Uga Project Progress-End of August (1)
Uga Project Progress-End of August (1)
Liquidated Damages
Mr. Samitha
Gobidan Wijesooriya
QS TO MEP TO
Actual %
48% 42% 90%
For the physical progress, considered work done Only ( 101 million)
Comparison of Actual Physical Progress with
Planed Physical Progress
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
Main House Swimming pool
Planned 41%
Status of NCR/QOR
QOR/NCR Issued nos Open Closed
NCR 41 6 35
QOR 11 3 8