Topic 05 Software Cost
Topic 05 Software Cost
MANAGEMENT
Software Costing
https://www.youtube.com/watch?v=rN0FrDpQNUk
Software Projects are
‘Special’
The software product is intangible and complex.
Software cannot be seen or touched. Software project managers cannot see
progress by simply looking at the artefact that is being constructed.
Software products are more complex than other engineered artifacts.
Top-down approach
Bottom-up approach
Expert Judgment
Ian Parkinson
Price-to Win
User Story
Playing Poker
Analogy
Machine Learning
Use Case Point
Constructive Cost Model (COCOMO)
25
Earned Value Management
Terms
The planned value (PV), formerly called the budgeted cost of work
scheduled (BCWS), also called the budget, is that portion of the
approved total cost estimate planned to be spent on an activity during a
given period.
Actual cost (AC), formerly called actual cost of work performed
(ACWP), is the total of direct and indirect costs incurred in accomplishing
work on an activity during a given period.
The earned value (EV), formerly called the budgeted cost of work
performed (BCWP), is an estimate of the value of the physical work
actually completed.
EV is based on the original planned costs for the project or activity and
the rate at which the team is completing
26 work on the project or activity
to date.
Rate of Performance
Rate of performance (RP) is the ratio of actual work completed
to the percentage of work planned to have been completed at any
given time during the life of the project or activity.
Brenda Taylor, Senior Project Manager in South Africa, suggests
using this approach for estimating earned value.
For example, suppose the server installation was halfway
completed by the end of week 1. The rate of performance would
be 50 percent (50/100) because by the end of week 1, the
planned schedule reflects that the task should be 100 percent
complete and only 50 percent of that work has been completed.
27
Thanks /
Q&A
Tutorial Session 1