

5.0 - Project Scheduling 1

Projecm 1

Uploaded by

xena.jocel.buera
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views

5.0 - Project Scheduling 1

Projecm 1

Uploaded by

xena.jocel.buera
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 29

PROJECT SCHEDULING

Project Scheduling
- is simply the project plan in an altered format. It is a
convenient form for monitoring and controlling project
activities.

- Commonly used formats :


• Gantt Chart
• PERT/CPM Networks – both methods employed
networks to schedule and display task sequences.
History
 Late 1950s
• Program Evaluation and Review Technique (PERT)
• It was developed by the U.S. Navy, Booz-Allen Hamilton (a business
consulting firm), and Lockheed Aircraft (now Lockheed Martin Corp.)
• Probabilistic (or uncertain) estimates of activity durations
• Critical Path Method (CPM)
• Dupont De Nemours Inc. developed the method
• Deterministic (or certain) estimates of activity durations
The Language of PERT/CPM
 Activity
• task or set of tasks required by the project.
• uses resources and time
 Event
• An identifiable state resulting from completion of one or more
activities
• consumes no resources or time
• Before an event can be achieved or realized, all its predecessor
activities must be completed
The Language of PERT/CPM continued
 Milestones
• Identifiable and noteworthy events that mark significant
progress on the project.
 Network
• diagram of nodes and arrows
• used to illustrate technological relationships of all
activities.
• Networks usually drawn with a “start” node on the left
and a “Finish” node on the right.
• Arcs are always tipped with an arrowhead to show the
direction of precedence, that is, from predecessors to
successors.
The Language of PERT/CPM concluded
 Path
• series of connected activities (or intermediate events) between
any two events in a network
 Critical Path
• set of activities on a path from the project’s start event to its finish
event, that, that if delayed, will delay completion date of the of
project
 Critical Time
• time required to complete all activities on the critical path
Building the Network
 Activities on Arrows (AOA) Network
- We depict the activities as arrows and events
as nodes.
- Usually associated with PERT
 Activities on Nodes (AON) Network
- Showing each tasks as a node and linking the
nodes with arrows that show their
technological relationship.
- Usually associated with CPM.
Given : A set of project activities and precedence

TASK Predecessor
a none
b none
c a
d b
e b
f c,d
g e
AON Network Stage 1
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AON Network - Stage 2
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AON Network - Complete
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AOA Network – Stage 1
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AOA network – Stage 2

TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d
g e
AOA Network – Showing The Use of a Dummy Task

TASK Predece
ssor f
a none
b none
c a
d b
e b g
f c,d
g e
AOA Network - Complete
TASK Predece
ssor
a none
b none
c a
d b
e b
f c,d e
g e
Information Contents in an AON
Node
Calculating Activity Slack

 Latest Start Time (LST) – Earliest Start Time (EST)


= Slack (excess time or unutilized time)
 Latest Finish time (LFT) – Earliest Finish time (EFT)
= Slack
Activity Predecessor Duration
Exercise
A None 5 days
B None 4
C A 3
D A 4
E A 6
F B,C 4
G D 5
H D, E 6
I F 6
J G, H 4

(a) Construct the network diagram in AOA & AON


(b) Find each activity’s EST, EFT, LST & LFT
(c) Identify all path. Which path is the critical path ?
(d) Calculate the slack for each activity
(e) How long will it take to complete the project ?
LST-EST LFT-LET Slack Time
A
B
C
D
E
F
G
H
I
J
LST-EST LFT-LET Slack Time
A 0–0 5–5 0
B 7–0 11 – 4 7
C 8–5 11 – 8 3
D 7–5 11 – 9 2
E 5–5 11 – 11 0
F 11 – 8 15 – 12 3
G 12 – 9 17 – 14 3
H 11 – 11 17 – 17 0
I 15 – 12 21 – 18 3
J 17 – 17 21 – 21 0

Note : Ex for activity B, even though delay 7 days, it wouldn’t affect the OCT, still
can finish in 21 days

Note : Activity A, E, H & J – CRITICAL, cannot delay


• Three Time Estimates
- Optimistic (a)
- Most Likely (m)
- Pessimistic (b)
The Statistical Distribution of all Possible
Times for an Activity
Activity Expected Time and Variance
( a  4m  b)
TE 
6

(b  a)

6

2
 (b  a ) 
Var  
2

 6 
95 Percent Level
Task will be a or lower 5 percent of the time
Task will be b or greater 5 percent of the time

(b  a )

3.3
90 Percent Level
Task will be a or lower 10 percent of the time
Task will be b or greater 10 percent of the time

(b  a )

2.6
Project Uncertainty & Risk
Management
Ex. of Probabilistic Network
A sample set of project activities with uncertain durations
Activity Pred. Opt Norm Pess TE VAR
a m b (a + 4m + b) / 6 ( (b-a) / 6 ) 2
A None 8 10 16
B A 11 12 14
C B 7 12 19
D B 6 6 6
E B 10 14 20
F C,D 6 10 10
G D 5 10 17
H E, G 4 8 11
Find the expected time and variance for each task :

Activity Pred. Opt Norm Pess TE VAR


a m b (a + 4m + b) / 6 ( (b-a) / 6 ) 2
A None 8 10 16 10.67 1.68
B A 11 12 14
C B 7 12 19
D B 6 6 6
E B 10 14 20
F C,D 6 10 10
G D 5 10 17
H E, G 4 8 11

You might also like