Resource management
Resource management
and
(2) the cost of using alternative resources; for example, overtime to meet a
schedule or subcontracting to accommodate a schedule change.
● Some resources are discrete. When this is the case, decreasing resource
levels, necessarily in integer quantities, could result in a sharp decline in
productivity and efficiency.
● The organization has better control over its own resources. When the choice
of acquiring or subcontracting for a resource exists, the degree of availability
and control should be weighed against cost considerations.
RESOURCE LEVELING SUBJECT TO
PROJECT DUE-DATE CONSTRAINTS
Sum = 196
Sum (resource day) / project duration = 196 labor days/22 weeks = 8.91
WEEK 1,2,3: 17 labor-days per week
In the example, If 17 or more labor-days are available every week, then either an
early-start or a late-start schedule can be used to complete the project within 22
weeks. The leveled resource profile derived above requires at most 12 labor-days
per week. Therefore, as long as this number is available, no delays will be
experienced
Strategy
If these strategies cannot solve the problem, then one or more activities will
have to be delayed beyond their total slack, causing a delay in the completion
of the project.
1. Performing activities at a lower rate using available resource levels
Consider activity B in the example. Assuming that only 11 labor-days are available
each week and activity A (which is critical) is scheduled to be performed using 8 of
those days, only 3 days a week are left for activity B. Because B requires a total of
3 weeks * 4 labor-days per week = 12 labor- days of the resource, it may be
possible to schedule B for 3 days per week for 4 weeks. If this is not satisfactory,
then extending B to 5 weeks at 3 days per week may provide the solution.
2. modifying the network
The analysis of multiple projects in which several types of resources are used in
each is a complicated scheduling problem. In most real-life applications, the
problem is solved with heuristics using priority rules to make the allocations
among activities.