0% found this document useful (0 votes)
2 views

Slide 6 - Project Schedules

The document discusses the principles of applied software project management, focusing on project definition, planning, scheduling, and metrics. It emphasizes the importance of managing performance, time, cost, and scope (PCTS) effectively, along with the use of tools like Work Breakdown Structure (WBS) and Gantt charts. Additionally, it highlights the significance of evaluating project outcomes and learning from challenges to improve future projects.

Uploaded by

Miguel3796
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

Slide 6 - Project Schedules

The document discusses the principles of applied software project management, focusing on project definition, planning, scheduling, and metrics. It emphasizes the importance of managing performance, time, cost, and scope (PCTS) effectively, along with the use of tools like Work Breakdown Structure (WBS) and Gantt charts. Additionally, it highlights the significance of evaluating project outcomes and learning from challenges to improve future projects.

Uploaded by

Miguel3796
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 41

Applied Software Project Management

Applied Software Project


Management
Project Schedules

http://www.stellman-greene.com 1 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Definition of a project
A completion of work which must satisfy
performance, time, cost, and scope
(PCTS) a multiple constraints or requests
Precise scope is a must
www.standishgroup.com
Only 17% software projects meet PCTS
 80 billion dollars are wasted on problematic
software project per year

Andrew Stellman & Jennifer Greene


Applied Software Project Management

C=f(P,T,S)
P = performance
T = time
S= scope C
C P
C = cost P
S
S

T T

Andrew Stellman & Jennifer Greene


Applied Software Project Management

PTCS
In principle of other discipline, the transformation
between P (performance),T(time), C(cost) is true
To software development, the transformation is
not true.
If you think you can add more people (more
cost) and you can reduce the completion time.
That is not true at all in software engineering
It is the well-known man-month mythic
More software engineering efforts , more true
the principle

Andrew Stellman & Jennifer Greene


Applied Software Project Management

What is project planning


Project planning is to answer questions
Do what?
How to do it?
Who is in charge ( 誰負責)
When to finish
At what cost
What kind of performance

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Using the work break down


structure (WBS)
A project needs to answer
When to complete
Complete what
What is the cost
The only way to achieve this objective is
to break down the work and then
estimating
Fact: estimating error is inevitable
Andrew Stellman & Jennifer Greene
Applied Software Project Management

WBS
In software project, typically we break
down the work from project ->
subsystem -> modules
When to stop? When a module is not too
complicated but also not too detailed?
A general rule is: until you can precisely
estimate its cost and time
Have we done a good job?

Andrew Stellman & Jennifer Greene


Applied Software Project Management

What is a project schedule?


The project schedule is a calendar that
links the tasks to be done with the
resources that will do them.
Before a project schedule can be created,
the project manager must have a work
breakdown structure (WBS) and estimates.
The schedule is part of the project plan.

http://www.stellman-greene.com 8 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Scheduling Project Work


Grantt chart (bar chart)
1950-1960
CPM (Critical Path Method)
PERT( Program evaluation and review
techniques) – U.S. NAVY, add probability

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Producing a workable
schedule
using critical path method leverage float
labor, or resources
你必須先找出 critical path 然後才能知道你有哪些人力,時間,
資源,是浮動的,可以調配

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

ES = early start ( 最快開始時間)


LS = late start ( 最遲開始時間)
EF = early finish ( 最快完成時間)
LF = late finish ( 最遲完成時間)
DU= duration 作業時間

Andrew Stellman & Jennifer Greene


Applied Software Project Management

forward pass computation


and
backward pass computation

compute ES, EF from the beginning of the


network
compute LS, LF from the end to beginning

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

critical task – ES=LS EF = LF


critical path – the path constituted by
critical task
floating task – the task has a time
buffer
zone between EF and LF

Andrew Stellman & Jennifer Greene


Applied Software Project Management

comments
a reminder: the time in the network is
estimated time. Typically, we will loosen
the estimated time.
people assigned to tasks in critical path
must be very cautious not to delay the
whole project
if all the tasks are critical task – allowing
no room for adjustments, no flexibility

Andrew Stellman & Jennifer Greene


Applied Software Project Management

長條圖

Andrew Stellman & Jennifer Greene


Applied Software Project Management

分配作業資源 and level resource


過渡使用資源案例

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

This constraints make


leveling resources
impossible

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Leveling resources
when leveling resources is impossible
the only way is
get more labor resource
or change C = f (P,T,S)
• time critical leveling
– fix time and let software find a possible leveling
• resource critical leveling
– fix resource, allow time to be increased

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Andrew Stellman & Jennifer Greene


Applied Software Project Management

資源有效性 (availability)
一般而言人的有效性不會超過 80 %
一天工作 8 小時大概只有 6 個小時真的有效
20 %花在 PDF
• P : personal 個性
• F : fatigue 疲勞
• D : delay 延遲,或等候下一步的訊息

80% 的有效性通常指作業員
研究顯示,腦力工作的人員比 50 %還低
了解參與專案人員的有效性十分重要,否則一定會有大災難

Andrew Stellman & Jennifer Greene


Applied Software Project Management

Scheduling concepts:
Effort vs. Duration
Effort represents the work required to perform a task.
 Effort is measured in person-hours (or person-days, person-
weeks, etc.)
 It represents the total number of hours that each person
spent working on the task.
Duration is amount of time that elapses between the
time the task is started and the time it is completed.
 Duration is measured in hours (or days, weeks, etc.)
 It does not take into account the number of people
performing the task

http://www.stellman-greene.com 27 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Scheduling concepts:
Slack and Overhead
Slack is the amount of time which any of the tasks can be
delayed without causing the due date of the final task in the
sequence to be delayed as well.
 A tight schedule has very little slack; a delay in any task will cause
a delay in the due date
 Parkinson’s Law: “Work expands so as to fill the time available for
its completion.”
Overhead is any effort that does not go to the core activities of
the task but is still required in order for the people to perform it
—a sort of “real world” cost of actually doing the work.
 Two people performing a task will require more effort than one
person doing the same task
 Assigning two people to the task requires more effort, but the task
has a shorter duration

http://www.stellman-greene.com 28 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Allocate resources
For each task in the WBS, one or more
resources must be assigned
Choose person or people for each task
based on qualifications, familiarity and
availability
Take overhead into account when
calculating the duration of each task

http://www.stellman-greene.com 29 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Identify dependencies
A task has a dependency if it involves an
activity, resource or work product which is
subsequently required by another task
Tasks may have dependencies because
they require the same resource

http://www.stellman-greene.com 30 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Identify dependencies (continued)
 Every dependency has a predecessor, or a task that must
be begun, in progress, or completed, for another task to
begin
 Identify the type of predecessor for each dependency

http://www.stellman-greene.com 31 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Create the schedule
Most project
schedules are
represented using a
Gantt chart
The Gantt chart
shows tasks,
dependencies and
milestones using
different shapes

http://www.stellman-greene.com 32 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Reconcile the schedule with the
organization’s needs
Once resources are allocated to each task, a final
date can be calculated
If this date is unacceptable, the project plan must
change
Either additional resources must be allocated to
the project or the scope must be cut down
Brooks’ Law: “Nine women cannot have a baby in
one month.”
• In other words, some tasks can only be done by one
person, no matter how critical they are.

http://www.stellman-greene.com 33 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Add review meetings to the schedule
Progress reviews are meetings held regularly to
check the progress of a project versus it's
scheduled progress.
Milestone reviews are meetings which the project
manager schedules in advance to coincide with
project events.
• The most common way for project managers to handle
milestone reviews is to schedule them to occur after the
last task in a project phase (such as the end of design or
programming).

http://www.stellman-greene.com 34 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Building the project schedule


Step 4: Optimize the schedule
 The critical path is the sequence of tasks that represent the
minimum time required to complete the project.
• If a task is only on the critical path when delaying that task will
delay the project.
• Allocating resources to tasks on the critical path will reduce the
project schedule; allocating them to other tasks will have less
effect.
 A resource is over-allocated if more than 100% allocated to
multiple tasks simultaneously
• If any resource is over-allocated, it means that there is a
dependency between two tasks which was not discovered.
• When this happens, the schedule is guaranteed to be
inaccurate. Find and fix over-allocated resources.

http://www.stellman-greene.com 35 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Don’t abuse buffers


A buffer is a task added to the schedule with no specific
purpose except to account for unexpected delays.
 This practice involves either adding extra tasks or padding existing
tasks at strategic points in the schedule where overruns are
“expected”.
 Buffers can be useful:
• On a year-long project, every programmer will take two weeks of
vacation
• Buffers can be used to account for this known delay
 Buffers are often abused
• The idea that overruns are expected means that there is an implicit
assumption that the estimate is incorrect.
• Buffers should not be used to add time to compensate for an inaccurate
estimate.

http://www.stellman-greene.com 36 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Project metrics
The baseline is the version of the schedule
that has been approved
The schedule will change based on the actual
work done by the project team.
When the deadline of the revised schedule is later
than that of the baseline, the project has slipped.
Variance is the difference between the
estimated effort in the baseline and the actual
effort performed by the team.

http://www.stellman-greene.com 37 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Project metrics
Earned value management tracks the project
by considering effort “earned” against a
budget only after it has actually been
performed
The budgeted cost for work scheduled (BCWS) is
the estimated effort of the actual tasks that appear
on the schedule to date.
The actual cost of work performed (ACWP) is the
effort spent on the tasks in the schedule that have
actually been completed by the development team
members.
Variance = BCWS – ACWP

http://www.stellman-greene.com 38 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Project metrics
The cost performance index is used to compare projects with
each other or to compare phases within a project
 CPI is calculated by dividing BCWS / ACWP (budgeted cost for
work scheduled/actual cost for work performed) and multiplying by
100 to express it as a percentage.
 A CPI of 100% means that the estimated cost was exactly right and
the project came in exactly on budget.
 A CPI under 100%, the work cost less effort than planned; a CPI
greater than 100% means that the estimate was not adequate for
the work involved.
• For example, if the programming tasks took twice as long as estimated
but every other type of task in the project took less time than estimated,
the total variance for the project might still be low. However, the
problem can still be pinpointed by calculating the CPI for each phase of
development.

http://www.stellman-greene.com 39 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Real Project Evaluation


When a project is finished, it is important to
evaluate the project
If a schedule does not run as planned, the
problem could be
 Programmer’s skill does not meet the expectation
 PM has problem in create and analyze a WBS
which make schedule impossible to achieve
Some real technical difficulties do occurs

http://www.stellman-greene.com 40 Andrew Stellman & Jennifer Greene


Applied Software Project Management

Dig the truth and story


As a higher-level PM, you just need to
dig the story when a schedule does not
work as planned.
Be aware that it becomes a 批鬥大會
Some of these findings can be collected
and improved in your next project.

http://www.stellman-greene.com 41 Andrew Stellman & Jennifer Greene

You might also like