FG#6 MHS SHutdown Report
FG#6 MHS SHutdown Report
•Total Job :
Mechanical:- Planned jobs- 89 nos. Actual Jobs- 46nos. , Completion – 52%
•VERTICAL START-UP OF PLANT
•Shutdown Days :
Planned: 06 days Actual: 09 days
Shutdown Planning VS Achieved Status for FG#6 MHS
1. Not Completed.
18 622 BC 10 1. Damaged roller replacement. 2. Not Completed.
2. Side skirt rubber replacement.
1. Not Completed.
19 622 BC 12 1. Damaged roller replacement. 2. Not Completed.
2. Side skirt rubber replacement.