3 - Lecture Slides
3 - Lecture Slides
METHOD
(103,00 (103,000.
0 0) 00)
40,905.0
1 45,000 45,000 0.9090 0 12 1
33,056.0
2 40,000 85,000 0.8264 0 12 2
121,00 27,046.8
3 36,000 0 0.7513 0 12 3
141,00 13,660.0 1,666.
4 20,000 0 0.6830 0 67 1.20
151,00
5 10,000 0 0.6209 6,209.00
SOLUTION: DISCOUNTED PAYBACK PERIOD
Option B
Pay
Year Cash Cum DF PV of Bac Mont Ye
s Flow . CF 10% CF k h ar
(103,00
0 0) 1
13,635.0
1 15,000 15,000 0.91 0 12 1
20,660.0
2 25,000 40,000 0.83 0 12 2
26,295.5
3 35,000 75,000 0.75 0 12 3
129,00 36,882.0
4 54,000 0 0.68 0 12 4
189,00 37,254.0 5,000.
5 60,000 0 0.62 0 00 1.11
• ACCOUNTING RATE OF RETURN – ARR
• ALSO AVERAGE ACCOUNTING RATE –
AAR
• NPV = Rs 137,997
• Total PV of Cash Flow = 2.437 million
• Initial Investment = 2.00 million
• Acceptance Rule:
• Benefit Cost Ratio > 1
• Project is undertaken
Evaluation Method
• NPV
• IRR
• Pay Back Period Method
• Discounted Pay Back Period
• Accounting Rate of Return (ARR)
• Profitability Index
Net Present Value (NPV)
• NPV states, if NPV is positive then project
is under taken.
• In case of more than one project, the
project with higher NPV can be
undertaken.
• If the project has negative NPV, it does
not add value to the company so rejected.
Internal Rate of Return
• Decision Rule
• If IRR is grater than targeted return the
project is viable, we can undertake the
project.
• If project yield less than targeted rate of
return then it is not accepted.
Pay Back Period Method
• Acceptance Rule
• If it return you the initial investment
to cash flows then it is acceptable
and if it is not reject the project.
Discounted Pay Back Period
• Acceptance Rule
• Same as Pay Back
• Just consider time value
Accounting Rate of Return
(ARR)
• Acceptance Rule
• If project yield more than target
return than project acceptable
otherwise vice versa.
Profitability Index