CHAPTER 5 Project Management and Resource Allocation
CHAPTER 5 Project Management and Resource Allocation
Introduction:
to accomplish something.
defined START POINT and END POINT to achieve some specific results.
WHAT IS PROJECT MANAGEMENT ?
• It also defined as a dynamic process that utilizes the appropriate resources of the
organization in a controlled and structured manner, to achieve some clearly
defined objectives identified as needs.
Selecting a team
Developing project objectives and a plan for execution
performing risk management activities
Cost estimating and budgeting
Scheduling
Managing resource
Project Management Process
• Planning
Project Definition, Scope, ….
• Mechanics of putting together a plan
Tools: Work Breakdown Structure (WBS)
• Defines the scope of the project in terms that the stakeholders can understand.
• The depth of the WBS is dependent upon the size and complexity of the project
• This rule states that the WBS includes 100% of the work defined by the project
management.
• This example is quite simple and the whole purpose is to bring the attention to
focus on the WBS itself.
• As you can see, the first level describes the product we want to achieve once the
project is complete.
• By meeting with the stakeholders, the team can start decomposing the product
into smaller, more manageable components.
This is what the level 2 is showing below:
• If we take the component called “Wheels” for example, we may want to break
it down into several pieces. However, the team has to decide how much detail
• For this example, we can just break this level into two pieces:
Thus, a product has only two wheels and from a project management standpoint.
• Finally, there could be a component that needs more details for other reasons. In our
example, the team decides to bring even more detail to the component called
“Testing”.
• Based on the project’s needs, there could be a reason to add three more work
packages as you can see in the following figure:
PLANNING AND SCHEDULING IN PROJECT MANAGEMENT
GANTT CHARTS
• Is the most popular tool for planning and scheduling simple projects.
• A visual display of project schedule showing activity start and finish times and where
extra time is available.
• Drawback: priority relationships are not always visible which limits chart’s use for
smaller projects
Building a Gantt Chart
• List all tasks from the project along the vertical axis
• List time frame along the horizontal axis
•Activities: Create box the length of each activity time duration
CPM can be used as a logic tool for decision making. For a deterministic (fixed) time
period
PERT used for activity with time not deterministic, hence probability function can
apply
It provides a means for planning, scheduling, controlling and presenting alternate
courses of action.
Definition and Terms of some CPM
•Activities (Arrows): An item of work, with or without its duration.
•Nodes(events): Start and finish points of an activity.
•Arrow diagram: A Network showing a logical sequence of activities and events which are graphically
shown as arrows and nodes.
• In order to develop a network, the following example illustrates the steps involve d
Analysis
•First, read through the given data and note that this in a nine-activity
network. Activity A is the first activity and Activity I is the last.
ASSIGNMENT: Draw the network and identify the critical path.
•Also calculate the earliest–latest starting and finishing times for each activity:
ASSIGNMENT: Draw the network and identify the critical path.
•Also calculate the earliest–latest starting and finishing times for each activity:
Project Crashing and Time-cost
• Project crashing is a method for shortening the project duration by
reducing the time of one (or more) of the critical project activities to less
than its normal activity time.
• This reduction in the normal activity time is referred to as crashing.