LECTURE_8_ Project Time Cost Function
LECTURE_8_ Project Time Cost Function
Project Time
Cost Function
Manjusha Nabar
PROJECT TIME-COST FUNCTION
The time and cost factors of a project are inter-related. The project cost function shows the
relationship of the cost versus the completion time. Its ordinate represents the cost and the abscissa
a time scale. In the formulation of the project cost function, the direct and indirect costs along with
the financial gains resulting from early completion are considered.
The project time corresponding to the minimum value of the cost function gives the most
economical duration of the project. The project cost function also gives the cost of reducing the
project duration from its economical (normal) completion time. Crash point at the interaction of
crash time and crash cost; corresponds to the maximum possible time crashing. In addition, project
cost function provides a ready reckoner for assessing the change in cost with varying project
duration and resulting critical activities.
CONCEPT
The basic concept behind the formulation of a project time-cost function is that the normal time
duration of an activity is based on considerations of normal cost, using an efficient or desired
method of performance of the activity. Each activity is considered in isolation, while working out
its normal, time and cost. The reduction in duration below the normal time by a changed method
of execution implies an increase in the cost. There will also be a stage beyond which the activity
duration cannot be further reduced. The lower limit up to which an activity time can be reduced,
is called the crash time and the corresponding cost is referred to as the crash cost.
The difference between the normal time and the crash time of an activity indicates its potential to
undergo crashing. The slope of the activity cost function shows the rate of increase of cost, with
the reduction in time for the activity as shown
Incorporating the cost implication in a table after each crashing. The network, after its fourth
crashing, shows the duration of the crashed activities and depicts the network plan of the least
cost of the project. The cumulative effects of direct and indirect costs and the savings for early
completion must be aggregated
Least cost schedule.