Software Project Management Chapter 3 Part 7
Software Project Management Chapter 3 Part 7
resources
3) Fast-tracking by:
i. Shorten the longest critical activities
ii. Partially overlap activities
iii. Employ start-to-start lag relationships
4) Overtime
The project manager should take the decision to crash the project. Why?
Total cost for 18 days project completion time will cost = total cost before crashing +
penalty =
18350 + (18-13) X 1500 = 18350 + 5 x 1500 = 18350 + 7500 = $ 25850
But the total cost after crashing = total cost before crashing + crashing cost – savings from
indirect cost =
18350 + 4150 – 5 X 200 = 22500 – 1000 = $ 21500
Cost savings = total project cost before crashing – total project cost after crashing = 25850
– 21500 = $ 4350
What is the lowest cost to complete this project in 53 weeks? Times are in weeks
and costs in dollars.
Activity Pred Normal Crash Normal Crash
Time Time Cost Cost
A -- 14 9 500 1500
B A 5 2 1000 1600
C A 10 8 2000 2900
D B, C 8 5 1000 2500
E D 6 5 1600 1900
F D 9 6 1500 3000
G E, F 7 4 600 1800
H G 15 11 1600 3600
Solution Copyright © 2010 Pearson Education, Inc.
Publishing as Prentice Hall
Cost Savings = Project cost before crashing – Project cost after crashing = 26600 – 17700 = $
8900
If we crash F by 2 days, crashing cost = 2 x 200 = 400 -> we will have 2 critical paths A B D F G
20 days and
A B D E G 20 days
Therefore, crashing B D E is not beneficial , we will find a common activity to crash such as A
So Crash A by 1 day , crashing cost = 1 x 500 = 500 the critical paths will remain the same A B
D F G 19 days or
A B D E G 19
days
The best scenario not to crash A
Now we need only 1 day to meet the deadline which is 18 days.
Crash D first by 2 days cost 600 but crashing then D
Crash D by 1 day , crashing cost = 1 x 300 = 300, the critical path will be A B D F G 18 days or
costs 800
A B D E G 18 days
Cost Savings = Project cost before crashing – Project cost after crashing = 26600 – 17700 = $
8900