Week 4 Formation of Ship Building Agreement
Week 4 Formation of Ship Building Agreement
SHIPBUILDING
AGREEMENT
NA 10 : CONTRACT AND SPECIFICATION
Mortgage
Direct Subsidy Indirect Subsidy
Guarantee
• Ensures loan • Government • Cost-sharing
security for ship covers a agreements to
construction. percentage of reduce shipyard
progress expenses.
payments.
the
the
provision of
the flushing provision of
all working
of all piping all fuel for
fluids in
testing
systems
A. The BUILDER guarantees and warrants that the subject vessel shall be
constructed in accordance with Local Classification of the work provide by the
BUILDER in the General Arrangement plan and Outline Specifications
mentioned in Annex "A" and "B" above, unless otherwise altered or changed by
the parties concerned.
C. As soon as the BUILDER turns over the vessel to the OWNER, any or all
defects or problems suffered which are attributable to natural causes or the
natural wear and tear of the vessel shall be for the account of the OWNER.
B. The payment of the contract price agreed by the parties shall be made by the OWNER under the
following schedule:
15% - Upon Mobilization, Mold Lofting, Start of Fabrication of Frames
15% - Upon Keel Laying, Erection of Mid section transverse bulkheads, double bottom tank.
10% - Upon Erection of 50% of Bottom Frames, 75% of Transverse Bulkheads
10% - Upon Erection of 30% Side Plate, 50% of Car Deck Frames, 50% of Engine Room Framing
10% - Upon 50% of Car Deck Plating, 30% of forward and aft section
10% - Upon start of Fabrication of Superstructure Framing up to Promenade Deck
10% - Upon Erection of Superstructure Sides & Deck Plating
5% - Upon completion of Hull Plating & Framings
5% - Upon completion of Superstructure up to Navigational Bridge Deck
5% - Upon Launching
5% - 15 days after delivery & acceptance
D. Any delay in the payment shall entitle the BUILDER to assess liquidated damages
at the rate of ONE THOUSAND PESOS (P1,000.00) per day of delay for each
corresponding billing within the first thirty (30) days and in the sum of TWO
THOUSAND PESOS (P2,000.00) per day after the first thirty days, computed starting
from the date each of the delayed payment becomes due, taking into account the 7-day
allowance indicated in the immediately preceding paragraph. Such liquidated damages
shall be separate from and in addition to the storage charges that may become due
under Article IV, section B, hereof. In addition, the BUILDER has the option to cause
the temporary stoppage of work in the construction until payment is made and resume
the work only after actual and full payment of the amount stated in the billing.
F. In the event that the BUILDER opted to temporarily stop the work and wait
till the OWNER cause valid payment, the period during which there was no
actual work shall be added to the period granted to the BUILDER to complete
the construction.