Bi Weekly HSE Report WE 12 Dec v2
Bi Weekly HSE Report WE 12 Dec v2
1.
1. Highlights
Highlights
2.
2.Achievements
Achievements
3.
3. Incidents
Incidents
4.
4. HSE
HSEStatistics
Statistics
5.
5. Key
KeyHSE
HSEActivities
Activities
6.
6. Training
TrainingStatistics
Statistics
7.
7. SOR’s
SOR’s
Highlights
Highlights
Contents
Page
• Gates 1 & 2 have made improvements with signage and better inspections of
personnel by security assigned at each gate.
• Samsung monthly HSE awards ceremony will be conducted 03 March 2014 at 1100.
• Beyond Zero training will be conducted March 5 th & 6th from 0800-1200 daily.
• One Near Miss involving man-lift at Pipe-Rack inside new Tank Farm area, Petrojet.
• Schedule was completed for the Bi-Weekly HSE meeting and distributed.
Achievements
Achievements
Contents
Page
• Marafiq Yanbu 2 project achieved 296 working days with a total of 18,056,436 man-
hours without Lost Time Incident.
• SADARA Chlorine project achieved 4,301,315 Man-hours without Lost Time Incident
(LTI).
• STWP project (Y1) achieved 1,065 working days with a total of 841,720 man-hours
without Lost Time Incident (LTI).
• LUBEREF project achieved 311 working days with a total of 760,403 man-hours
without Lost Time Incident (LTI).
• Fuel Supply project (Y1) achieved 879 working days with a total of 1.7 million man-
hours without Lost Time Incident (LTI).
Achievements
Achievements
Contents
Page
• RO4 project (Marafiq Jubail) achieved 431 working days with a total of 668,715 Man-
hours without Lost Time Incident (LTI).
• EPS project (Marafiq Jubail) achieved 277 working days with a total of 308,134 man-
hours without Lost Time Incident (LTI).
• IWTP-II project (Y1) achieved 90 working days injury free with a total of 533,302
man-hours without Lost Time Incident (LTI).
• STG 5 & 6 project (Y1) project achieved 616 working days with a total of 6.97 million
man-hours without Lost Time Incident (LTI).
• Small project (Y1) achieved 1,096 working days with a total of 2.38 million man-
hours without Lost Time Incident (LTI).
Incidents
Incidents
Contents
Page
Incidents
Incidents
Contents
Page
HSE
HSEStatistics
Statistics
Contents
Page
KSA YTD
WH TRI TRIR LTI LTIR
TOTAL 596,094 0 0 0 0
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
Luberef Project achieved 311 working days with a total of 760,403 man-hours without Lost
Time Incident (LTI).
HSE Concerns
Project expected to reach 1,000,000 man-hours on first week of January 2013, Everyone is
alerted to stay focused and continued monitor the site activities
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
HSE CONCERNS
Working near Live Power cables.
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
HSE Concerns
• Safety Campaign for “Chemical Handling Safety” and monitoring of civil activities.
• Start mobilization/site preparation for 4km cable outside activity and assigned Safety
Officer.
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
HSE Concerns
Provide additional life support at Switchgear and inspection of Third party SETE Excavator
for renewal and installation of access scaffold for electrical pull pits.
CPChem – Jubail
Site HSE Activities
• Hand Safety Awareness Campaign has been raised on 30 th November 2013. This campaign
set was continue for a minimum of 4 weeks to focus the PCC project on hand safety with
awareness talks, posters and signs to remind employees of hand safety and protection
methods.
• Develops Supervisor Orientation, Inspections of equipment and review new Jacobs HSEPs.
HSE Concerns
• They have significant observation on site were identified employees are not using 100% fall
protection, unstable of scaffold platforms and electrical cables laying on a wet surface.
• Safety issues on site are fall protection and specific tasks of SPA is not completed.
Project
ProjectHSE
HSEHighlights
Highlights
Contents
Page
SADARA Chlorine
• OSHA 30hours (classroom training) second session was conducted on 30 November 2013.
• Beyond Injury Free (BIF) Training session has been conducted by HSE Department for
staffs, next session to be scheduled and Jacobs Orientation for newly arrive at site.
SADARA PE
• Weekly HSE Walkthrough was organized & workers were rewarded as a part of ongoing
Safety Recognition program.
• Beyond Injury Free Training done at site was attended by 34 project team members.
• Monthly HSE meeting with the supervisors
• Emergency Response Drill for Electrocution had been conducted.
HSE
HSETraining
TrainingEfforts
Efforts
Contents
Page
SORs
SORs
Contents
Page
In Jacobs ZATE home office ground floor, the floor is very slippery, even when
dry. This might be due to very smooth surface of the tiles and/or too much
polish used.
Several of our doors from the elevator lobbies into our secure areas are in need
of maintenance so they will close well and lock securely. This is an office
security issue.
SORs
SORs
Contents
Page
Immediately removed the empty cartridge and informed facilities to clean the
scattered ink in the floor and trash bin cover.
Notice was placed near the printer warning employees no to attempt unauthorized
maintenance.
SOR
SORTrend
TrendAnalysis
Analysisfrom
from Sites*
Sites*
Contents
Page
1400 1,334
1200
996
1000
800
Total Positve
600
Total Negative
409
400
293
166
200 128
77 101
76 55 40
31 15 15 0 3
0
1 2 il L 4
he
m u u ba C PE EP
S
O
C nb nb Ju ar
a
ar
a
iq iq
R
P Ya Ya iq d d af af
C iq iq af Sa Sa ar ar
af af ar M M
ar ar M
M M
SOR
SORTrend
TrendAnalysis
Analysisfrom
from Sites*
Sites*
Contents
Page
43 3
55
116 101 166
485 76
1162
92
15 31
293
1627