PPAP
PPAP
PPAP ?
The purpose of PPAP is to determine if
all customer engineering design record
and specification requirements are
properly understood by the organization
and that the manufacturing process has
the potential to produce product
consistently meeting these
requirements during an actual
production run at the quoted production
Submission Requirements :
– The organization shall obtain approval from the
authorized customer representative for :
1. A new part or Product
2. Correction of a discrepancy on a previously submitted part.
3. Product modified by an engineering change to design records,
specifications, or materials.
4. Any situation given below :
– Production from new or modified tools ,dies, molds, patterns
etc.,
– Production Ramp-up , Re-arrangement of existing tooling or
equipment.
– Production from tooling and equipment transferred to a
different plant site or from an additional plant site.
– Change of organization .
– Product produced after the tooling has been inactive for
volume production for twelve months or more.
– Product or Process changes at sub-vendors .
– Change in test or inspection method – new technique.
Significant Production Run :
4.Design FMEA :
– To be submitted by the organization , if it is
design responsible.
7.Control Plan :
– The organization shall have control plan that
defines all methods used for process control
and complies with customer-specified
requirements.
Criteria of acceptance :
9.Dimensional Results :
– Evidence of dimensional results indicate
complience with the Design records and
control plan.
– Dimensional results of each unique mfg
process e.g., cells ,cavities ,molds or dies.
10.Records of Material /Performance
Test Results :
– The organization shall have records of
material and /or performance test results for
tests specified on the design record or
control plan.
− Material test & Performance Test result shall
indicate and include :
• The design record change level of the parts.
• Engineering change document if the change is not
incorporated in the design record.
• The number ,date ,and change level of the specifications to
which the part was tested.
• The date on which the testing took place.
• The quantity tested.
• The actual results.
• organization name /code.
11.Initial Process Studies :
Results Interpretation
Index > 1.67 The process currently meets the
acceptance criteria.
Index < 1.33 The process does not currently meet the
acceptance
Criteria.
15.Master Sample :
– The organization Shall retain a master sample for the same period
as the PPAP records or as per the customer requirement.
– Master sample shall be identified and shall show customer approval
date on the sample .
– For multi cavity dies , the organization shall retain a master for
each cavity unless otherwise specified by the customer.
16.Checking Aids :
– The organization Shall certify that all aspects of the checking aid
agree with part dimensional requirements.
– Measurement System analysis e.g., gauge R&R ,accuracy, bias,
linearity and stability studies shall be conducted in compliance to
customer requirements.
17.Customer Specific Requirements :
– The organization shall have the records of all customer
specific requirements.
Interim Approval :
− Interim approval permits shipment of material for production
on a limited time or piece quantity basis.
PPAP Rejected :
− PPAP may be rejected when :
• Failed Production Trail Run .
• PPAP submission does not meet customer requirements based
on the production lot from which it was taken and /or
accompanying documentation. In such cases the submission
and /or process shall be corrected to meet customer
requirements.
.