Uga Project Progress-End of August (1)

The document outlines the proposed additions and alterations to the UGA Hallowella Holiday Bungalow, detailing the project status, contract specifics, and overall progress. The project, valued at approximately 119 million SLR, is set to commence on March 21, 2024, with a revised completion date of October 30, 2024. Key issues include delays in architectural design finalization and client material supply.

Uploaded by

gobi.rdc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

Uga Project Progress-End of August (1)

The document outlines the proposed additions and alterations to the UGA Hallowella Holiday Bungalow, detailing the project status, contract specifics, and overall progress. The project, valued at approximately 119 million SLR, is set to commence on March 21, 2024, with a revised completion date of October 30, 2024. Key issues include delays in architectural design finalization and client material supply.

Uploaded by

gobi.rdc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 23

PROPOSED ADDITION AND ALTERATION

TO THE EXISTING FOR UGA


HALLOWELLA HOLIDAY BUNGALOW
Status of the project
SITE LAYOUT
PROJECT THE PROPOSED
LOCATION SITE
 Main house building (1 Story/ 729m2)
 Swimming pool( 79.5m2)
 Back of House (1 Story/ 147.87m2)
 External works.
Project Details
PROPOSED ADDITION AND ALTERATION TO THE EXISTING FOR
Contract Name
UGA HALLOWELLA HOLIDAY BUNGALOW.
119,180,557.23 SLR. (Rupees One Hundred Nineteen
Contract Value
Million One Hundred Eighty Thousand Five Hundred Fifty-
Seven and Cents Twenty-Three)
Employer UGA Escape (Pvt) Ltd.

Engineer Resource Development Consultant (Pvt) Ltd.

Contractor Kemyo Pvt Ltd

Commencement Date 21/ March 2024

Completion Date 21/ Sep 2024

Original Contract Duration 180 calendar days

Revised Completion Date 30/Oct 2024

Liquidated Damages

Amount of Advance Payment Paid

Defects Notification Period 1 year


Organization Chart- Consultant
Staff
CEO

Mr. Samitha

Struc.Eng MEP Eng

Gobidan Wijesooriya

QS TO MEP TO

Dilshan Gayan Kumara


Overall progress

1. Overall Physical Previous Cumulativ


Item Progress
August e
Cumulative
Planed %
Main House 60% 35% 95%

Actual %
48% 42% 90%

Swimming pool Planed %


23% 27 % 50%

Actual % 18% 23% 41%

For the physical progress, considered work done Only ( 101 million)
Comparison of Actual Physical Progress with
Planed Physical Progress
100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%
Main House Swimming pool

Planned 41%
Status of NCR/QOR
QOR/NCR Issued nos Open Closed
NCR 41 6 35
QOR 11 3 8

QOR-Quality observation report


NCR-Non conformality Report
 Issues

 Finalization of Architectural Design delays.

 Delays in client supply materials.


THANK YOU !