Lec - 4 Scheduling
Lec - 4 Scheduling
Project Scheduling
1. Project Scheduling
1
1. Project Scheduling
• Following steps are required to develop project schedule:
1. Break down scope of work into manageable portions,
• Project’s work breakdown structure (WBS) defines work
activities.
packages that can be sequenced (scheduled) to coordinate
2.project
Estimating each activity’s duration.
construction.
•3.Resulting
Establishing sequence
project schedulerelationships
is importantamong activities.
for many management
4.functions.
Finding earliest and latest possible times for execution of
each activity.
• Schedule provides concise means to communicate intended
5.construction
Looking upstrategy and
project’s can reveal
critical any inconsistencies.
sequence of activities and
flexibility that activities not included in this sequence can
have.
6. Reviewing, optimizing, communicating, updating, and
using schedule.
Construction Project 1
Management
2. Estimating Activity Durations
• After list of activities is developed, duration of each one must be
estimated.
• Duration of any activity is largely determined by:.
1. Nature of work that activity entails.
2. Quantities of work.
3. Technique used for task.
4. Resources used to perform work.
5. Working hours for resources.
3
3. Bar Charts
• Bar chart is representation of project work item or activity as time
scaled bar whose length represents planned duration of activity.
• Bar is located on timeline to indicate schedule for planned start,
execution, and completion of the project work activity.
4
3. Bar Charts
4. Activity Precedence Diagrams
• Precedence diagram is graphical tool that shows project’s activities as
rectangles or circles joined by arrows indicating their mutual
dependency or relationship.
6
• Resulting network clearly indicates intended sequence of
activities and is fundamental graphical component of Critical
Path Method (CPM).
2. Start-to-Start Relationship :
• It is possible that the start of an activity is a condition for the start of a
follower, in what is called a start-to-start (SS) relationship.
8
3. Finish-to-Finish Relationship :
• Finish of activity can constrain finish of
another in finish-to-finish (FF) relationship.
4. Start-to-Finish Relationship :
• Start of an activity constrains the finish of another
in a start-to-finish (SF) relationship.
5. Generalized Relationships
Activities with Multiple Mutual Relationships
• Two activities can have more than one mutual relationship as long as
relationships specify different types of conditions, and predecessor–
successor relation is not swapped.
9
10
6. Critical Path Method Scheduling Procedure
• When two activities are linked by traditional relationship, predecessor
must finish before successor can begin.
• Earliest possible dates to execute each activity in network can be
found when this rationale is applied to all activities in diagram.
• This process is known as CPM forward pass and also
determines minimum possible duration of project.
• Similar procedure is then performed backward, from last to first
activities in diagram.
• This second step is called CPM backward pass and computes
latest dates by which each activity can be performed without
increasing project’s minimum duration.
1
1
6. Critical Path Method Scheduling Procedure
• Difference between earliest and latest possible dates to execute each
activity is its total float.
• It is time that an activity can ‘‘drift’’ or be ‘‘floated’’ between its two
extreme dates.
• Chain of critical activities will not have any available float.
• The timely completion of this chain of activities is critical for the
scheduled completion of the entire project.
• This activity chain is appropriately called critical path of project and
is central to schedule that entire scheduling technique is called critical
path method.
Construction Project 1
Management 2
6. Critical Path Method Scheduling Procedure
1
4
6. Critical Path Method Scheduling Procedure
15
6. Critical Path Method Scheduling Procedure
Backward Pass
• Second phase of CPM
computations is backward
pass, whose progression
through network is opposite to
that of forward pass, as name
suggests.
• Backward pass computes
latest date by which each
activity must finish to avoid
extending project
duration.
1
6
6. Critical Path Method Scheduling Procedure
17