10 Monitoring and Control v0.93 (short with scenario)
10 Monitoring and Control v0.93 (short with scenario)
Lecture 10
Monitoring and control
Clive Vassell
Aims and Objectives
▪ To discuss:
— Project and programme monitoring and control tools and terminology
— Sources of project or programme change and effective change
management
▪ To be able to:
— Understand the importance of effective project and programme
monitoring and control
— Use project reporting and control tools and techniques
— Understand the importance of properly closing projects and
programmes
— Be able to recognise sources of change and describe an effective
change management process
Page 2
Project and Programme Monitoring
and Control
Page 4
Sources of information
▪ Formal
— Reports from team/work package owners,
project manager
— Reports from stakeholder groups, outputs from
meetings
— Quality control documentation
▪ Informal
— Discussions with sponsor, other senior
managers or stakeholders
— “Management by walking about” (MBWA)
Page 5
Issues with project and programme
information
▪ Who is telling me this?
▪ Why?
▪ Why now?
▪ Hidden agenda?
▪ How accurate?
▪ Project and programme managers need:
— a healthy degree of scepticism
— their own reliable sources of information
Page 6
Formal project and programme reporting
Portfolio
Management/
Executive Board
Programme
Sponsor or Board
Project
Board
Programme
Manager
Project
Manager
Team
members
Task
owners
Page 7
Report Content
Page 8
Frequency / depth
Page 9
Gate (or Gateway) reviews
Page 11
JLR Scenario
Page 12
Any Questions?
Page 13
Monitoring the schedule
Page 14
What to watch for (2)
▪ Monitoring progress
— the “nearly done” syndrome
▪ % done?
▪ estimated time to complete?
▪ Why are things happening?
— why milestone missed, activities not being
done?
Page 15
Showing progress on a Gantt chart
Page 16
Showing Progress on a Gantt Chart
October November December January February Marc
ID Task Name Duration 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4
1 Start 0 days 10/16
2 Concept and System Design 30 days
3 Capture User Requirements 3 days
4 Develop System Concept 10 days
5 Review w ith Customer 2 days
6 Concept Agreed 0 days 11/3
7 System Design 15 days
8 Develop Sub-system #1 27 days
9 Design 10 days
10 Review 0 days 12/8
11 Manuf acture 15 days
12 Test 2 days
13 Develop Sub-system #2 13 days
14 Design 5 days
15 Review 0 days 12/1
16 Manuf acture 7 days
17 Test 1 day
18 Integration and Test 50 days
19 Develop Integration Plan 7 days
20 Develop Test Equipment 5 days
21 Integration 3 days
22 System Test 5 days
23 Acceptance 1 day
24 Delivery 0 days 1/15
25 Com m issioning 5 days
26 Hand over 0 days 1/22
Page 17
Milestones
Page 18
Milestone slip chart
Page 19
Milestone slip chart
now
A
B
Page 20
Any Questions?
Page 21
JLR Scenario
Page 22
Any Questions?
Page 23
Project Control
Page 24
What tools do you have to control the
project?
Page 25
Range of project/programme control
▪ Do nothing light
Page 26
Types of control
▪ Do nothing
— a considered response, not a failure to act
▪ Encouragement and advice
▪ Emphasis and clarification
▪ Increase or decrease supervision
▪ Reassigning tasks
▪ Adjustments to the scheduling of tasks
▪ Approval or otherwise of task commencement
▪ Modifications to the project plan
▪ Add, move or remove personnel
▪ Add or remove other resources
▪ Buy in more resource
▪ Stop the project or programme
Page 27
Project change management
Page 28
Sources of change
▪ Business requirements
— competitive pressure, new personnel, senior management
▪ Stakeholder requirements
— revised idea of what the customer or the user wants
▪ External environmental changes
— Political, economic etc. – remember PESTLE
▪ Issues arising during the project or programme
— resources no longer available, technical failures
▪ Potential opportunities identified
— availability of new technology, other markets identified
▪ Errors or omissions in original plans
— not always clear what users/customer wants
Page 29
Benefits of change management
Evaluate
Recommend
and decide
No
Change
Close
accepted?
Yes
Implement
Page 31
Receive request
▪ Formal: in writing
▪ Internal (to the project) or external (by the customer)
▪ Must state:
— source and what is requested
— justification – impact on benefits
— costs – impact on budget, other resources
— impact on objectives and scope
— impact on risks
▪ Will typically have agreed formats
— part of governance/customer contract
▪ Don’t engage the formal process too early
Page 32
Register the Change
Page 33
Evaluation and Decision
▪ Review with all affected:
— Customer
— Sponsor
— Appropriate stakeholders
Page 34
Approval levels
Page 36
Decision Criteria
Page 37
Outcomes
▪ Reject
— Closed
▪ Provisional approval
— Need more information
— Still open
▪ Approved
— Complete or partial implementation
▪ Impose limitations
— Open until tested
Page 38
Implement
▪ Changes adopted into project documentation
▪ Test if appropriate
▪ Update all relevant documentation
— when all have been done, the change is
closed
▪ Budget may be increased (customer-initiated
change) or funds drawn from management
reserve
▪ Inform – communication is vital
▪ "close" noted on the change register
Page 39
Very easy to be swamped by changes
Page 40
Any Questions?
Page 41
JLR Scenario
Page 42
Any Questions?
Page 43
Break?
Page 44
Coursework Questions
Page 45
Configuration management
Page 47
What are we producing for the customer?
Page 48
What specification are we using?
Page 50
Configuration management
Page 51
Configuration management
Page 52
"Configuration Items" might include
▪ Physical items
— parts, tools, ingredients
▪ Requirements
— users, regulators, legal, safety
▪ Specifications
— designs, technical specifications
▪ Plans, drawings, code
▪ Project documents
— project plans, schedules, budgets, test plans
▪ Most important = the "as built" (to be delivered) product to the
customer
▪ Should include relationships with other items
Page 53
Links between configuration
management and change control
▪ Configuration management sets out which outputs /
deliverables are subject to change control:
— items which are critically important to get right
▪ Other parts of the project depend on them
▪ Customer requirements, technical designs and
specifications
Page 56
Have your say!
Page 57
This week’s seminar
Page 58
Main Reading
APM v7 Handbook:
Sections 4.3
Supplemental Reading
Agile Project Framework:
Chapters 16
Thank you