OSHA 500 Steel Erection
OSHA 500 Steel Erection
Final Rule
• The Steel Erection Final Rule was
published on January 18, 2001
• Effective date:
• January 18, 2002
• Painted surfaces provision - 2006
Subpart R – Steel Erection
• Scope
Final Rule
• Metal Buildings
– §1926.750
– §1926.758 Systems-
• Definitions
engineered Metal
– §1926.751
Buildings
• Site Preparation
• (Non-Hoist) Overhead
– §1926.752 Site Layout and
Hazards
Construction Sequence
• Cranes – §1926.759 Falling Object
Protection
– §1926.753 Hoisting and
Rigging • Fall Protection
• Structural Stability – §1926.760 Fall Protection
– §1926.754 Structural Steel (for connectors, deckers,
Assembly and all others
– §1926.755 Column Anchorage • Training
– §1926.756 Beams and – §1926.761 Training
Columns (general and specialized)
– §1926.757 Open Web Steel
§1926.750 Scope
• The standard
covers all
employers
engaged in steel
erection
activities
§1926.750 Scope
§1926.750 Scope
• Choker means a
wire rope or
synthetic fiber
rigging assembly
that is used to
attach a load to a
hoisting device.
Definitions
• Column means a
load-carrying
vertical member
that is part of the
primary skeletal
framing system.
Columns do not
include posts. Column
Post
Definitions
• Connector means an
employee who,
working with hoisting
equipment, is placing
and connecting
structural members
and/or components.
Definitions
• Controlled Decking Zone (CDZ) means an
area in which work may take place without the
use of guardrail systems, personal fall arrest
systems, fall restraint systems, or safety net
systems and where access to the zone is
controlled.
§1926.752 Site Layout, Erection
Plan and Construction Sequence
• Approval to begin
steel erection
• Before steel erection
begins, controlling
contractor provides
steel erector with
written notifications:
– Concrete in footings,
walls is 75% ASTM
cured
§1926.752 Site Layout, Erection
Plan and Construction Sequence
• Steel erection
contractor does
not begin until he
has received
notification from
the controlling
contractor
§1926.752 Site Layout, Erection
Plan and Construction Sequence
• Site layout. The
controlling contractor
shall ensure that the
following is provided
and maintained:
– Adequate access roads
– A firm properly graded
area
§1926.752 Site Layout, Erection
Plan and Construction Sequence
• Pre-planning of
overhead hoisting
operations
• Site-specific erection
plan (Appendix A)
§1926.753 Hoisting and
Rigging
• Pre-shift visual inspection of cranes:
– All controls and drive mechanism
– Safety devices and pressurized lines
§1926.753 Hoisting and
Rigging
• Hooks & wire ropes
• Electrical
• Tires
• Ground conditions
§1926.753 Hoisting and
Rigging
• Hoisting equipment
removed from service
until hazards are
corrected.
• Crane operator has
final call
• “Qualified rigger”
inspects rigging prior
to each shift
• Cannot ride the ball
§1926.753 Hoisting and
Rigging
• Only connectors and
riggers allowed under
loads & loads rigged to
prevent unintentional
displacement
• All loads rigged by
qualified rigger
§1926.753 Hoisting and
Rigging
• Prescribes proper
procedure for multiple
(lifts “christmas-treeing”
“multiple lift rigging
procedure)
• Maximum of 5 pieces
• Only similar type lifted
(no decking bundles)
§1926.753 Hoisting and
Rigging
• Employees trained in
procedure
• Multiple lift assembly rigged
rigged from at
used is that the top least 7
manufactured by a wire down feet
apart
rope rigging supplier
• Crane manufacturer
attached at their
does not prohibit it center of gravity
[.760 (e)(1)] and maintained
level
Typical Multiple
Lift Rigging
Assembly A D
What do you need
to know?
E (shackle)
• How much does
each piece weigh? B
F (hook)
• What size slings?
• What size and type of G
hooks? C H (shackle)
I (hook)
• What size of
shackles?
§1926.754 Structural Steel Assembly
• 8 Floors max.. between
erection floor & uppermost
permanent floor.
• Max 4 floors unfinished
bolting
• Fully decked or nets within
two floors or 30 feet under
erection work
§1926.754 Structural Steel Assembly
• Metal deck
openings turned
down
• Holes cut
immediately prior
to filling
• No shear
connectors on
beams until
walking surface
installed
Shear connectors
installed after
decking has been
installed
§1926.754 Structural Steel Assembly
• Plumbing up to
ensure stability of
structure
• Installed before
constructions are
placed on structure
• Removed only with
approval of
competent person
§1926.754 Structural Steel Assembly
• No hoisting using bundle straps or bands
• Loose items secured
• Land decking joists according to 757(e)(4)
• Secure at end of shift if necessary
§1926.754 Structural Steel Assembly
•Holes covered
•Covers secured
•Twice anticipated load
•Marked ‘Cover’ or ‘Hole’
• Perimeter
cables required
as soon as
decking is
installed
§1926.760 Fall Protection (cont.)
• Between 15 and 30
feet: Fall protection
required for all with
exceptions for:
– Deckers in controlled
decking zone (CDZ) and
– Connectors
– Connectors must be
provided and wear
equipment necessary to
be able to be tied-off, or
to be provided with other
means of fall protection
§1926.760 Fall Protection (cont.)
• Controlled Decking Zone (CDZ). A controlled
decking zone may be established in that area of the
structure over 15 and up to 30 feet above a lower
level
§1926.760 Fall Protection (cont.)
CDZ shall not be more than
90 feet wide and 90 feet
deep from any leading edge.
CDZ marked by the use of
control lines
Unsecured decking in a
CDZ 3,000 square feet
max..
§1926.760 Fall Protection (cont.)
• Guardrail systems
and safety net
systems must meet
1926.502 criteria.