We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 14
Base Load and Peak Load on Power Station
The changing load on the power station makes
its load curve of variable nature. Fig. 3.13. shows the typical load curve of a power station. It is clear that load on the power station varies from time to time. However, a close look at the load curve reveals that load on the power station can be considered in two parts, namely;
(i) Base load
(ii) Peak load
(i) Base load. The unvarying load which occurs almost the whole day on the station is known as base load. Referring to the load curve of Fig. 3.13, it is clear that 20 MW of load has to be supplied by the station at all times of day and night i.e. throughout 24 hours. Therefore, 20 MW is the base load of the station. As base load on the station is almost of constant nature, therefore, it can be suitably supplied without facing the problems of variable load. (ii) Peak load. The various peak demands of load over and above the base load of the station is known as peak load.
Referring to the load curve of Fig. 3.13, it is
clear that there are peak demands of load excluding base load. These peak demands of the station generally form a small part of the total load and may occur throughout the day Method of Meeting the Load The total load on a power station consists of two parts viz., base load and peak load. In order to achieve overall economy, the best method to meet load is to interconnect two different power stations. The more efficient plant is used to supply the base load and is known as base load powerstation. The less efficient plant is used to supply the peak loads and is known as peak load power station. There is no hard and fast rule for selection of base load and peak load stations as it would depend upon the particular situation. For example, both hydro-electric and steam power stations are quite efficient and can be used as base load as well as peak load station to meet a particular load requirement Illustration. The interconnection of steam and hydro plants is a beautiful illustration to meet the load. When water is available in sufficient quantity as in summer and rainy season, the hydroelectric plant is used to carry the base load and the steam plant supplies the peak load as shown in Fig 3.14 (i). However, when the water is not available in sufficient quantity as in winter, the steam plant carries the base load, whereas the hydro-electric plant carries the peak load as shown in Fig. 3.14 (ii). Important Points in the Selection of Units While making the selection of number and sizes of the generating units, the following points should be kept in view : (i) The number and sizes of the units should be so selected that they approximately fit the annual load curve of the station (ii) The units should be preferably of different capacities to meet the load requirements. Although use of identical units (i.e., having same capacity) ensures saving* in cost, they often do not meet the load requirement. (iii) The capacity of the plant should be made 15% to 20% more than the maximum demand to meet the future load requirements. (iv) There should be a spare generating unit so that repairs and overhauling of the working units can be carried out. (v) The tendency to select a large number of units of smaller capacity in order to fit the load curve very accurately should be avoided. It is because the investment cost per kW of capacity increases as the size of the units decreases. Example 3.18. A proposed station has the following daily load cycle : Time in hours 6—8 8—11 11—16 16—19 19—22 22 —24 24—6 Load in MW 20 40 50 35 70 40 20 Draw the load curve and select suitable generator units from the 10,000, 20,000, 25,000, 30,000 kVA. Prepare the operation schedule for the machines selected and determine the load factor from the curve Solution. The load curve of the power station can be drawn to some suitable scale as shown in Fig. 3.12. Units generated per day = Area (in kWh) under the load curve = 103 [20 × 8 + 40 × 3 + 50 × 5 + 35 × 3 + 70 × 3 + 40 × 2] = 103 [160 + 120 + 250 + 105 + 210 + 80] kWh = 925 × 103 kWh Average load = 925 × 10 3/24= 38541·7 kW Load factor = 38541.7/70×103× 100 = 55·06% Selection of number and sizes of units : Assuming power factor of the machines to be 0·8, the output of the generating units available will be 8, 16, 20 and 24 MW. There can be several possibilities. However, while selecting the size and number of units, it has to be borne in mind that (i) one set of highest capacity should be kept as standby unit (ii) the units should meet the maximum demand (70 MW in this case) on the station (iii) there should be overall economy. Keeping in view the above facts, 4 sets of 24 MW each may be chosen. Three sets will meet the maximum demand of 70 MW and one unit will serve as a standby unit Operational schedule Referring to the load curve shown in Fig. 3.12, the operational schedule will be as under : (i) Set No. 1 will run for 24 hours. (ii) Set No. 2 will run from 8.00 hours to midnight. (iii) Set No. 3 will run from 11.00 hours to 16 hours and again from 19 hours to 22 hours