Module 5- Pert and Cpm Ppt
Module 5- Pert and Cpm Ppt
INTRODUCTION
NETWORK PLANNING
ESTIMATING TIME
CPM
PERT
Project Management
Project
• A project is an interrelated set of activities that has a definite
starting and ending point and that results in a unique product
or service.
Project management
• Project management is a scientific way of planning, implementing,
monitoring & controlling the various aspects of a project such as time,
money, materials, manpower & other resources.
Network Planning Methods
1)Helpful in Planning.
2)Inter-Relationship of various activities.
3)Cost Control.
4)Minimization of Maintenance.
5)Reduction of time.
6)Control on Idle Resources.
7)Avoiding Delays , interruptions.
Continue..
1)Helpful in planning : Network analysis is
powerful tool for planning , scheduling and
controlling.
2)Inter-Relationship of various activities:
Network analysis creates inter-relationship
and inter dependence of various activities of
project or a programme.
3)Cost Control : In certain cases we can measure
cost of delay in the completion of the project.
This cost can be compared to the cost of the
resources required to carry out various
activities at various speed.
4)Minimization of Maintenance: Network
analysis helps the management to minimize
the total maintenance time.
Project
scheduling by
PERT - CPM
• Planning
• Scheduling
• Controlling
Project Planning : In the project
planning phase, you need to
perform the following activities
• Identify Tasks
• Determine Resources Requirement
• Estimate Cost and Time
• Specify inter-relationship between Tasks
• Develop network Diagram
Identify various tasks or work
elements to be performed in
the project
• Once the planning phase , scheduling of the project is when each of the
activities requried to be performed , taken up.
• Estimate the durations of activities.
• To calculate the total project project duration by applying network analysis
techniques.
Project Control
Concepts
• Activity
• Precedence relationship
• Successor
• Event
Guidelines for network diagram
ACTIVITY ON ARC(AOA):
• Uses arcs to represent activities and nodes
to represent events.
• It is Event Oriented.
3
1 2 6 7 8
4 5
DUMMY ACTIVITY
2
2) When two or more activities share the same
precedence activity but not all the precedence are
shared.
1 3 5
2 4 6
ACTIVITY ON NODE(AON):
3) EF-Earliest finish time: equals to the earliest start time for the activity
plus the time required to complete the activity.
4) LF- Latest finish time: the latest time in which the activity can be
completed without delaying the project.
5) LS- Latest start time: equal to the latest finish time minus the time
required to complete the activity.
6) FORWARD PASS:
The early start and early finish times are calculated by
moving forward through the network and considering the
predecessor activities Considers maximum
7) BACKWARD PASS:
The latest start and finish times are calculated by moving backward through the
network.
Considers minimum
8) SLACK TIME:
Slack time for an activity is the difference between its earliest and latest start
time or between the earliest and latest finish time.
Critical path is the path of activities having zero Slack time.
A Simple Project
HISTORY :
It was developed by J.E.KELLY of REMINGTON-RAND
and M.R.WALKER of DU PONT and the emphasis was
on the trade-off between the cost of project and its overall
completion time. The first test was made in 1958,when CPM
was applied to the construction of a new chemical plant.
DEFINITION:
Critical path is the sequence of activities between a project’s
start and finish that takes the longest time to complete.
STEPS IN DETERMINING
CRITICAL PATH
A - 3 300
B A 3 30
C A 7 420
D A 9 720
E D 5 250
F B,C,E 6 320
G F 4 400
H F 13 780
I G 10 1000
Total 4220
4 7
1 2 5 6
3
8
Overhead cost as per the given data- Rs.50
Paths in the network diagram :
A-D-F-G-I = 32
A-D-F-H = 31
A-C-F-H = 29
A-C-F-G-I = 30
A-B-E-F-H = 30
A-B-E-F-G-I = 31
Critical path – A-D-F-G-I = 32
4 7
1 2 6
5
3
8
TIME ESTIMATES
A Initial - 12 16 26 17
design
B Survey A 6 9 18 10
market
C Build A 8 10 18 11
prototype
D Test C 2 3 4 3
prototype
E Redesign B,D 3 4 11 5
ing
F Market E 6 8 10 8
testing
G Set up F 15 20 25 20
productio
n
1 2 4 5 6 7
A-B-E-F-G = 60
A-C-D-E-F-G = 64 (CRITICAL PATH)
Advantages of PERT
• The activities that have slack time and that can lend resources
to critical path activities.
CPM PERT
• CPM works with fixed • PERT works with probabilistic
deterministic time time
• CPM is useful for repetitive and • PERT is useful for non repetitive
non complex projects with a and complex projects with
certain degree of time estimates. uncertain time estimates.