Project+Cost+Management 2
Project+Cost+Management 2
MANAGEMENT
Prepared by:
2. Performance measurement
Performance measurement techniques help assess the
magnitude of any variations that do occur. Earned Value
Management (EVM) is especially useful for cost control. An
important part of cost control is to determine what is causing the
variance & to decide if the variance requires corrective action.
3. Earned Value Management (EVM)
3 independent variables:
3.1 Planned value – the physical work schedule to be performed, including
the estimated value of this work (previously called the Budgeted Costs of Work
Scheduled, BCWS), as compared against;
3.2 Earned value – physical work actually accomplished, including the
estimated value of this work (previously called the Budgeted Costs of Work
Performed, BCWP);
3.3 Actual cost incurred – to accomplish the Earned Value; the relationship
of (2) Earned Values less (1) Planned Value constitutes the Schedule Variance
(SV). The relationship of (2) Earned Value less (3) Actual Cost constitutes the
Cost Variance (CV) for the project.
2. Budget updates
Changes to an approved cost baseline.
3. Corrective actions
Anything done to bring expected future project performance in
line with the project plan.
4. Estimate at completion (EAC) (Cost Forecast – PMBOK)
Forecast of likely total projects costs based on project performance & risk
quantification.
5. Project closeout
Processes and procedures should be developed for the closing or canceling
of project.
6. Lessons learned
The cost of variances, the reasoning behind the corrective action chosen, &
other types of lessons learned from cost control should be documented so
that they become part of historical database for both this project & other
projects of the performing organizations.
Reference: