JamilAhmed - 2355 - 16664 - 1 - Lecture007-Capital Budgeting Decisions
JamilAhmed - 2355 - 16664 - 1 - Lecture007-Capital Budgeting Decisions
Capital Budgeting
Decisions
Jamil Ahmed
Assistant Professor
Steps in the Process
1. Proposal Generation
3. Decision Making
4. Implementation
5. Follow-up
2
Net Present Value
$315,000
NPV 260,000 $26,363.64
(1.10)
Internal Rate of Return
The internal rate of return is the discount rate
that sets NPV of the expected cash flows to
zero.
The internal rate of return is the project’s
expected return.
Undertake a project if the IRR exceeds r, the
project’s cost of capital.
Calculating IRR
Recall that the IRR is the project’s expected return. Usually—
but not always—if the IRR exceeds the cost of capital, the NPV is
positive. This is always true for independent, conventional
projects.
Example: A project costs $100,000 and is expected
to generate a $28,600 cash flow per year for six
years. What is the project’s IRR?
IRR = 18.0123%
N=6 PV=-100,000 PMT=28,600 FV=0 i=18.0123
NPVL
IRR iL (iU iL )[ ]
NPVL NPVU
Using NPV and IRR
%
$1,000
.9 5
16
$-
0% 5% 10% 15% 20% 25%
$(1,000)
$(2,000)
Discount Rate
Types of Projects
A firm is considering two mutually exclusive one-year projects, with the cash
flows shown below. The cost of capital for both projects is 12%. Compute the
NPV and IRR for each project and indicate which one should be undertaken.
Project CF0 CF1 NPV IRR
Small -1,000 +1,200 71.43 20%
Big -8,000 +9,200 214.29 15%
Project L Project H
IRR 19.06% 22.59%
NPV @ 10% $3,685 $3,200
NPV @ 12.93% $2,330 $2,330
NPV @ 17.00% $716 $1,258
NPV Profiles for L and H
$12,000
$10,000
Project L
$8,000
NPV
$6,000
$4,000 Project H
$2,000
$0
0% 5% 10% 15% 20%
NPV
$0.06
$0.04
IRR =
$0.02 25%
$0.00
($0.06)
($0.08)
Decision Rule:
Undertake the project if the MIRR exceeds
the cost of capital.
Modified IRR: MIRR
A project with a 12% cost of capital costs $2,000, and is expected to return
$600 per year for five years plus a salvage value of $700 at the end of five
years. The MIRR = 17.6690% (IRR = 21.5226%):
1-24
Equivalent Annual Annuity Approach
1-25
Replacement Chain Method
Year 0 1 2 3 4 5 6 7 8 9 10 NPV
Solar
Park
Cash
7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50 7.50
flows
Investme
-20 -20
nt
Net cash
-20 7.50 7.50 7.50 7.50 -12.5 7.50 7.50 7.50 7.50 7.50
flows
PV
1 0.91 0.83 0.75 0.68 0.62 0.56 0.51 0.47 0.42 0.39
Factor
PV -20 6.82 6.20 5.63 5.12 -7.76 4.23 3.85 3.50 3.18 2.89 13.7
Wind
Farm
Cash
8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
flows
Investme
-35
nt
Net cash
-35 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00 8.00
flows
PV
1 0.91 0.83 0.75 0.68 0.62 0.56 0.51 0.47 0.42 0.39
Factor
PV -35 7.27 6.61 6.01 5.46 4.97 4.52 4.11 3.73 3.39 3.08 14.2
1-26