2. PROJECT CYCLE
2. PROJECT CYCLE
1
The Project Life Cycle
2
Initiating Phase
First phase
Identify need, problem, or opportunity
Determine if select project
Develop project charter
Rationale
Project objective
Expected benefits
General requirements and conditions
Decide if RFP needed
3
Planning Phase
Second Phase
Show how project scope will be accomplished
Plan the work and work the plan
Develop baseline plan
What needs to be done -- scope, deliverable
How it will get done -- activities, sequence
Who will do it -- resources, responsibilities
How long it will take -- durations, schedule
How much it will cost -- budget
What the risks are
Have actual resources plan the work
4
Performing Phase
Third phase
Accomplish project objectives
Project manager leads
Project team completes the project
Increase pace as more resources are
added
Monitor and control progress
Take corrective action as needed
Manage and control changes with
sponsor approval
Achieve customer satisfaction with
acceptance of deliverable
5
Closing Phase
Final phase
Collect and make final payments
Recognize and evaluate staff
Conduct post project evaluation
Document lessons learned
Archive project documents
Record lessons learned
6
Project Planning Process
Establish project objective
Define scope
Create WBS
Assign responsibility
Define specific activities
Sequence activities
Estimate activity resources
Estimate activity durations
Develop project schedule
Estimate activity costs
Determine budget
7
Stakeholder Analysis (4 steps)
Identifying Key Stakeholders (beneficiaries, vulnerable
groups, possible adversely effected groups, socio-
economic characteristics, relationships etc.)
9
PROBLEM ANALYSIS
10
Step 1:Problem analysis (I)
11
Problem analysis
Establishing cause-effect relations between problems
Decreasing in-comes
of artisanal fisherfolk Effects
12
Problem analysis
agree on the unit of analysis
identify major problems existing within a given situation
(brainstorming)
select a starter problem
look for related problems to the starter problem
establish hierarchy of cause and effects
• problems which are directly causing the starter problem are put
below
• problems which are direct effects of the starter problem are put
above
complete with all other problems accordingly
connect the problems with cause-effect arrows
review the diagram and verify its validity and completeness
13
2. Analysis of objectives
Turning the negative aspects into future desired, but realistic situations
Incomes of artisanal
fisherfolk increased Ends
14
3: Analysis of Strategies
The purpose is:
• to identify possible alternative options or ways to
contribute to the overall objectives
• to agree on priority strategies based on an
assessment of the relevance, the feasibility and
the sustainability of each of them
• to concentrate the means of the project on what
is really important, effective and feasible
15
Analysis of Strategies (III)
IN
OUT Incomes
Incomesofofartisanal
fisherfolk
artisanal
increased
fisherfolk increased
OVERALL
OBJECTIVE
17
Logframe Approach
ANALYSIS PHASE PLANNING PHASE
Stakeholder Analysis - identifying & Logframe - defining the project/
stakeholders
project logic
groups & beneficiaries, defining whose internal logic, formulating
Define the
Identify
operationalising
Specifying and
Analysis of objectives - developing responsibility
objectives from the identified problems;
identifying means to end relationships
Resource scheduling - from
Select the
Incomes of artisanal
fisherfolk increased
1.Quality of fish
processing improved
2.Access to markets
improved
Activities Means Costs
1.1. To train fish handlers
1.2. To install appropriate
Equipment etc.
Pre-conditions
21
Logframe Basics
Objectively
Intervention Logic Verifiable Sources of Assumptions
Indicators Verification
Incomes of artisanal
fisherfolk increased
‘... IF results are delivered, AND assumptions hold true, Prmission local
Gov. Obtained
THEN the project purpose will be achieved ...’ Project facilities
provided
22
Assumptions HOW?
23
Assessment of Assumptions
Is the external factor important?
Yes No
24
Project assumptions:
•Project assumptions may be outside of the
project control (policy, collaboration external
actors etc.)
25
WHY?
Indicators
To:
• Clarify the characteristics of the OO, SO and R
• Manage the project more objectively
• Provide a basis for performance measurement,
monitoring and evaluation
OVI’s describe the project’s objectives in operationally
measurable terms (quantitiy, quality, time)
Note:
Often, it is necessary to establish several indicators for one
objective. Together, these will provide reliable information on the
achievement of objectives.
26
Indicators: An Example
Objective: Efficiency and effectiveness of the learning and and
administration processes/practices have been enhanced
27
Some criteria for good indicators
Valid Does the indicator directly represent the objective it is
intended to measure?
28
Activity Scheduling
An activity schedule:
Maintains objective-oriented approach of logframe
Breaks activities down into operational detail
Clarifies sequence, duration and precedence of activities
Identifies key milestones
Assigns management responsibility
and implementing responsibilities
and should include management
tasks
Workplan
Workplan
Workplan
USE project charts
29
Project charts
Gantt chart = common technique for representing the
phases and activities of a project
In this example :
- What are the different tasks;
- What is the start and end date of the tasks.
30
Project charts
Gantt chart can also include:
- Who is responsible?
- What is the relation between ≠tasks?
- Are the deadlines met?
31
Project charts
PERT = Project Evaluation and Review Technique
32
Project charts
Gantt versus PERT
33
LFA link to evaluation (Logical Framework Approach)
34
Create WBS and Assign
Responsibility
35
Sequence Activities
36
Develop the Project Schedule
37
Determine Budget
38
Execute the Project Plan
Perform the work
Monitor and control progress
Control changes
39
Global Project Management
Globalization Helpful Competencies
Adds a dimension of complexity Foreign language skills
Changes project dynamics Knowledge of
Cultures
Requires awareness of factors Geography
Cultural differences World history and contemporary
events
Currency International economics
Codes and regulations Awareness of
Business organization Customs and etiquette
Political relations Geopolitical environment
Workforce availability Technology adoption and translation
software
40
Project Management Associations
Project Management Institute Global Associations
Worldwide not-for-profit association of Links available at
practitioners www.cengagebrain.com
350,000 members in >170 countries
250 chapters in >70 countries
Online communities for collaboration
PMBOK® Guide
PMI Code of Ethics and Professional
Conduct
Certifications
www.pmi.org
41
Critical Success Factors
Planning and communication are critical to successful project management. They prevent problems from
occurring or minimize their impact on the achievement of the project objective when they do occur.
Taking the time to develop a well thought-out plan before the start of the project is critical to the successful
accomplishment of any project.
A project must have a clear objective of what is to be accomplished and defined in terms of end product or
deliverable, schedule, and budget; and is agreed upon by the customer.
Involve the sponsor or customer as a partner in the successful outcome of the project through active
participation during the project.
Achieving customer satisfaction requires ongoing communication with the customer to keep the customer
informed and to determine whether expectations have changed.
The key to effective project control is measuring actual progress and comparing it to planned progress on a
timely and regular basis and taking any needed corrective action immediately.
After the conclusion of a project, the project performance should be evaluated to learn what could be improved if
a similar project were to be undertaken in the future. Feedback should be obtained from the sponsor or customer
and the project team.
Learning and understanding the culture and customs of other project participants will demonstrate respect,
help build trust, and aid in developing an effective project team; and it is critical for successful global project
management.
42
Summary
A project is an endeavor to accomplish a specific objective through a unique set of interrelated tasks and the
effective utilization of resources.
The successful accomplishment of the project objective could be constrained by many factors, including scope,
quality, schedule, budget, resources, risks, and customer satisfaction.
The project life cycle has four phases: initiating, planning, performing, and closing the project.
Project management is planning, organizing, coordinating, leading, and controlling resources to accomplish the
project objective. The project management process involves two major functions: first establishing a plan and
then executing that plan to accomplish the project objective.
Globalization changes the dynamics of a project and adds a layer of complexity that can adversely affect the
project outcome if the project participants are not aware of what they can encounter regarding cultural
differences and multinational economic transactions.
The Project Management Institute is a premier worldwide not-for-profit association for practitioners in the
project management profession.
The ultimate benefit of implementing project management techniques is having a satisfied customer—whether
you are the customer of your own project or a business (contractor) being paid by a customer to perform a
project.
43
What is a project?
• A project features the following characteristics;
Specific start and end date
Series of tasks to achieve a defined outcome or
objective
Uses people or resources to achieve that objective
44
What is project management?
45
What is the project life-cycle?
• Logical sequence of activities to accomplish the
project’s goals or objectives
46
What do you do at each stage?
• Initiate
Define scope
Develop outline business case *
• Plan
Identify milestones and outputs
Identify required funding and resources
Identify and analyse risks *
Identify and analyse stakeholders
Undertake E&D impact assessment *
Develop project initiation document
47
What do you do at each stage?
• Deliver
Communicate with stakeholders
Identify project governance requirements
Identify and undertake commissioning exercises *
Monitor and report on project progress
Manage risks
Record lessons learned
• Review
Hold post project review meeting
• Close
Close project
48
PMBOK Definitions
PROJECT = “…a temporary endeavour or undertaking to create a
unique product or service”
49
The Project Management
Institute
“Project Management Institute is the global professional association for
project programme or portfolio managers and PMO officers. PMI UK is the
United Kingdom branch.
The core purpose of PMI is to advance the practice, science and profession
of project management throughout the world. PMI's goal is that worldwide,
organisations will embrace, value and utilise project management and
attribute their success to it.”
www.pmi.org.uk
50
Association for Project
Management (APM)
“The Association for Project Management has over 35 years combining
its members’ extensive experience in developing the science and art of
project management. This is encapsulated in the APM Body of
Knowledge, qualifications and other research activities and disseminated
through its members, and more widely via
print, electronic media and events.”
www.apm.org.uk
51
PMBOK Definitions
PROJECT = “…a temporary endeavour or undertaking to create a
unique product or service”
52
What is a Project?
53
What is Project Management?
“ . . . a way of developing structure in a complex
project, where the independent variables of time,
cost, resources and human behaviour come
together.”
Burke (1999)
54
Characteristics of a Project
Define
State the Identify Determine
management Obtain
problem activities personnel
style client
needs
acceptance
Identify Estimate
Establish
project goals time & cost Recruit
control tools Install
Project
deliverables
List the Sequence Manager
Prepare
objectives activities
status report Document
Recruit
the project
Determine Identify Project Team
Review
preliminary critical
project Issue final
resources activities Organise
schedule report
team
Identify Write
Issue Conduct
assumptions project Assign work
change project audit
and risks proposal packages
orders
PLANNING IMPLEMENTATION 56
Example of Framework
57
The Project Life Cycle (PLC) the time
distribution of project activity
Level of activity
Develop it
Design it
Define it
58
The Project Life Cycle (PLC) the time
cumulative expenditure
Cumulative Expenditure
Develop it
Design it
Define it
59
The PMI Body of Knowledge
• The Project Management Framework
• The Project Management Context
• Project Management Processes
• Project Integration Management
• Project Scope Management
• Project Time Management
• Project Cost Management
• Project Quality Management
• Project Human Resource Management
• Project Communications Management
• Project Risk Management
• Project Procurement Management
60
Maintaining the balance …
TIME
COST QUALITY
61
Tolerances
PRINCE uses tolerances
Is there any latitude in the quoted delivery date or budget?
Define
The tolerances in a project
Who may use the tolerances.
62
Activities / tasks
63
Milestones
Milestones are key points for the project.
They have no duration – they are just target dates.
e.g
Obtain planning approval
Roof on
Wiring complete
Piping complete COMPLETE 14/10/2008
64
Resources
What is required for an activity
65
Deliverables
e.g.
Preliminary drawings
Working drawings
Bill of quantities
Shell of house
66
Gantt Charts
Shows activities/ tasks and milestones
Can show resources
Clear indication of timescales
Task Task DO Res. PE AE M T W T F M T W T F
Number Name
1 Design Prog. SH 2 2
2 Code Prog. 1 DC 4 5
3 Document Prog. 2 NJ 2 1
Planned Elapsed
Actual Elapsed
67
Issue or Risk?
Issues Resolution
Risks Management
68
Stages in project management
Stage 1
Understanding
the project
environment
Stage 2
Project Changes
definition
Stage 3
Project Corrective action
planning
Stage 4 Stage 5
Technical Project
execution control
69
Stage 1: Understanding project environment
The project environment comprises the factors
which may affect the project during its life. See
slide 16.6
70
Geo-social environment Econo-political environment
• Geography • Economy
• National culture • Government
The Project
72
Project objectives
The hierarchy of objectives:
At the top of the hierarchy is the overall objective or goal
of the project, lower levels of the hierarchy are the
objectives of each part of the project (big projects
consists of many parts).
Objectives of each part must be related to its overall
objective.
73
Objectives must be clear:
Good objectives are those which are clear, measurable and,
preferably, quantifiable.
One method of clarifying objectives is to break down project
objectives into three categories:
Purpose: to prevent production from failing to meet output as
forecast.
End result: a report which identifies the causes of lost
production, and which recommends how the target output can be
met.
Success criteria: the report should be completed by 30 June.
The recommendations should enable output to reach at east 70
tonnes per year. Cost of the recommendations should not
exceed RM200,000.
74
The three project performance objectives
Qualit
y
New aircraft
project
75
Project scope
- Identifies the work content and the outcomes.
- Boundary setting exercise – divides work content for each
part of the project.
- Important for managing contractors – commercial and legal
aspect of the scope of supply.
- Can change during the course of the project.
76
Project strategy
- Defines in general how the organization is going to
achieve its project objectives and meet the related
measure of performance.
- Two ways:
1) Define phases (time based sections) of the project.
2) Set milestones at which specific reviews of time, cost
and quality are made.
77
Stage 3: Project planning
Fulfills four distinct purpose, it determines:
1. The cost and duration of the project.
2. The level of resources needed.
3. Helps to allocate work and monitor progress.
4. Helps to assess the impact of changes to the project.
78
Stages in the project planning process
Adjust as necessary
1 2 3 4 5
79
1. Identify activities: Work breakdown
structure
1. Serve
breakfast in bed
80
2. Estimate times and resources
Table 16.1
Time and resources estimates for a breakfast-in-bed” project
No Activity Effort (person) Duration (secs)
1 Serve breakfast in bed 1 120
2 Pour juice in glass 1 5
3 Fetch juice 1 10
4 Fetch glass 1 10
5 Place boiled egg in egg cup 1 3
6 Boil egg 0 240
7 Fetch egg 1 10
8 Bring water to boil 0 180
9 Fill pan with water 1 8
10 Fetch egg cup 1 10
11 Butter the toast 1 10
12 Toast bread 0 30
13 Slice bread 1 30
14 Fetch bread 1 10
15 Fetch butter 1 10
81
Typical subjective probability distribution
for an activity time estimate
Accuracy of
estimates comes
with experience!
Probability
3 5 6 Activity duration 13
Optimistic time Expected time
Most likely time Pessimistic time
82
3. Identify relationship and dependencies
83
4. Identify schedule constraints
84
“Making breakfast” - Do activities at
earliest time
Time (mins)
0 1 2 3 4 5 6 7 8 9
Orange
Activities requiring
operator time
Bread Toast Butter
Bed
Water Boil water Boil egg
room
Tray
4
Staff required
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (mins)
85
“Making breakfast” – Minimizing staff
requirements
Time (mins)
0 1 2 3 4 5 6 7 8 9
Orange
Bed
Water Boil water Boil egg
room
Tray
4
Staff required
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (mins)
86
5. Fix the schedule
“Making breakfast” – Maximizing toast
quality
Time (mins)
0 1 2 3 4 5 6 7 8 9
Orange
4 Tray
Staff required
3
2
1
0
0 1 2 3 4 5 6 7 8 9
Time (mins)
87
Stage 5: Project control
1. Project monitoring: current expenditure to date, amount of
overtime authorized, inspection failure, progress of activities etc.
88
Network planning
1. Use of Gantt chart is the simplest technique that supports
project planning and control.
89
Critical Path Method
1. Represents the project activities diagrammatically.
2. Project activities are represented by arrows (See 16.26).
3. At the tail (start) and head (finish) of each activity is a circle which
represents and event (See 16.27).
Rules for drawing a network diagram:
1. An event cannot be reached until all activities leading to it are
complete - (16.27 – event 5 is not reached until c and e are
completed).
2. No activity can start until its tail event is reached - (16.27 –activity
f cannot start until event 5 is reached).
3. No two activities can have the same heat and tail events (16.28 –
activities x and y cannot be drawn as first shown, they must be
drawn using a dummy activity (no duration and shown as a dotted
line)
90
Activities and network for a simple
project
Immediate Activity duration
Activity (in days)
predecessors
a Remove furniture None 1
b Prepare bedroom a 2
c Paint bedroom b 3
d Prepare kitchen a 1
e Paint kitchen d 2
f Replace furniture c, e 1
om Pa
r o int
d be
e be dr
par oo
m
r e
P
Remove furniture Replace furniture
Pr
ep en
are c h
kit kit
ch
en a int
P
91
Network diagram for simple decorating project
EET – the very earliest the event could possibly
Activity reference a occur if all preceding activities are completed as
early as possible.
Activity duration 1
LET – the latest time that the event could possibly
1 take place without delaying the whole project
Event number
3
An Event
b c
2 3
1 a 2 5 f 6
1 1
d e
Earliest Event Latest Event
1 2
Time (EET) Time (LET) 4
92
Activity on arrow – Using “dummy”
activities
2
x
x
1 2 1 3
y
1 3 5
2 4 6
93
Critical Path
Network diagrams have more that one sequence of activities
which will lead from the start to the end of the project – these
sequence are called paths.
Each path has a total duration which is the sum of all its activities.
The path which has the longest sequence of activities is called the
critical path.
It is called the critical path because any delay in and of the
activities on this path will delay the whole project.
94
Network analysis for simple decorating project
With earliest and latest event times
3
3 3
b c
2 3
1 a 2 5 f 6
0 0 1 1 1 6 6 1 7 7
d e
1 2
4
2 4
Chapter 16, Page 575
95
Worked Example
96
Road Construction Activities
Activity Duration Preceding activities
A 5 -
B 10 -
C 1 -
D 8 B
E 10 B
F 9 B
G 3 A, D
H 7 A, D
I 4 F
J 3 F
K 5 C, J
L 8 H, E, I, K
M 4 C, J
97
Network Diagram For Motorway Project
18 20 G
A
H 3
5 D
8 7
B E L
0 0 10 10 27 27 35 35
10 10 8
F I
9
C 4
K M
1 19 19 5
4
3J
22 22
98