5.+NETWORK+DIAGRAM
5.+NETWORK+DIAGRAM
Network Diagram
From the following table of information, (a) Draw a
precedence diagram, (b) Find the Critical Path, (c)
Determine the expected duration of the project.
Activity Precedes Expected time (days)
a c, b 4
c d 12
d i 2
b i 5
e f 3
f j 8
i j 12
j end 9
g h 1
h k 3
k end 15
Solution
:a. precedence
diagram
c=1 d=2
2 b=5
a=4 i =1
e=3 f =8 2
b. Critical g=1
Path
Path j =9
:a,c,d, i, j = 4+12+2+12+9 = h=3
𝑬𝑺=𝑬𝑺+ 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏
𝑬𝑭 =𝑬𝒂𝒓𝒍𝒚 𝑬𝒗𝒆𝒏𝒕+𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏
• Latest Event
Time
– is the latest time the event may occur
without
delaying project completion.
Cont’d Definition of Terms
• Latest
Finish
- An activity cannot be later than the
latest event time of its j-node.
𝑳𝑭 =𝑳𝑺+ 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏
𝑳𝑺=𝑳𝒂𝒕𝒆𝒔𝒕 𝑭𝒊𝒏𝒊𝒔𝒉 − 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏
Cont’d Definition of Terms
• Activity Total Float or Activity Total Slack
– is the span of time an activity can be
delayed
after its earliest start time without
delaying
𝑳𝑭 – 𝑬𝑭
the project =𝑻𝒐𝒕𝒂𝒍 𝑭𝒍𝒐𝒂𝒕
completion
)
𝑳𝑺 – 𝑬𝑺=𝑻𝒐𝒕𝒂𝒍 𝑭𝒍𝒐𝒂𝒕
Cont’d Definition of Terms
• Activity Free
Float
– is the span of time an activity can be
delayed
after its Early Start without delaying the
Earliest Start of any succeeding actual
activity
that may be availed of and still allow its
succeeding real activities to begin at their
Earliest 𝑭𝑭
Start time.
= 𝑬𝑺 – ( 𝑬𝑺+ 𝑫)
Cont’d Definition of Terms
• Independent
Float
– is that portion of the activities Free
Float
that would remain if all its preceding
activities
used up all their float.
𝑳𝑭 =𝑬𝑺 – ( 𝑳𝑭 − 𝑫)
Computing the Early Start and the Early Finish
1 8
Start 1 0 2 4
4
6 13
3 5 6 End
12 2
Figur
Solution:
𝟎 𝟏𝟎 The Early Finish (EF) of
Start activity 1-2 becomes the
ES
for the two activities 2-4
2-5 that follows it.
𝟔
Assume an Early Start ()
for activities without
predecessors. . Similarly, the EF of
The EF time for these activities activity 1-3 becomes
are: the
ES for activity 3-5.
𝑬𝑭 𝟏− 𝟐 ¿ 𝟎+𝟏𝟎
𝑬𝑭 𝟏− 𝟑=𝟎 +𝟔¿𝟔
Cont’d Solution: Summar
𝟎 𝟏𝟎 𝟏𝟖 y: Duratio ES EF
Start Activity n
𝟎 𝟏𝟎
𝟐𝟑𝟐𝟐𝟐𝟓 𝟎 𝟔
End
𝟔 𝟏𝟖 𝟏𝟎 𝟏𝟖
𝑬𝑭 𝟏− 𝟐=𝟏𝟎 ; 𝑬𝑭 𝟏− 𝟑 =𝟔 𝟏𝟎 𝟐𝟑
𝟔 𝟏𝟖
𝑬𝑭 𝟐− 𝟒 ¿𝟏𝟎+𝟖 𝟏𝟖 𝟐𝟐
𝑬𝑭 𝟐− 𝟓¿𝟏𝟎 +𝟏𝟑 𝟐𝟑 𝟐𝟓
𝑬𝑭 𝟑− 𝟓 ¿ 𝟔+𝟏𝟐
𝑬𝑭 𝟒 −𝟓¿ 𝟏𝟖+𝟒 ¿ 𝟐𝟐
𝑬𝑭 𝟓− 𝟔¿ 𝟐𝟑+𝟐¿ 𝟐𝟓
Computing the Last Start and the Last
Finish
The Latest Start (LS) of an activity plus the
duration is equal to the Latest Finish (LF).
4
6 13
3 5 6 End
12 2
Figur
Solution:
Solve for the values of LS
𝟏𝟗 going Backward from node
Start 6 staring from 25 weeks.
𝑳𝑺=𝑳𝒂𝒕𝒆𝒔𝒕 𝑭𝒊𝒏𝒊𝒔𝒉 − 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏
𝟐𝟑 𝟐𝟓
𝑳𝑺𝟓 −𝟔
End
Figur
Solution:
0 10 18
Start
23 22 24
End
6 18 20 25
Path Length in weeks Float/
Slack
𝟏 −𝟐 −𝟒 − 𝟓− 𝟔 𝟏𝟎+ 𝟖+𝟒+ 𝟐=𝟐𝟒 𝟐𝟓 −𝟐𝟒=𝟏
𝟏 −𝟐 −𝟓 −𝟔 𝟏𝟎+ 𝟏𝟑+𝟐=𝟐𝟓C 𝟐𝟓 −𝟐𝟓=𝟎
𝟏 −𝟑 −𝟓 −𝟔 𝟔+𝟏𝟐 +𝟐=𝟐𝟎P 𝟐𝟓 −𝟐𝟎=𝟓
End