Session 11 & 12 Time Cost Tradeoff - Transmission Line Project & Optimal Crashing
Session 11 & 12 Time Cost Tradeoff - Transmission Line Project & Optimal Crashing
Rohit Kapoor
Direct Cost Increment
900
800
780 Crash A & B by 1
700 Month each
600
560
500 Crash F & G by 2
Months each
Direct Cost
400
Increment
300
200 Crash D by 2 Months
160
100
11 12 13 14 15 16
Project Duration
Further …
• Lets say Indirect cost per day, Rs. 10,00,000/Month?
• What is total cost curve and optimal duration?
Project Direct Cost Indirect Cost Total Cost
Duration
16 1,32,00,000 1,60,00,000 2,92,00,0000
A4
D2 E7
1
B4
2 4
Completion
Activity Preceeding Times (in
Symbol Activity Description Activity Weeks)
A Site Excavation - 2
B Foundations A 3
Underground
C Utilities A 7
D Plumbing: Stage 1 B 4
E Framing B 5
F Roofing E 3
G Electrical Work F 3
H Inferior Walls D, G 4
I Plumbing: Stage 2 H 2
J Exterior Finishing F 6
K Landscaping C, I, J 2
A Situation
Normal Time
(Days)
Activity A B C D E F G H I J K
Time 10 15 35 20 25 15 15 20 10 30 10
Cost (Rs. 00000s) 2 3 10 6 12 9 6 7 3 5 3