Time Management
Time Management
Competence
Enhancement Training
Time Management
in
Road Construction
1
Projects
By: Kiflom G/hiwot: PE-VII
M
e
G
s
a
o
s
n
fa
a
u
B
ll
g
u
e
d
p
g
rm
e
o
e
jt
n
e
e
c
td
t
c
t
c
o
i
o
m
m
s
p
te
l
e
t
2
i
Time management
Tool
Competent Schedule
Useful Road-Map
realistic and achievable
regular status-ed and updated
Pre-initiation(commitment / planning),
Initiation and Planning (execution scheduling) and
3
Executing and Monitoring & Controlling (performance
control).
Need for Scheduling
To predict the project completion date
To serve as an effective project control tool
To manage money by predicting cash flows
To determine the “time window” of an activity
To coordinate subcontractors
To coordinate client-supplied info
To predict resource demand and improve resource
allocation
To mitigate supply-demand conflicts
To create progress record
To compute progress payments
To serve as an effective communication tool
evaluate the time impact of changes
4
Scheduling Skills
envision the shape and flow of the project’s work in ‘4D’ – the
three physical dimensions + time.
(how the elements fit together),
synthesize information from disparate sources into an integrated
and ‘sensible’ schedule,
analyze and validate this preliminary schedule against the overall
project objectives,
work with the project team to optimize and refine the schedule
(identify and suggest options, test ‘what-if’ scenarios, etc) until
an agreed schedule has been developed,
effectively communicate the outcome of the schedule
development (or update) process by presenting targeted and
relevant information from the schedule in elegant and effective
formats;
reporting the right information to the right stakeholder at the
right time!
assist the various project stakeholders, and in particular the
project manager, understand and manage the project from a time
perspective.
5
PROJECT Characteristics
Limited Information
Projects are surrounded by ambiguity
searching for exactitudes causes paralysis.
Recognize Some things require precision.
take account of the project’s environment:
Consider un-productive activities
6
Planning
Operational design
Knowledge of construction methods
Visualize discrete work elements (tasks) +
Determine task types & quantities +
know tasks interdependence +
establish tasks sequence
Availability of resources
(Materials; local & industrial; Equipment; Human
resource
> task types & quantities
> WBS
Concept > Definite ‘Job’ > ‘Work in progress’
7
Planning
the overall strategy of how the work process is to
be broken down for control;
how the control is to be managed;
what methods are to be used for design,
procurement and construction;
the strategy for subcontracting and procurement;
the interface between the various participants;
the zones of operation and their interface;
maximizing efficiency of the project strategy with
respect to cost and time;
risk and opportunity management.
8
TIME MANAGEMENT
Plan Schedule
deals with Deals with
• Why • when
(project objectives)
• what
(scope of work or basis of
constn)
• how
(project execution strategy
& plan)
• Who
(project organization
structure & Execution
strategy)
9
Plan Schedule
Provides the basis for: reflection of the plan
time and resource Involves:
estimation
•Involves the setting of : • the mechanics of
goals and objectives converting the plan into a
Methods & WBS time table
•Defines : •the timing of activities
the activities to •allocation of resources to
accomplish goals and activities
objectives •Estimates durations
resources needed to •Shows relationships
undertake activities. •Shows critical path
•Deals with: •Deals with implementation
the development of and operation of progress
progress measurement measurement system
system.
10
Plan Schedule
Estimates: •Shows planned work &
Production rates progress
Cost rates •a useful tool for:
Methods & WBS controlling progress
•Defines : communicating
the party who will information
perform the activities
the resources to be
applied to the
activities
•Deals with:
the method of
sequencing
communication and
reporting formats,
timing, etc.
11
Scheduling Technique
No. or (Level) of Schedules
What an appropriate level of detail to use for
the activities?
Too much Too Little
•confusing
•insufficient
•overly large project information for the
schedule on-going
• management of the
•difficult and expensive project
to manage
12
Schedule Levels –
Level 1 Schedule:
Executive Summary,
Project Master Schedule
(PMS)
Level 2 Schedule:
Management Summary,
Summary Master Schedule
(SMS)
Level 3 Schedule:
Project Coordination
Schedule (PCS) :Publication
Schedule
Level 4 Schedule:
Execution Schedule,
Project Working Level
Level 5 Schedule:
Schedule Detail
13 Schedule
Schedule Levels…
PMS
This is a major milestone type of schedule; usually only one
page,
it highlights major project activities, milestones, and key
deliverables for the whole project.
SMS
depicts the overall project broken down into its major
components by area and is used for higher-level management
PCS
Initially developed as an integrated CPM overview of the
project
for reporting status to senior management
spans the whole of the project
primary coordination tool for the overall project
14
Schedule Levels…
PWLS
key working level CPM schedule displaying the activities to be
accomplished by the project workforce and is required for
every project
represents the area of authority of a section manager or
engineer,
So one manager is responsible for all of the work in the
schedule.
Activities are generally over a week in duration (depending on
the nature of the project) and
should be resource loaded at least in the near term and
include detailed crew movements and other means and
methods to ensure viability.
Where used, short term ‘look ahead’ are produced from this
level; typically ‘Three Week Look-ahead’ schedules are
15 updated every two weeks.
Schedule Levels…
DS
A short term schedule
used to map out the detailed tasks needed
to coordinate day to day work in a specific areas
are developed by workforce supervisors
to plan and coordinate their work at the detail
level;
Typically Bar Charts (Gantt Charts),
The schedules are replaced in weeks
superintendents, team leaders, crew leaders &
foremen.
16
Appropriate cycle for: statusing and
updating
• Long enough to implement the last update
• Rate of change in the project
• optimum level of control information
• the timing of review meetings
• management reporting requirement
Time-Scale
frequency of the control processes
level of detail needed in the activities.
Information required
18
key steps in designing a
schedule
Intelligence gathering
agree the major compromises/parameters
needed from the schedule
Creation and adoption of a specification for the
schedule
Select the scheduling method
Enter project specific data into the scheduling
model.
maintain by statusing, updating and
incorporating authorized changes
On completion of the project, archive the project
schedule model for future reference.
19
Schedule Model:
21
Sub-base Placing Pdn @ S1 Pdn @ S2
SB Source
Hauling Approval
Sub-base
mtl
Capping
top-layer Quality
Approval Approval
tests
Blendi
Capping
layer As-built
Survey
Source
ng. Reading
Selection
Product
S1
Approva
l
Product
S2
Approva
l
RFI
Capping
ROW
Layer
clearance
ROW
obstructio
n list
SB source
Identificati
on
22
Establish project calendars and
work periods
primary or default calendar for the project:
a project calendar which is adequate and reasonable
to perform the work, based on normal working times.
Special calendars (few)
may then be used for areas of the project (or resources)
needing different working times.
for each portion of the project (and potentially each
resource)
The number of working days in a week
The number of shifts to be worked each day
The number of hours to be worked each shift or
day
Any periods of scheduled ‘overtime’ work or non-
working time (eg holidays)
23
Activity coding structure
24
Developing the Baseline
schedule
28
Activity duration
29
Activity duration
30
Productivity Factors (PF)
31
The productivity factor for any given work situation needs to
be assessed and applied to the work to base the scheduling
process against the net available productive hours rather than
the ‘paid hours’.
The factor is not fixed, it can vary depending on geographic
region, climate, the accessibility of the work place (working at
height or in confined spaces), the skill of the contractor, etc.
The PF needs to be factual and not used to hide
administrative inefficiencies:
• Waiting for an inspection to be completed is a legitimate PF
inclusion – the work cannot be completed or continued without
the sign-off.
• Waiting for the inspector to turn up is an administrative
inefficiency – a better organized process would ensure the
inspector is available when needed.
• The down-time for a scheduled tea break included in the
contract is a legitimate inclusion, plus reasonable travel time
from the work place to the tea room.
• If lax behavior routinely extends a 15 minute break to 25
32
minutes, the additional 10 minutes is an inefficiency, not a PF
Analyzing the schedule output
A start date is assigned to the start milestone
start and finish dates are calculated for each activity and
milestone
establishes the earliest possible finish date for the
project
Next, a finish date is assigned to the end milestone
backward pass and establishes the late dates
Total Float (TF)= LFT-EST-Dur
Free Float (FF)=ESTsucc-EFT
Resource smoothing and/or levelling
minimize resource over allocations or
reduce the fluctuations in resource demand
May extend project duration if resource becomes
scarce.
33
Schedule
Facilitates project processes
Budgets time
Minimizes risks
Saves Costs
34
Earned Value Management
(EVM)
performance measurement and feedback
tools for managing projects
to identify problems early and make
adjustments that can keep a project on time
and on budget
“Plan, Do, Check, Act.”
patterns and trends in the past can be good
predictors of the future.
integrate the management of project scope,
schedule, and cost
BCWS, BCWP, ACWP Vs elapsed time
35
Earned Value Management
(EVM)
Are we ahead of or behind schedule?
How efficiently are we using our time?
When is the project likely to be completed?
Are we under or over our budget?
What is the remaining work likely to cost?
What is the entire project likely to cost?
How much will we be under or over
budget?
36
THANKYO
U!
I appreciate your patience.
37