ASCI - Managing Contract Modifications - Variations - 14 Dec 2022
ASCI - Managing Contract Modifications - Variations - 14 Dec 2022
Environment “
ASCI , Hyderabad , 14th December 2022
Managing Contract
Modifications / Variations
A. Venkateshwar BE , IRAS
President , Acceleron India
Former Consultant , Ministry of Railways ,
GOI
In this discussion …
• A variations register is used to administer and keep track of the status of a variation.
Normally, the contractor has a tendency to report and claim positive variations
(variations causing higher payments) and may not report negative variations. However,
the client must keep track of such negative variations and issue timely letters.
• This shall cover the following important steps:
a) The client ’s prior approval of the issue of the variation instruction;
b) The client ‘s instruction to the contractor (this letter creates the variation).
c) The variation instruction letter must be given a unique number in the register;
d) The status of the variation has to be updated / summarized in the register monthly
e) The financial implications have to be kept upto date.
Introduction of Addl. Items in a Contract / Variations in existing Items
• Extra Works:
Should works over and above those included in the contract require to be executed at the site,
the Contractor shall have no right to be entrusted with the execution of such works which may be
carried out by another Contractor or Contractors or by other means at the option of the Railway.
• Separate Contracts in Connection with Works:
The Railway shall have the right to let other contracts in connection with the works.
The Contractor shall afford other Contractors reasonable opportunity for the storage of their
materials and the execution of their works and shall properly connect and coordinate his work
with theirs.
The Contractor's failure so-to inspect and report shall constitute an acceptance of the other
Contractor's work as fit and proper for the reception of his work.
• They shall be performed by the Contractor as provided therein and be subject to the same
conditions, stipulations and obligations as if they had been originally and expressively included
and provided for in the Specifications and Drawings .
Introduction of Addl. Items in a Contract / Variations in existing Items …1
• Items with rates higher or lower by more than 30% of the estimated rates shall be
considered as abnormally high or low rated items.
• During the course of execution, a constant watch shall be kept on any upward
variation in respect of the items having abnormal high rates (AHR)- for “Vitiation
of Contract”
• Normally, the quantity of AHR items should not be allowed to exceed the quantity
mentioned in the BOQ.
• However, in case of if quantity of AHR items > BOQ , the same shall have to be
approved by competent authority immediately on such increase , after checking
interse position of the bidders against the tender and supported by adequate
justification.
• The same procedure shall also be followed for deviation in any single item, which
has significant impact on the contract value (say above 5%).
Introduction of Addl. Items in a Contract / Variations in existing Items …2
Excess over Contract Value:
• In case of Item rate contracts, when the executed value is about 80% of the contract
value and is likely to be exceeded, the revised deviation statement shall be processed
for approval of competent authority.
• The circumstances leading to the excess with proper justifications of each item need
to be recorded.
• It is usually stipulated in the tender document that the contractor must enclose the
proposed deviation statement with the RA Bill once the executed value of work has
reached 80% of the awarded value.
• In case of maintenance contracts, there could be variation in individual quantity of
items.
• For variation in quantity within the contract value, the final deviation statement
should be approved by concerned HOD /DGM with due concurrence by associate
finance department.
Fixation of Rate in
Negotiations
Negotiating Principles …. World Bank guidelines
Valuation of Variations:
• In this regard variations , the perceived risks in quick finalisation of variations against the
opportunity costs of delayed decision making e.g. project delays, cost escalations, loss of
transparency etc must be balanced.
• The following are the steps to be taken by the Engineer:
a) To decide as to the applicability of the rates in BOQ and agree to use them
b) If not considered applicable, to use BOQ rates as the basis for a fresh valuation;
c) In the event of a disagreement, to develop new rates from first principles;
d) If there is disagreement, to fix the appropriate rate; and
e) To determine provisional rates to allow monthly certification.
• In case it is noticed that there is a significant variation in terms of both quantity and cost , the
client may seek the reasons of the Consultant if appointed and take action as deemed fit based
on the same.
Fixation of Rate in Negotiations for
Variations ..Ministry of Railways…1
Rates for Extra / new Items of Works:
• To be finalized in a meeting between Contractor and the Engineer i/c. ( Negotiating Tender
Committee)
• Any new SOR item of work - as per the "Schedule of Rates of Railway" at the tender % .
• Any new non – SOR items - at the rate agreed upon mutually . before their execution .
• Contractor to notify at least 7 days in advance of such execution.
• In case there is no agreement , the Railway shall get the extra works executed by other means .
• Contractor shall have no claim for loss or damage that may result from such procedure.
• The new / extra items added to the agreement ‘s scope shall not affect its validity.
• The rates shall be assessed based on
(i) the prevailing rates
(ii) Analysis of Unified Schedule of Rates of Indian Railways
(iii) Analysis of Delhi Schedule of Rates issued by CPWD
(iv) Market Analysis
Fixation of Rate in Negotiations for
Variations ..Ministry of Railways…2
Rates for Extra / new Items of Works:
• If the contract value fall below 75% or exceed 150% of the awarded value for tenders for capital
nature work estimated above Rs. 2 crore following may be incorporated in SCC.
• If due to variation/ amendments ,the gross value of work actually performed is < 75% of CV ,
then an additional 5% on the amount by which the CV falls short of 75% of total CV is payable to
the Contractor.
• Similarly if due to variation/ amendments , the gross value of work actually performed by the
Contractor is > 150% of CV, then a discount of 5% on the amount by which the CV exceeds
beyond 150% of total CV is leviable.
• Provision of incentives for completion of work before schedule should be sparingly made after
careful assessment of tangible benefits there from .
• If work completed is ahead of schedule a bonus limited to max. 5% of CV or executed CV ,
whichever is lower , is payable . The Incentive/bonus clause shall be included in SCC.
Deletion/ Modification or
Change of Clauses in Agreement
Deletion/ Modification or Change of Clauses in Agreement
Ministry of Finance
• In case any of the provisions of the contract are required to be modified after the
contract documents have been signed, the modifications shall be made in writing and
signed by the Railway and the Contractor
• No work shall proceed under such modifications until this has been done.
• Any verbal or written arrangement abandoning, modifying, extending, reducing or
supplementing the contract or any of the terms thereof shall be deemed conditional
• No modification shall be binding on the Railway unless and until the same is
incorporated in a formal instrument and signed by the Railway and the Contractor .
• Till then the Railway shall have the right to repudiate such arrangements.
Deletion/ Modification or Change of Clauses in Agreement
Ministry of Railways …2
Powers of Modification to Contract:
• The Contractor will not be entitled, to any compensation for any increase/reduction in
the quantities of work but will be paid only for the actual amount of work done and for
approved materials supplied against a specific order.
Deletion/ Modification or Change of Clauses in Agreement