Switchyard Schemes
Switchyard Schemes
and Layout of
EHV Switchyards
By
S.Kameshwaran
Contents
Introduction
Bay Width
Live as if your were to die tomorrow. Learn as if you were to live forever.
- Mahatma Gandhi
In my life, I have never learned anything from any man who agreed with
me.
- Dudley Field Malone l
He who asks a question is a fool for five minutes; he who does not ask
a question remains a fool forever
- Chinese Proverb l
Introduction
Generating Substation
Primary Grid Substation (400 kV, 220 kV, 110 kV)
Secondary Substation (220 kV, 110 kV, 66 kV)
Distribution Substation (33 kV & below)
Bulk Supply and Industrial Substation (EHV/6.6 or 11kV)
Various Bus arrangements
Reliability
Cost
Space
Operational Flexibility
Ease of Maintenance
Maintenance of Breaker
Maintenance of Bus bars & Insulators
Single Bus arrangement
I/C
O/G-1 O/G-2
Single Bus arrangement
I/C
O/G-1 O/G-2
Single Bus arrangement
I/C
O/G-1 O/G-2
Single Bus arrangement
I/C
O/G-1 O/G-2
Single Bus arrangement
1 out of 2 I/L
Single Bus arrangement
1 out of 2 I/L
Single Bus arrangement
1 out of 2 I/L
Single Bus arrangement
Merits
Simple
Cheapest
Require Less space
Demerits
Maintenance of Breaker without affecting the feeder is not
possible
Maintenance of Bus without affecting the feeder is not possible
Comments
Preferred for lower voltage levels up to 110 kV, rarely in 220 kV &
never in 400 kV
Single Bus with Bus Sectionaliser
Layout
Plan Layout
Section
Single Bus with Bus Sectionaliser
Merits
Economic
Any outage can be confined to one section of the bus bar
Demerits
Maintenance of Breaker without affecting the feeder is not
possible
Maintenance of Bus without affecting the feeder is not possible
Constraints
Full advantage of the scheme is realized by distributing the
incoming & outgoing feeders evenly on either section
The use of Isolator for bus sectionalizing does not fulfill the
purpose. The isolators have to be operated “off circuit” and it
may present to obtain zero current across the section.
Single Main & Transfer Bus
Main Bus
Transfer Bus
TBC Bay
Normal operation
Main Bus
Transfer Bus
TBC Bay
Main Bus
Transfer Bus
TBC Bay
Layout
Plan & Section
Single Main & Transfer Bus
Features
While Main Bus is sized for entire Station Load, Transfer bus is designed to
take only one feeder load, as TBC CB can act as feeder breaker only for one
feeder & not for >1
Merits
Provides facility to carry out breaker maintenance
Demerits
Does not Provide facility to carry out Bus maintenance
Only one feeder breaker can be taken for maintenance at a time
Constraints
In order to carry out breaker maintenance, the circuit is changed over to
the Transfer bus & controlled by Bus Transfer breaker through a Trip
Transfer Switch.
All tripping signals to be routed to TBC breaker
Normally, applicable upto 132kV only
Double Main Bus
Main-2 Bus
B/C
Main-1 Bus
Main-2 Bus
B/C
Main-1 Bus
Main-2 Bus
B/C
Main-1 Bus
Main-2 Bus
B/C
Layout
Plan & Section
Double Main Bus
Features
Utilizes 2 identical buses, each sized for complete station load
Load can be fed from either buses. Incomer & loads shall be grouped
based on operational considerations
Bus coupler breaker, is invariably provided, as it enables “on load” change
over from one bus bar to the other.
For normal operations, Bus isolators are interlocked such that the feeders
are closed on only one of the buses, except under load transfer conditions,
where both the isolators can be closed as BC feeder would have been
closed then.
CT Switching required for proper Bus bar protection
Normally applicable for 220 & 400 kV levels
Merits
Provides facility to carry out Bus maintenance
Demerits
Does not Provide facility to carry out Breaker maintenance
Double Main & Transfer Bus
Main-1 Bus
Main-2 Bus
Normal operation
Transfer Bus
Main-1 Bus
Main-2 Bus
Main-1 Bus
Main-2 Bus
Layout
Plan & Section
Double Main & Transfer Bus
Features
This is a combination of double main bus and Main & Transfer Bus
Each Main bus is designed to cater to the complete station load,
while Transfer bus is designed to take only one feeder load, as TBC
CB can act as feeder breaker only for one feeder & not for >1
Normally used at 220 & 400 kV levels to improve reliability &
where cost is not a concern
CT Switching required for proper Bus bar protection
Merits
Provides facility to carry out Bus maintenance as well as Breaker
maintenance
Demerits
Costly
Requires more space
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme
Substation-A
B
Substation-C
Substation-B
1 ½ Breaker Scheme
Main-2 Bus
1 ½ Breaker Scheme – ‘D’ Layout
Main-2 Bus
1 ½ Breaker Scheme – ‘D’ Layout
Layout
Plan
Layout
Section
1 ½ Breaker Scheme
Features
Three circuit breakers are used for connecting the two feeders &
hence “one and a half breaker” name for the scheme
Used at 400 kV levels only
Depending on availability of space I or D type is picked
Merits
More flexible than any of the above schemes & continuity of supply
can be assured
Interconnection of feeders in each bay can be maintained even
without energizing the main bus bars (LILO)
Both breaker and Bus Maintenance are possible
Avoids the need of the bus coupler
Demerits
Expensive arrangement
Mesh scheme
Layout Plan
Mesh scheme
Features
Provides double feed to each circuit – opening of one breaker
under maintenance or otherwise does not affect the supply to
any circuit
Only 220 kV Ring Main Scheme in India executed by L&T at
PPN project.
Merits
Permits breaker maintenance without interrupting the
continuity of supply
All sections of conductor in the station are covered by feeder
protection & vis-à-vis Distance, Differential no separate bus
protection is needed
Constraints
Suggested only when there is a limited number of circuits are
to be connected & future extension is never envisaged
Clearances
Safety Clearances
Phase to Earth Clearance
in an Outdoor
Switchyard
Sectional Clearance
Ground Clearance
Clearances
Please note that the minimum clearance different from spacing adopted.
Insulation Levels
System Voltage in kV
220kV
DMT SY
with DBR
Isolator
220kV
DMT SY
with HCB
Isolator
Phase Sequence
400kV
R Y B
CT Location
BBP BBP
‘1’ ‘2’
H J
‘Z’
G LP
Line Protection LP K L
‘H’ ‘J’
Busbar Protection LP LP
‘K’ ‘L’
Teed-1
Teed-2
Metering
Distance – M2
Distance - M1
Metering
Teed-1
Teed-2
Busbar M1
Busbar M2
Metering
Teed – 2
Teed - 1
Earth Switches
Earth Switches are provided in a Switchyard to ensure safe working of men and
machinery during maintenance.
It is important to note the location of the Earth Switch before erection to ensure
the above. Check the following
Location of Earth Switches as in SLD
E/S at Isolator (Male or Female contact side) with respect to moving
contact opening direction
Fouling of Earth Switch moving contact with nearby Tower
Earth Switches
Layout Plan
showing
location of
Earth
Switches
Earth Switches
Female contact
Earth Switch
Male contact
Earth Switch
Earth Switch on Male contact side
Earthing
Practice Share