CRASHING
CRASHING
CRASHING
Revision
• Total Normal Cost = Direct Cost + Indirect Cost
• Direct Cost= Sum of normal Costs of all activities
• Indirect Cost = No. of days X Cost per day.
• Crash Slope = Crash Cost-Normal Cost = Cc-Nc
Normal Time - Crash Time Nt-Ct
Path In Network
Critical Path :1-2—5 1-2-5 = 18 Days
Normal Project Completion Time = 18 days 1-2-4-5 = 13 days
1-3-4-5 = 12 days
Total Normal Cost = Direct Cost + Indirect Cost
= 580 + (70 x 18) Direct Cost = Sum of normal Costs of all activities
= 1840 = 100 + 150 + 50 + 100 + 100 + 80 = 580
Indirect Cost = No. of days X Cost per day.
= 18 x 70 = 1260
Maximum
Activity Normal Time Crash Time Normal Cost Crash Cost Cost
Activity Crashable Rank
Slope/ day
limit (days)
2 -4 2 1 50 90
2 -4 1 40 3
2 -5 10 5 100 400
2 -5 5 60 5
3 -4 5 1 100 200
3 -4 4 25 2
4- 5 3 1 80 100 4- 5 2 10 1
Paths Cost
Maximum Activity
Cost 1 -2 -5 1-2-4-5 1-3-4-5 Direct Indirect Total
Activity Crashable Rank
Slope/ day
limit (days) Before Crashing 18 13 12 580 1260 1840
1st crashing
18 -1 = 17 13-1 =12 12 580 + (50x1) = 630 17 x 70 = 1190 1820
1-2 by 1 day
1 -2 2 50 4 2nd crashing
17 -1 = 16 12-1=11 12 630 + (50x1) = 680 16 x 70 = 1120 1800
1-2 by 1 day
1 -3 2 100 6 3rd crashing
16 -1 = 15 11 12 680 + (60x1) = 740 15 x 70 = 1050 1790
2-5 by 1 day
2 -4 1 40 3 3rd crashing
16 -1 = 15 11 12 680 + (60x1) = 740 15 x 70 = 1050 1790
2-5 by 1 day
5th crashing
2 -5 5 60 5 14-1 = 13 11 12 800 + (60x1) = 860 13 x 70 = 910 1770
2-5 by 1 day
6th crashing
3 -4 4 25 2 13 -1 = 12 11 12 860 + (60x1) = 920 12 x 70 = 840 1760
2-5 by 1 day
7th crashing
920 + (60x1) +
4- 5 2 10 1 2-5 by 1 day 12 -1 = 11 11- 1 =10 12- 1 = 11 11 x 70 = 770 1760
(10 x 1) = 970
and 4-5 by 1
Path In Network
Critical Path A – D – G A- F = 11
Normal Project Completion Time = 13 days A –D –G = 13
B–G = 10
C –E – G =8
Normal Project Cost = Direct Cost + Indirect Cost
= 713 + 400
= 1113
Maximum
Normal Crash Normal Crash Cost Slope/
Activity Activity Crashable Rank
Time Time Cost Cost day
limit (days)
A 4 3 60 90 A 1 30 2
B 6 4 150 250 B 2 50 3
C 2 1 38 60 C 1 22 1
D 5 3 150 250 D 2 50 3
E 2 2 100 100 E 0 0 0
F 7 5 115 175 F 2 30 2
G 4 2 100 240 G 2 70 4
Paths Cost
Activity
A-F A-D-G B-G C-E-G Direct Indirect Total
Before Crashing 11 13 10 8 713 400 1113
1st crashing
11-1 =10 13-1 =12 10 8 713 + (30x1) =773 250 993
A by 1 day
2nd crashing
10 12-1 =11 10 8 743 + (50x1) =793 175 968
D by 1 day
3rd crashing
10 11-1 =10 10 8 793 + (50x1) = 843 100 943
D by 1 day
4th crashing
10-1 = 9 10-1 = 9 10-1 = 9 8 -1 =7 843 + (70x1)+(30x1)=943 75 1018
G by 1 day
5th crashing
G by 1 day and 9 -1 = 8 9 -1 = 8 9 -1 = 8 7-1 = 6 943 + (70x1)+(30x1)=1043 50 1093
F by 1 day