CEE 3348 Lesson 4 Unit 1
CEE 3348 Lesson 4 Unit 1
ENGINEERING CASES
CEE 3348a
Lesson #4 – Project Planning & Scheduling
Lecturer: Kevin Lawrence McGuire P. Eng.
Today’s Lecture
This timing dictates that we may need to eat into some of our
Laboratory hours with lecturing in order to complete all we
need to do this week.
If you apply the voice over for these slides, ignore any
references to laboratories. The voice over is old. Follow the
schedule for labs provided to you in BrightSpace or any other
directions provided by the instructor.
What is Construction Project
Management ?
It is broken into:
Concise
Bar (Gantt) Charts
TE = [A + 4(B) + C] / 6
PERT – Enhance Expert Judgment
Technique - Example
Determination of resources
Activity on Node
Relationships:
Finish-Start
Start-Start
Finish-Finish
Start-Finish
Project Investigation
Investigation is required prior to preparing a network
schedule so that all team members have complete
understanding of the objective
Decomposition
Subdividing
work packages into smaller, more manageable
components called schedule activities
Involving
team members in the decomposition can lead to better
and more accurate results
Critical Path
Longest path through network
Determines the duration of the project
Critical Activities
Activities that lie along the critical path
By definition, critical activities cannot be delayed without
extending the project duration
No floats
If the total project duration is extended due to a delay of an
activity, then the activity is critical
Project Planning
Shortening the duration of an activity on the critical
path will shorten the duration of the whole project
Milestone
A key event in the life of a project
Not an activity – does not consume resources/time
Example continued
Network Diagram - Project Activity
Network Showing Project Durations
Example continued
Network Diagram – Rules when using
the Forward Pass
Example continued
Network Diagram - Activity Network
with Forward Pass
Example continued
Network Diagram - Rules when using
the Backward Pass
Example continued
Network Diagram - Activity Network
with Backward Pass
Example continued
Network Diagram - With Critical Path
and Slack Times Calculated
Example concluded
Creating a Project Schedule
Step 1 – Work Breakdown Structure
Historical data
Subcontractors
Creating a Project Schedule
A
FF - Finish to Finish
FF Task B has a Finish to Finish Relationship with
Task A. (A must finish before B can finish).
B C
A SS - Start to Start
SS Task B has a Start to Start Relationship with
Task A. (A must start before B can start.)
B C
Relationships between activities
Basic Predecessor/Successor Relationship Types (cont.)
Lag
FS - Finish to Start with Lag
}
A B C
Task B has a lagging FS Relationship with
Task A. (A must finish x days before B can start)
FS
Lag
}
A
SS SS - Start to Start with Lag
Task B has a lagging SS Relationship with TaskA.
B C
}
fs
1 Month
fs Task C Task D
fs
2 Months 1 Month
Task B
Task C
Task D
Critical Path
Scheduling – Float Representation
Float or Slack
al Float is the amount of float before the Critical Path is impacte
e Float is the float before the start of the following task is affect
month 0 month 1 month 2 month 3 month 4
Task A Free Float
for Task B
Task B Free Float
for Task B1
Task B1
Task C
Task D
Total Float = Free Float for Task B + Free Float for Task B1
Scheduling – Schedule Report
Tracking Gantt Chart
month 0 month 1 month 2 month 3 month 4
Task A
Task B
C Float
A
Task C
Critical Path
A
is monitored
Projections of
Task D
B key milestones
are analyzed
Task status vs
C baseline is
reviewed.
B
Schedule Slip & Schedule Crash
If the Schedule Slips - How to Resolve it (Schedule Crash)
Analyze the critical path and near critical path activities for
potential concurrency tasks
Crash
Point
Crashed
Cost
Normal
Point
Normal
Crashed Normal
Activity Duration
CRASHING ACTIVITIES – AN EXAMPLE
Sample Project
Normal Crashed
Activity Duration Cost Duration Cost Crashing Cost / day
A 3 days $ 1,000 2 days $ 1,500 $ 500
B 4 days $ 700 2 days $ 1,000 $ 150
C 3 days $ 2,500 2 days $ 4,000 $ 1,500
D 6 days $ 1,500 6 days $ 1,500 N/A
E 9 days $ 3,750 7 days $ 9,000 $ 2,625
F 4 days $ 5,000 3 days $ 7,000 $ 2,000
G 6 days $ 2,550 5 days $ 3,500 $ 950
H 8 days $ 5,500 4 days $ 7,550 $ 513
80
70
60
Project Cost (Thousands)
50
40
30
20
10
0
25 30 35 40 45 50 55 60 65
Duration (Weeks)
Tools to Cover:
What is Required:
Generate a critical (red) path as shown.
Create full schedule with the Work Breakdown Structure & activities shown,
incorporating durations.
What to Use:
Incomplete Schedule (Showing WBS & Activities).
• CPM schedule
• PERT schedule
• Gantt Chart
• Linear balance diagram
• Matrix schedule
Scheduling Sample Questions – cont’d
• CPM schedule
• PERT schedule
• Gantt Chart
• Linear balance diagram
• Matrix schedule
Scheduling Sample Questions – cont’d