C3 MGMT8360 Estimating Duration
C3 MGMT8360 Estimating Duration
Estimating Tasks
in MS Project
Week 3 Agenda
Work involved
Also, depends
+ on the resource
assigned to the
task
Elapsed time
Estimating Activity Duration
Discretionary Dependencies
Preferred logic to execute work
Best practices
External Dependencies
Relationships outside project
Other projects
Operations
Leads and Lags
Example
Most likely estimate: 8 hours
Pessimistic estimate: 16 hours
Optimistic estimate: 6 hours
Estimate = (6 + 4 x 8+ 16) / 6 = 9 hours
Estimate Effort techniques